SW4210401_STORMWATER_CALCS_SAND_FILTER_UNDERGROUND_20210426
BROWN APARTMENTS BOONE, NC HYDROLOGIC AND HYDRAULIC ANALYSIS REPORT BREC •�ti Prepared By: Prepared For: Project Site: BREC, P.A. Kent Brown 599 Old US 421 South 1520 Meadowview Drive Boone, NC 28607 Wilkesboro, NC 28697 NCBELS Firm #C-3448 (336) 844-4088 justin@brec.biz 15 April 2021 CARo /''% O9-'FEsSIc ?.•moo '!' �•.-9 SEAL - 035736 = %`�G'•�NG�NE��'•G�: Justin Church, PE Principal Engineer BREC, P.A. Brown Apartments 1 Table of Contents 1.0 General Information........................................................................................3 2.0 Methodology...................................................................................................3 2.1 Curve Number Calculations 3 2.2 Time of Concentration Calculations 4 2.3 Rainfall Data 5 2.4 Pipe Design 5 2.4.1 Outlet Design 6 2.5 Hydrology Calculations 7 2.6 Modified Curve Number Calculations 7 2.7 Sand Filter Design 8 2.7.1 Chamber and Filter Sizing 8 2.7.2 Underdrain Sizing 8 3.0 Results ..........................................................................................................10 Appendix.............................................................................................................11 Post -construction First Flush Post -construction 1 Year, 24 Hour Post -construction 100 Year, 24 Hour List of Figures Figure 1 - System Storage of First Flush............................................................10 List of Tables Table 1 - Pre -Construction Drainage Area............................................................3 Table 2 - Post -Construction Drainage Areas........................................................4 Table 3 - Pre -Construction ToC............................................................................4 Table 4 - Post -Construction ToC...........................................................................4 Table 5 - NOAA Rainfall Depths...........................................................................5 Table 6 - NOAA Rainfall Intensity.........................................................................5 Table 7 - Composite Rational Coefficients............................................................5 Table 8 - Pipe Design Summary ...........................................................................5 Table 9 - Riprap Outlet Stone Sizing.....................................................................6 Table 10 - Riprap Apron Dimensions....................................................................6 Table 11 - Modified SCS Curve Numbers.............................................................7 Table 12 - Post Construction SCM Peak Elevations...........................................10 BREC, P.A. Brown Apartments 2 1.0 General Information This document contains hydrologic and hydraulic calculations demonstrating compliance with post -construction state and local stormwater regulations for the construction of a three story residential apartment building with a 6,044 ft2 footprint at 599 Old US 421 South, Boone, NC. Specifically, regulations for this area require water quality treatment of the first flush (1") storm due to the site being located within the portion of the South Fork New River watershed classified as C+. The construction area is a portion of an existing development that includes a gym/fitness center and parking. The building footprint is the only added impervious. Post construction stormwater requirements will be satisfied with a below ground sand filter which is approved by NCDEQ as a primary stormwater control measure (SCM). 2.0 Methodology One pre -construction drainage area and one post -construction drainage area covering the building pad area was identified. All net proposed impervious area is routed to the SCM for treatment prior to discharge. 2.1 Curve Number Calculations Composite SCS curve numbers were calculated as weighted averages using values of 74 for grass coverage, 70 for wooded areas, and 98 for impervious surfaces. Design values were based on HSG C soils as they are the majority. For pre -construction drainage areas, the composite curve number is calculated as: (Aimp x 98 + Agrass x 74 + Awooded x 70) CNComhpre Atotal Table 1 - Pre -Construction Drainaae Area Name Atotal (acres) Aimp acres Agrass acres Awooded (acres) CNcom ppre PRE-CONA 0.17 0 74.0 0 74.0 For post -construction drainage areas, the composite curve number is calculated as: CNcompositepost (Aimp x 98 + Agrass x 74 + Awooded x 70) Atotal BREC, P.A. Brown Apartments 3 Table 2 - Post -Construction Drainage Areas + Routed through SCM prior to discharge. 2.2 Time of Concentration Calculations Time of concentration values for vegetated drainage areas were evaluated using the segmental equations. All majority impervious drainage areas less than one acre were assigned a design time of concentration value of five minutes. Tcsegmental (hr) = Tsheet + Tscf 0.007(nl)0.8 Tsheet = 2S0.4 2 n = Manning's coefficient PZ = 2 yr, 24 hr rain f all (in) ft S = slope ( ) t f l Tscf 3,600V ft 1 V = shallow concentrated flow velocity (S) Table 3 - Pre -Construction ToC Table 4 - Post -Construction ToC See Table 15-3 of USDA NRCS NEH for shallow concentrated flow velocity equations. BREC, P.A. Brown Apartments 4 Name Atotal (acres) Aimp acres Agrass acres Awooded (acres) CNcom pnost POST-CON:1+ 0.17 0.17 0 0 98.0 Name Slope Tc—talc Tc—assumed ;Length t t min min PRE-CON:1 - - - Name Length S10�7e Tc—talc Tc—assumed t t min min POST-CON:1 - - - 5 2.3 Rainfall Data Rainfall data was taken from NOAA Atlas 14, Volume 2, Version 3 for Stokesdale, NC. Rainfall depths for each design storm are summarized below. Table 5 - NOAA Rainfall Deaths Storm Rainf all Depth in First Flush 1.00 1 Year, 24 Hour 3.72 100 Year, 24 Hour 10.90 Table 6 - NOAA Rainfall Intensitv 10 Year Storm Duration min Rainfall Intensity in/hr 5 7.48 2.4 Pipe Design A composite post -construction rational coefficient was also assigned to each post construction drainage area as needed for pipe design. The composite rational coefficients were calculated using individual coefficients of 0.95 for impervious surfaces, 0.20 - 0.30 for grass surfaces, and 0.15 for wooded areas in HSG C soils. Ccomp — Almp x 0.95 + Agrass x (0.20, 0.30) + Awooded x 0.15 Atotal Table 7 - Composite Rational Coefficients ft3 Name CComp Q10 s POST-CONA 0.95 1.19 The 10 year rational discharges were used to size pipes by solving Manning's equation iteratively for the normal depth. Table 8 - Pine Design Summary NAME DIA (in) Qdesign (f't3S) 1 t Vdesign() s PIPE-1 15 1.2 3.9 See Appendix for complete pipe design table. BREC, P.A. Brown Apartments 5 2.4.1 Outlet Design Outlet design for NCDOT-PIPE-1, PIPE-4, PIPE-5, and PIPE-9 was taken from Chapter 10 of HEC-14. Riprap D50 was calculated as: 4 D50 = 0.21) Qdesign3 ( D ) (jgD2.5) TWWhere, D50 = riprap size, (f t) ft3 Qdesign = Design discharge — s D = Pipe diameter, (f t) TW = Tailwater depth, (f t) g = gravitational acceleration (32.2 t sZ) Substituting the corresponding pipe diameters and design discharges into the equation above for PIPE-1 yields: Table 9 - Ri ra Outlet Stone Sizing NAME DIA (ill) Qdesign (A minimum D50 of 5 inches was chosen for each pipe which corresponds to NCDOT Class A stone. Given the design D50, the dimensions of the apron were taken from Table 10.1 equations from HEC 142. La = Apron length (f t) = 4D Da = Apron depth (f t) = 3.5D50 W1 = Upper width (f t) = 3D W2 = Lower width (f t) = 3D + (3)La Table 10 - Ri ra Aron Dimensions z http://www.fhwa.dot.gov/engineering/hydraulics/pubs/06086/hec14ch10.cfm BREC, P.A. Brown Apartments 6 f s3 D50calc (ill) D50design (in) NCDOT CLASS PIPE-1 15 1.2 0.7 5 A NAME DIA (in) La (ft) Da (ft) W1 (ft) WZ (ft) PIPE-1 15 5 1.5 3.8 7.1 2.5 Hydrology Calculations The water quality volume (WQV) required to be treated from the first flush was calculated using the Schueler method outlined in the NCDEQ Stormwater Design Manual3. The Schueler method utilizes the following equations: R„=0.05+0.9IA WQV = 3,630RDR„ A Where IA is the impervious fraction of the drainage area, R„ is a runoff coefficient, RD is the rainfall depth, A is the drainage area, and WQ„ is the runoff volume. The following parameters are used for the drainage routed to the SCM. Ia = 1.0 R„ = 0.05 + 0.9(1.0) = 0.95 RD = 1.0 inch A = 0.17 WQV = 3,630(1.0)(0.95)(0.17) = 576 f t3 WQVadj = 0.75WQ„ = 0.75(576) = 432 ft3 2.6 Modified Curve Number Calculations To route the WQV through the SCM, it is necessary to calculate a modified SCS curve number to avoid underrepresenting the first flush. The modified curve number is calculated as follows: CN,,, = 1000/ 110 + 5RD + 10R„ — 10 Rv + 1.25R„RD] The modified curve numbers were used to route the first flush using an SCS 6 hour balanced storm distribution. The remaining design storms were routed with standard curve numbers and an SCS type II 24 hour storm distribution. Table 11 -Modified SCS Curve Numbers Name R CN POST-CON:1 0.95 99.57 2.7 Sand Filter Design The combined area of the sediment chamber and sand chamber is determined from the relationship of the max water depth observed during the water quality event, Hmax, and the adjusted water quality volume. (As + Af )min W QVad j lHmax The design value for Hmax was chosen as 2.0 ft. When coupled with the adjusted water quality volume, WQVadj = 0.75WQV = 432 ft3, the minimum area of the sand filter is calculates as: _ 432 ft3 (As + Af)min — 2 ft = 216 ft2 As + Af provided = 232 ft2 2 2.7.1 Chamber and Filter Sizing The sediment chamber and filter chamber are equally sized. The sediment chamber has a 2 ft permanent pool to assist with maintenance and primary sediment deposition; however, this added volume is not considered in calculations to meet minimum design criteria requirements. The sediment and sand chamber sizes were selected from available sizes of traffic rated pre -cast tanks available at a local provider. This yields a sand media area, Ascend, of 80 ft2 (8 x 10 ft2). Discharge through the sand media is governed by Darcy's Law. Asandk(ha + df) Qsand = df Where, Asand = Sand media surface area (f t2) = 80 ft2 _ da k = Sand media permeability ft (day) 4.0 ft Y df = Sand media depth (ft) = 1.5 ft ha = Average height of water above sand media 2.7.2 Underdrain Sizing Drawdown time is calculated as: BREC, P.A. Brown Apartments 8 WQVdf 576(1.5) t = _ = 25.9 hours k(ha + df)Asand 4.0(1.0 + 1.5)80 Discharge rate is calculated as: WQV 576 f t3 Qunderdrain — t 25.9 0.006 s After applying a safety factor of 10, ft3 Qunderdraintotal 10Qunderdrain = 0.06 t The diameter of a single pipe is calculated as- 3 D = 16 nQunderdraintotal 8 Where, n = Manning's roughness f or pipe S = pipe slope 3 (0.011(0.06) $ D = 16 = 2.8 inches 0.005 Per Table 1 of Section A-5 of the NCDEQ Stormwater Design Manual, use (2) 4 inch pipes. BREC, P.A. Brown Apartments 9 3.0 Results The first flush (1") storm is routed through the SCM and reaches a max storage depth of 1.99 ft which does not exceed the design Hmax = 2.0 ft. The water quality volume is discharged over a period of 26.5 hours. — Storagesystem (POST -CON -ROUTING 2021-04-1s 11'. 51'S4) 765 714 663 612 561 m 510 !n 459 408 357 306 0 5 10 15 20 25 30 35 40 45 Time (hrs) Figure 1 - System Storage of First Flush Table 12 - Post Construction SCM Peak Elevations Storm PEAK ELEVATION ( t) 1 Inch 3075.99 1 Year, 24 Hour 3076.10 100 Year, 24 Hour 3076.20 zLn O1 m w o L w V 0 X Q cn 2 " cr N c-I � O O H W O L LnLL O L O Ln z 1D w J L.L Z co J ( rI = O O O com N > z o ro a m o 00 J N = O m N > d z � o _ m Q - z `n � 0 C LU Q � a� z ¢ a W m Post -construction First Flush BREC, P.A. Brown Apartments 12 Project Description File Name................................................................... POST -CON -ROUTING BALANCED.SPF Project Options FlowUnits................................................................... CFS Elevation Type............................................................ Elevation Hydrology Method ...................................................... SCS TR-55 Time of Concentration (TOC) Method ........................ User -Defined Link Routing Method .................................................. Hydrodynamic Enable Overflow Ponding at Nodes ........................... YES Skip Steady State Analysis Time Periods .................. YES Analysis Options Start Analysis On ........................................................ Feb 09, 2021 000000 End Analysis On ......................................................... Feb 11, 2021 000000 Start Reporting On ..................................................... Feb 09, 2021 00:00:00 Antecedent Dry Days .................................................. 0 days Runoff (Dry Weather) Time Step ............................... 0 01:0000 days hh:mm:ss Runoff (Wet Weather) Time Step .............................. 0 00:05:00 days hh:mm:ss Reporting Time Step .................................................. 0 00:00:05 days hh:mm:ss Routing Time Step ...................................................... 5 seconds Number of Elements Qty RainGages................................................................ 1 Subbas in s.................................................................... 1 Nodes.......................................................................... 4 Junctions 1 Outfalls 1 Flow Diversions 0 Inlets 0 Storage Nodes 2 Links............................................................................ 4 Channels 0 Pipes 1 Pumps 0 Orifices 1 Weirs 1 Outlets 1 Pollutants.................................................................... 0 LandUses.................................................................. 0 Rainfall Details SN Rain Gage Data Data Source Rainfall Rain State County Return Rainfall Rainfall ID Source ID Type Units Period Depth Distribution (years) (inches) 1 BOONE Time Series 1-IN-6HR-BALANCED Cumulative inches 0.00 Subbasin Summary SN Subbasin Area Peak Rate Weighted Total Total Total Peak Time of ID Factor Curve Rainfall Runoff Runoff Runoff Concentration Number Volume (ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss) 1 POST-CON:1 0.17 484.00 99.57 1.00 0.95 0.16 0.35 0 00:05:00 Node Summary SIN Element Element Invert Ground/Rim Initial Surcharge Ponded Peak Max HGL Max Min Time of Total ID Type Elevation (Max) Water Elevation Area Inflow Elevation Surcharge Freeboard Peak Flooded Elevation Elevation Attained Depth Attained Flooding Volume Attained Occurrence (ft) (ft) (ft) (ft) (ft') (cfs) (ft) (ft) (ft) (days hh:mm) (ac-in) 1 SCM-OUTLET Junction 3071.75 3079.00 3071.75 0.00 0.00 0.01 3071.78 0.00 7.22 0 0000 0.00 2 OUTFALL Outtall 3071.50 0.01 3071.53 3 SAND -CHAMBER Storage Node 3074.00 3077.50 3074.00 0.00 0.51 3076.00 0.00 4 SEDIMENT -CHAMBER Storage Node 3072.00 3077.50 3074.25 0.00 0.35 3076.01 0.00 Total Time Flooded (min) 0.00 0.00 0.00 N J ow a � o LL cZ N E N N 1 W F m E E wE 3 wo y W — U) r J O r r O OO M M M 000 000 N V V r r r 000 M M M Ir w m 2 Ir Ir ¢ww =mm U < < F Q Q Z = _ W U U � 0 0 ozz w¢¢ U U U Subbasin Hydrology Subbasin : POST-CONA Input Data Area(ac)..................................................... 0.17 Peak Rate Factor ........................................ 484.00 Weighted Curve Number ............................ 99.57 Rain Gage ID ............................................... BOONE Composite Curve Number Area Soil Curve Soil/Surface Description (acres) Group Number - 0.17 - 99.57 Composite Area & Weighted CN 0.17 99.57 Subbasin Runoff Results Total Rainfall (in) ......................................... 1.00 Total Runoff (in) .......................................... 0.95 Peak Runoff (cfs)........................................ 0.35 Weighted Curve Number ............................ 99.57 Time of Concentration (days hh:mm:ss) ..... 0 00:05:00 Subbasin : POST-CON:1 2.3 2.2 2.1 2 1.9 1.8 1.7 1.6 1.5 1.4 1.3 _- L2 � 1 0 0.9 0.8 0.7 06 0.5 0.4 0.3 0.2 0.1 0.30 0.36 0.34 032 0.3 0.28 0.26 0.24 0.22 0.2 0.18 0.16 0.14 0.12 0.1 008 0.06 004 0.02 Rainfall Intensity Graph 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 Time [hrs] Runoff Hydrograph 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 Time [hrs] Junction Input SIN Element Invert Ground/Rim Ground/Rim Initial Initial Surcharge Surcharge Ponded Minimum ID Elevation (Max) (Max) Water Water Elevation Depth Area Pipe Elevation Offset Elevation Depth Cover (ft) (ft) (ft) (ft) (ft) (ft) (ft) (ft) (in) 1 SCM-OUTLET 3071.75 3079.00 7.25 3071.75 0.00 0.00-3079.00 0.00 0.00 Junction Results SIN Element Peak Peak Max HGL Max HGL Max Min Average HGL Average HGL Time of Time of Total Total Time ID Inflow Lateral Elevation Depth Surcharge Freeboard Elevation Depth Max HGL Peak Flooded Flooded Inflow Attained Attained Depth Attained Attained Attained Occurrence Flooding Volume Attained Occurrence (cfs) (cfs) (ft) (ft) (ft) (ft) (ft) (ft) (days hh:mm) (days hh:mm) (ac-in) (min) 1 SCM-OUTLET 0.01 0.00 3071.78 0.03 0.00 7.22 3071.76 0.01 0 04:59 0 00:00 0.00 0.00 Pipe Input SIN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial ID Invert Invert Invert Invert Drop Slope Shape Diameteror Width Roughness Losses Losses Losses Flow Elevation Offset Elevation Offset Height (ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs) 1 SCM-OUTLET-LINK 10.00 3071.75 0.00 3071.50 0.00 0.25 2.5000 CIRCULAR 15.000 15.000 0.0120 0.5000 0.5000 0.0000 0.00 Flap No. of Gate Barrels No 1 Pipe Results SN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number Condition Occurrence Ratio Total Depth Ratio (cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min) 1 SCM-OUTLET-LINK 0.01 0 05:00 11.06 0.00 1.32 0.13 0.03 0.02 0.00 Calculated Storage Nodes Storage Node : SAND -CHAMBER Input Data Invert Elevation (ft)....................................................................................... 3074.00 Max (Rim) Elevation (ft)............................................................................... 3077.50 Max (Rim) Offset (ft).................................................................................... 3.50 Initial Water Elevation (ft)............................................................................. 3074.00 Initial Water Depth (ft).................................................................................. 0.00 Ponded Area (ft').......................................................................................... 0.00 EvaporationLoss......................................................................................... 0.00 Storage Area Volume Curves Storage Curve : SAND -CHAMBER Stage Storage Storage Area Volume 0 104 0.000 2.5 104 260.00 2.6 1 265.25 3.6 1 266.25 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 Storage Area Volume Curves Storage Volume (ft) 0 40 20 30 40 50 60 70 80 90 100 110 420 430 140 450 460 170 180 490 200 240 220 230 240 260 260 6----,----------------------------------------------------------------------------- v---------------- - - --- 3.6 5---------------- --------- ------------------------ --- ------- -- - - 3.5 4 ---i------ --i---r---7------- i------- ------------------------------- 7 - - - 7-------------- ------ 3.4 3--- '----------- •---'---`---`------- '--- '---`---`-- - - - - 3.3 2 --- --- - -- - -- --- --- --- --- ------ --- --- --- --- - ------ - - - - -- - -- - -- - -- - -- --- --- -- - --- -- 3.2 7---'---'---'---•---'---`---`---`-- '--- '---`---`-- - - - - 3.1 3 --- - -- - -- - -- - -- --- --- --- - - -- -- --- --- --- --- ------- - - - - -- --- - -- - -- --- - -- - -- - - -- -- -- 3 9 ---'---'---'--- I-------`---`---`-- - - - - 2.9 8 - -- *- - - * - -- -- -- - ------------- --- --- --- --- --- --- ------ -- 2.8 6----- -- ------ --- --- --- --- --- --- ------ - 2.6 4 *---*--- -- -- - --- ------------- --- --- --- --- --- --- -- -- 2.4 3-- - - - - -- - ----------------------------------------------------- - - - - ------------ 2.3 2'---"--------'---------------'---'-- '---"---"---'---'--- - - - - 2.2 7-- - - - - -- - - -------------------------------------------- - - -- -------------- ------ 2.1 2 - - - ................................. - - - 2 9-------- - --------------------------------------------------------------------- 1.9 8 ------------------------------------ - - - - 7.8 6---------*--- --------------�--- --- ---- ---- --- --- --- --- --- --- ------ -- 7.6 5-- - - - - -- - - -- ------------------- - - -- --------------------------------------- - - - -- 7.5 4'---"---"---"---'---•---•---'---'-- -----I'---"---'--- - - - - 1.4 3;---;---'---'---;---'---;---;----I--- ------------------------------- 7.3 2---'---'---'---•--- `---`---`-- '---'---'--`---`-- - - - - 1.2 7 --- --- --- - -- - -- - -- --- --- - - -- -- - -- - - -- --- - ---------- -- --- - -- - -- - -- --- --- ------ -- 7.7 9- ------------- ---- ------- - - -- -- ,---,---,------------ ,---,---.---.------ 0.9 7---- ;--- ;- - -T--- -- - -- ;--- ;- - - - - -- - --- -------- --- --- --- --- -- - --- -- 0.7 5 ---------- - -- - -- -- -- ;---;---;-- --- ------- - - -- -- I--- --- --- --- --- - -- - - - --- -- 0.5 3 ;---;-- T--- -- -- ----------- --- ------------- --- --- --- --- --- --- ------ -- 0.3 2--------------------------------------------------------------- 4.2 7 -- ------*--- --- -- --- ------�--- ------------- --- --- --- --- --- --- ------ -- 0.1 4 4 5 40 75 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 Storage Area (ft) Storage Area — Storage Volume Storage Node : SAND -CHAMBER (continued) Outflow Weirs SIN Element Weir Flap Crest Crest Length Weir Total Discharge ID Type Gate Elevation Offset Height Coefficient (ft) (ft) (ft) (ft) 1 EM-SPILLWAY Rectangular No 3076.25 2.25 8.00 0.25 3.33 Output Summary Results Peak Inflow (cfs).......................................................................................... 0.51 Peak Lateral Inflow (cfs).............................................................................. 0.00 Peak Outflow (cfs)........................................................................................ 0.31 Peak Exfiftration Flow Rate (cfm)................................................................. 0.00 Max HGL Elevation Attained (ft)................................................................... 3076.00 Max HGL Depth Attained (ft)........................................................................ 2 Average HGL Elevation Attained (ft)............................................................ 3074.50 Average HGL Depth Attained (ft)................................................................. 0.5 Time of Max HGL Occurrence (days hh:mm).............................................. 0 0459 Total Exfiltration Volume (1000-ft3).............................................................. 0.000 Total Flooded Volume (ac-in)....................................................................... 0 Total Time Flooded (min)............................................................................. 0 Total Retention Time (sec)........................................................................... 0.00 Storage Node : SEDIMENT -CHAMBER Input Data Invert Elevation (ft)....................................................................................... 3072.00 Max (Rim) Elevation (ft)............................................................................... 3077.50 Max (Rim) Offset (ft).................................................................................... 5.50 Initial Water Elevation (ft)............................................................................. 3074.25 Initial Water Depth (ft).................................................................................. 2.25 Ponded Area (ft2).......................................................................................... 0.00 EvaporationLoss......................................................................................... 0.00 Storage Area Volume Curves Storage Curve : SEDIMENT -CHAMBER Stage Storage Storage Area Volume (ft) (ft2) (ft') 0 128 0.000 4.5 128 576.00 4.6 1 582.45 5.6 1 583.45 Storage Area Volume Curves S101a9e Volume (ft) 0 50 100 150 200 250 300 360 400 460 600 660 G.6 5.6 G.4-------------------- '--------'--------•--------'--------'--------- '--------------------------------------------- 6.4 1.2 ---------- ---------- --------'-----------------`--------'---------'--------'--------'--------'-------------- 5.2 6 ------- ----- ------ ------ ------ ----- ----- ----- ----- ------ ------ ---- 5 66 '--------'--------'-------- `-------- '--------- '------------------'--------'--------`----- 4.6 64 ------------------------- -- 4.4 4 -------- -------- -------- -------- -------- ------------------------- -------- -------- ------ ----- 4 1.6 '-------- '--------'--------'--------'--------`-------- '--------- -------- '--------'----- --------- ----- 3.6 1.6 ; ; ;-- - - - - -� ----- 3.6 1.4 '---------- --------'--------'-----------------`--------'---------'--------'------'----------------------- 3.4 1.2 -------------------------------------------------------------------- -------------------------------- 3.2 3 --------------------------------------------------------------------------------------------------- 3 !.8 ----------------------------------------------------------------------------------------------------- 2.8 !.6 -----------------'--------'------------------------------------------------------------------ ------ 2.6 !.4------------------------------------------------ -----------------------------------4--------------- 2.4 !.2 -------------------'--------'------------------------------------------------------------------ ------ 2.2 2 ----- ----- ------ ------ ------ ----- ----- ----- ----- ------ ------ ---- 2 I.6 '--------'--------'--------'--------'-------`--------'---------'--------'--------'--------'--------`----- 1.6 1 -------- -------- -- --- -------- -------- ------------------------- -------- -------- -------- ----- 1 1.6 -------- '--------�------- '--------'--------`-------- '--------- '-------- '--------'--------'-------- ----- 0.6 1.6 ;- - -- - - -; ; � - - - -- 0.6 1.4 ----------------'--------'--------f--------------------------------------------'---------------------- 4.4 1.2---- --------------------------------------------------------------------------------------------- 0.2 0 0 0 5 10 15 20 25 30 35 40 45 50 65 60 65 70 76 80 85 90 95 100 105 110 115 120 125 Storage Area (ft) Storage Area - Storage Volume Storage Node : SEDIMENT -CHAMBER (continued) Outflow Orifices SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation (in) (in) (in) (ft) 1 CHAMBER -CONNECTION Side CIRCULAR No 15.00 3074.00 0.61 Output Summary Results Peak Inflow (cfs).......................................................................................... 0.35 Peak Lateral Inflow (cfs).............................................................................. 0.35 Peak Outflow (cfs)........................................................................................ 0.51 Peak Exfiftration Flow Rate (cfm)................................................................. 0.00 Max HGL Elevation Attained (ft)................................................................... 3076.01 Max HGL Depth Attained (ft)........................................................................ 4.01 Average HGL Elevation Attained (ft)............................................................ 3074.50 Average HGL Depth Attained (ft)................................................................. 2.5 Time of Max HGL Occurrence (days hh:mm).............................................. 0 0457 Total Exfiltration Volume (1000-ft').............................................................. 0.000 Total Flooded Volume (ac-in)....................................................................... 0 Total Time Flooded (min)............................................................................. 0 Total Retention Time (sec)........................................................................... 0.00 Post -construction 1 Year, 24 Hour BREC, P.A. Brown Apartments 13 Project Description File Name .................................................... POST-CON-ROUTING.SPF Project Options Flow Units ................................................... CFS Elevation Type ............................................ Elevation Hydrology Method ....................................... SCS TR-55 Time of Concentration (TOC) Method ........ User -Defined Link Routing Method ................................... Hydrodynamic Enable Overflow Ponding at Nodes ............ YES Skip Steady State Analysis Time Periods ... YES Analysis Options Start Analysis On ........................................ Feb 09, 2021 000000 End Analysis On .......................................... Feb 11, 2021 000000 Start Reporting On ...................................... Feb 09, 2021 000000 Antecedent Dry Days .................................. 0 days Runoff (Dry Weather) Time Step ................ 0 01:0000 days hh:mm:ss Runoff (Wet Weather) Time Step ............... 0000500 days hh:mm:ss Reporting Time Step ................................... 0000005 days hh:mm:ss Routing Time Step ...................................... 5 seconds Number of Elements Qty RainGages ................................................. 1 Subbas in s.................................................... 1 Nodes........................................................... 4 Junctions 1 Outfalls 1 Flow Diversions 0 Inlets 0 Storage Nodes 2 Links............................................................. 4 Channels 0 Pipes 1 Pumps 0 Orifices 1 Weirs 1 Outlets 1 Pollutants.................................................... 0 LandUses ................................................... 0 Rainfall Details SN Rain Gage Data Data Source Rainfall Rain State County Return Rainfall Rainfall ID Source ID Type Units Period Depth Distribution (years) (inches) 1 BOONE Time Series 1YR-24HR Cumulative inches North Carolina Watauga 1 3.72 SCS Type II 24-hr Subbasin Summary SN Subbasin Area Peak Rate Weighted Total Total Total Peak Time of ID Factor Curve Rainfall Runoff Runoff Runoff Concentration Number Volume (ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss) 1 POST-CON:1 0.17 484.00 98.00 3.72 3.48 0.58 0.81 0 00:05:00 Node Summary SIN Element Element Invert Ground/Rim Initial Surcharge Ponded Peak Max HGL Max Min Time of Total ID Type Elevation (Max) Water Elevation Area Inflow Elevation Surcharge Freeboard Peak Flooded Elevation Elevation Attained Depth Attained Flooding Volume Attained Occurrence (ft) (ft) (ft) (ft) (ft') (cfs) (ft) (ft) (ft) (days hh:mm) (ac-in) 1 SCM-OUTLET Junction 3071.75 3079.00 3071.75 0.00 0.00 0.81 3072.06 0.00 6.94 0 0000 0.00 2 OUTFALL Outtall 3071.50 0.81 3071.73 3 SAND -CHAMBER Storage Node 3074.00 3077.50 3074.00 0.00 0.81 3076.35 0.00 4 SEDIMENT -CHAMBER Storage Node 3072.00 3077.50 3074.25 0.00 0.81 3076.36 0.00 Total Time Flooded (min) 0.00 0.00 0.00 N J ow a � o LL cZ N E N N 1 W F m E E wE 3 wo y W — U) r J O r r O OO M M M 000 000 N V V r r r 000 M M M Ir w m 2 Ir Ir ¢ww =mm U < < F Q Q Z = _ W U U � 0 0 ozz w¢¢ U U U Subbasin Hydrology Subbasin : POST-CONA Input Data Area(ac)..................................................... 0.17 Peak Rate Factor ........................................ 484.00 Weighted Curve Number ............................ 98.00 Rain Gage ID ............................................... BOONE Composite Curve Number Area Soil Curve Soil/Surface Description (acres) Group Number - 0.17 - 98.00 Composite Area & Weighted CN 0.17 98.00 Subbasin Runoff Results Total Rainfall (in) ......................................... 3.72 Total Runoff (in) .......................................... 3.48 Peak Runoff (cfs)........................................ 0.81 Weighted Curve Number ............................ 98.00 Time of Concentration (days hh:mm:ss) ..... 0 00:05:00 Subbasin : POST-CON:1 5.2 5 4.8 4.6 4.4 42 4 3.8 3.6 34 3.2 3 2.8 2.6 2.4 ry 2.2 2 1.0 16 1.4 1.2 1 08 06 0.4 0.2 0.9 0.85 0.8 0.75 0.7 0.65 0.6 0.55 N 0.5 w 0.45 o 0 Y 0.4 0 35 0.3 0.25 02 0.15 0.1 0.05 Rainfall Intensity Graph 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 Time [hrs] Runoff Hydrograph 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 Time [hrs] Junction Input SIN Element Invert Ground/Rim Ground/Rim Initial Initial Surcharge Surcharge Ponded Minimum ID Elevation (Max) (Max) Water Water Elevation Depth Area Pipe Elevation Offset Elevation Depth Cover (ft) (ft) (ft) (ft) (ft) (ft) (ft) (ft) (in) 1 SCM-OUTLET 3071.75 3079.00 7.25 3071.75 0.00 0.00-3079.00 0.00 0.00 Junction Results SIN Element Peak Peak Max HGL Max HGL Max Min Average HGL Average HGL Time of Time of Total Total Time ID Inflow Lateral Elevation Depth Surcharge Freeboard Elevation Depth Max HGL Peak Flooded Flooded Inflow Attained Attained Depth Attained Attained Attained Occurrence Flooding Volume Attained Occurrence (cfs) (cfs) (ft) (ft) (ft) (ft) (ft) (ft) (days hh:mm) (days hh:mm) (ac-in) (min) 1 SCM-OUTLET 0.81 0.00 3072.06 0.31 0.00 6.94 3071.78 0.03 0 11:55 0 00:00 0.00 0.00 Pipe Input SIN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial ID Invert Invert Invert Invert Drop Slope Shape Diameteror Width Roughness Losses Losses Losses Flow Elevation Offset Elevation Offset Height (ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs) 1 SCM-OUTLET-LINK 10.00 3071.75 0.00 3071.50 0.00 0.25 2.5000 CIRCULAR 15.000 15.000 0.0120 0.5000 0.5000 0.0000 0.00 Flap No. of Gate Barrels No 1 Pipe Results SN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number Condition Occurrence Ratio Total Depth Ratio (cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min) 1 SCM-OUTLET-LINK 0.81 0 11:55 11.06 0.07 4.21 0.04 0.27 0.21 0.00 Calculated Storage Nodes Storage Node : SAND -CHAMBER Input Data Invert Elevation (ft)....................................................................................... 3074.00 Max (Rim) Elevation (ft)............................................................................... 3077.50 Max (Rim) Offset (ft).................................................................................... 3.50 Initial Water Elevation (ft)............................................................................. 3074.00 Initial Water Depth (ft).................................................................................. 0.00 Ponded Area (ft').......................................................................................... 0.00 EvaporationLoss......................................................................................... 0.00 Storage Area Volume Curves Storage Curve : SAND -CHAMBER Stage Storage Storage Area Volume 0 104 0.000 2.5 104 260.00 2.6 1 265.25 3.6 1 266.25 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 Storage Area Volume Curves Storage Volume (ft) 0 40 20 30 40 50 60 70 80 90 100 110 420 430 140 450 460 170 180 490 200 240 220 230 240 260 260 6----,----------------------------------------------------------------------------- v---------------- - - --- 3.6 5---------------- --------- ------------------------ --- ------- -- - - 3.5 4 ---i------ --i---r---7------- i------- ------------------------------- 7 - - - 7-------------- ------ 3.4 3--- '----------- •---'---`---`------- '--- '---`---`-- - - - - 3.3 2 --- --- - -- - -- --- --- --- --- ------ --- --- --- --- - ------ - - - - -- - -- - -- - -- - -- --- --- -- - --- -- 3.2 7---'---'---'---•---'---`---`---`-- '--- '---`---`-- - - - - 3.1 3 --- - -- - -- - -- - -- --- --- --- - - -- -- --- --- --- --- ------- - - - - -- --- - -- - -- --- - -- - -- - - -- -- -- 3 9 ---'---'---'--- I-------`---`---`-- - - - - 2.9 8 - -- *- - - * - -- -- -- - ------------- --- --- --- --- --- --- ------ -- 2.8 6----- -- ------ --- --- --- --- --- --- ------ - 2.6 4 *---*--- -- -- - --- ------------- --- --- --- --- --- --- -- -- 2.4 3-- - - - - -- - ----------------------------------------------------- - - - - ------------ 2.3 2'---"--------'---------------'---'-- '---"---"---'---'--- - - - - 2.2 7-- - - - - -- - - -------------------------------------------- - - -- -------------- ------ 2.1 2 - - - ................................. - - - 2 9-------- - --------------------------------------------------------------------- 1.9 8 ------------------------------------ - - - - 7.8 6---------*--- --------------�--- --- ---- ---- --- --- --- --- --- --- ------ -- 7.6 5-- - - - - -- - - -- ------------------- - - -- --------------------------------------- - - - -- 7.5 4'---"---"---"---'---•---•---'---'-- -----I'---"---'--- - - - - 1.4 3;---;---'---'---;---'---;---;----I--- ------------------------------- 7.3 2---'---'---'---•--- `---`---`-- '---'---'--`---`-- - - - - 1.2 7 --- --- --- - -- - -- - -- --- --- - - -- -- - -- - - -- --- - ---------- -- --- - -- - -- - -- --- --- ------ -- 7.7 9- ------------- ---- ------- - - -- -- ,---,---,------------ ,---,---.---.------ 0.9 7---- ;--- ;- - -T--- -- - -- ;--- ;- - - - - -- - --- -------- --- --- --- --- -- - --- -- 0.7 5 ---------- - -- - -- -- -- ;---;---;-- --- ------- - - -- -- I--- --- --- --- --- - -- - - - --- -- 0.5 3 ;---;-- T--- -- -- ----------- --- ------------- --- --- --- --- --- --- ------ -- 0.3 2--------------------------------------------------------------- 4.2 7 -- ------*--- --- -- --- ------�--- ------------- --- --- --- --- --- --- ------ -- 0.1 4 4 5 40 75 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 Storage Area (ft) Storage Area — Storage Volume Storage Node : SAND -CHAMBER (continued) Outflow Weirs SIN Element Weir Flap Crest Crest Length Weir Total Discharge ID Type Gate Elevation Offset Height Coefficient (ft) (ft) (ft) (ft) 1 EM-SPILLWAY Rectangular No 3076.25 2.25 8.00 0.25 3.33 Output Summary Results Peak Inflow (cfs).......................................................................................... 0.81 Peak Lateral Inflow (cfs).............................................................................. 0.00 Peak Outflow (cfs)........................................................................................ 0.81 Peak Exfiftration Flow Rate (cfm)................................................................. 0.00 Max HGL Elevation Attained (ft)................................................................... 3076.35 Max HGL Depth Attained (ft)........................................................................ 2.35 Average HGL Elevation Attained (ft)............................................................ 3075.05 Average HGL Depth Attained (ft)................................................................. 1.05 Time of Max HGL Occurrence (days hh:mm).............................................. 0 11:55 Total Exfiltration Volume (1000-ft3).............................................................. 0.000 Total Flooded Volume (ac-in)....................................................................... 0 Total Time Flooded (min)............................................................................. 0 Total Retention Time (sec)........................................................................... 0.00 Storage Node : SEDIMENT -CHAMBER Input Data Invert Elevation (ft)....................................................................................... 3072.00 Max (Rim) Elevation (ft)............................................................................... 3077.50 Max (Rim) Offset (ft).................................................................................... 5.50 Initial Water Elevation (ft)............................................................................. 3074.25 Initial Water Depth (ft).................................................................................. 2.25 Ponded Area (ft2).......................................................................................... 0.00 EvaporationLoss......................................................................................... 0.00 Storage Area Volume Curves Storage Curve : SEDIMENT -CHAMBER Stage Storage Storage Area Volume (ft) (ft2) (ft') 0 128 0.000 4.5 128 576.00 4.6 1 582.45 5.6 1 583.45 Storage Area Volume Curves S101a9e Volume (ft) 0 50 100 150 200 250 300 360 400 460 600 660 G.6 5.6 G.4-------------------- '--------'--------•--------'--------'--------- '--------------------------------------------- 6.4 1.2 ---------- ---------- --------'-----------------`--------'---------'--------'--------'--------'-------------- 5.2 6 ------- ----- ------ ------ ------ ----- ----- ----- ----- ------ ------ ---- 5 66 '--------'--------'-------- `-------- '--------- '------------------'--------'--------`----- 4.6 64 ------------------------- -- 4.4 4 -------- -------- -------- -------- -------- ------------------------- -------- -------- ------ ----- 4 1.6 '-------- '--------'--------'--------'--------`-------- '--------- -------- '--------'----- --------- ----- 3.6 1.6 ; ; ;-- - - - - -� ----- 3.6 1.4 '---------- --------'--------'-----------------`--------'---------'--------'------'----------------------- 3.4 1.2 -------------------------------------------------------------------- -------------------------------- 3.2 3 --------------------------------------------------------------------------------------------------- 3 !.8 ----------------------------------------------------------------------------------------------------- 2.8 !.6 -----------------'--------'------------------------------------------------------------------ ------ 2.6 !.4------------------------------------------------ -----------------------------------4--------------- 2.4 !.2 -------------------'--------'------------------------------------------------------------------ ------ 2.2 2 ----- ----- ------ ------ ------ ----- ----- ----- ----- ------ ------ ---- 2 I.6 '--------'--------'--------'--------'-------`--------'---------'--------'--------'--------'--------`----- 1.6 1 -------- -------- -- --- -------- -------- ------------------------- -------- -------- -------- ----- 1 1.6 -------- '--------�------- '--------'--------`-------- '--------- '-------- '--------'--------'-------- ----- 0.6 1.6 ;- - -- - - -; ; � - - - -- 0.6 1.4 ----------------'--------'--------f--------------------------------------------'---------------------- 4.4 1.2---- --------------------------------------------------------------------------------------------- 0.2 0 0 0 5 10 15 20 25 30 35 40 45 50 65 60 65 70 76 80 85 90 95 100 105 110 115 120 125 Storage Area (ft) Storage Area - Storage Volume Storage Node : SEDIMENT -CHAMBER (continued) Outflow Orifices SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation (in) (in) (in) (ft) 1 CHAMBER -CONNECTION Side CIRCULAR No 15.00 3074.00 0.61 Output Summary Results Peak Inflow (cfs).......................................................................................... 0.81 Peak Lateral Inflow (cfs).............................................................................. 0.81 Peak Outflow (cfs)........................................................................................ 0.81 Peak Exfiftration Flow Rate (cfm)................................................................. 0.00 Max HGL Elevation Attained (ft)................................................................... 3076.36 Max HGL Depth Attained (ft)........................................................................ 4.36 Average HGL Elevation Attained (ft)............................................................ 3075.05 Average HGL Depth Attained (ft)................................................................. 3.05 Time of Max HGL Occurrence (days hh:mm).............................................. 0 11:55 Total Exfiltration Volume (1000-ft').............................................................. 0.000 Total Flooded Volume (ac-in)....................................................................... 0 Total Time Flooded (min)............................................................................. 0 Total Retention Time (sec)........................................................................... 0.00 Post -construction 100 Year, 24 Hour BREC, P.A. Brown Apartments 14 Project Description File Name .................................................... POST-CON-ROUTING.SPF Project Options Flow Units .................................................... CFS Elevation Type ............................................. Elevation Hydrology Method ........................................ SCS TR-55 Time of Concentration (TOC) Method ......... User -Defined Link Routing Method .................................... Hydrodynamic Enable Overflow Ponding at Nodes ............. YES Skip Steady State Analysis Time Periods .... YES Analysis Options Start Analysis On ......................................... Feb 09, 2021 000000 End Analysis On .......................................... Feb 11, 2021 000000 Start Reporting On ....................................... Feb 09, 2021 000000 Antecedent Dry Days ................................... 0 days Runoff (Dry Weather) Time Step ................. 0 01:0000 days hh:mm:ss Runoff (Wet Weather) Time Step ................ 0000500 days hh:mm:ss Reporting Time Step .................................... 0000005 days hh:mm:ss Routing Time Step ....................................... 5 seconds Number of Elements Qty RainGages .................................................. 1 Subbas in s..................................................... 1 Nodes........................................................... 4 Junctions 1 Outfalls 1 Flow Diversions 0 Inlets 0 Storage Nodes 2 Links............................................................. 4 Channels 0 Pipes 1 Pumps 0 Orifices 1 Weirs 1 Outlets 1 Pollutants..................................................... 0 LandUses .................................................... 0 Rainfall Details SN Rain Gage Data Data Source Rainfall Rain State County Return Rainfall Rainfall ID Source ID Type Units Period Depth Distribution (years) (inches) 1 BOONE Time Series 100YR-24HR Cumulative inches North Carolina Watauga 100 10.90 SCS Type II 24-hr Subbasin Summary SN Subbasin Area Peak Rate Weighted Total Total Total Peak Time of ID Factor Curve Rainfall Runoff Runoff Runoff Concentration Number Volume (ac) (in) (in) (ac-in) (cfs) (days hh:mm:ss) 1 POST-CON:1 0.17 484.00 98.00 10.90 10.66 1.78 2.39 0 00:05:00 Node Summary SIN Element Element Invert Ground/Rim Initial Surcharge Ponded Peak Max HGL Max Min Time of Total ID Type Elevation (Max) Water Elevation Area Inflow Elevation Surcharge Freeboard Peak Flooded Elevation Elevation Attained Depth Attained Flooding Volume Attained Occurrence (ft) (ft) (ft) (ft) (ft') (cfs) (ft) (ft) (ft) (days hh:mm) (ac-in) 1 SCM-OUTLET Junction 3071.75 3079.00 3071.75 0.00 0.00 2.39 3072.34 0.00 6.66 0 0000 0.00 2 OUTFALL Outtall 3071.50 2.39 3071.89 3 SAND -CHAMBER Storage Node 3074.00 3077.50 3074.00 0.00 2.39 3076.45 0.00 4 SEDIMENT -CHAMBER Storage Node 3072.00 3077.50 3074.25 0.00 2.39 3076.61 0.00 Total Time Flooded (min) 0.00 0.00 0.00 N J ow a � o LL cZ N E N N 1 W F m E E wE 3 wo y W — U) r J O r r O OO M M M 000 000 N V V r r r 000 M M M Ir w m 2 Ir Ir ¢ww =mm U < < F Q Q Z = _ W U U � 0 0 ozz w¢¢ U U U Subbasin Hydrology Subbasin : POST-CONA Input Data Area(ac)..................................................... 0.17 Peak Rate Factor ........................................ 484.00 Weighted Curve Number ............................ 98.00 Rain Gage ID ............................................... BOONE Composite Curve Number Area Soil Curve Soil/Surface Description (acres) Group Number - 0.17 - 98.00 Composite Area & Weighted CN 0.17 98.00 Subbasin Runoff Results Total Rainfall (in) ......................................... 10.90 Total Runoff (in) .......................................... 10.66 Peak Runoff (cfs)........................................ 2.39 Weighted Curve Number ............................ 98.00 Time of Concentration (days hh:mm:ss) ..... 0 00:05:00 Subbasin : POST-CON:1 15 14.5 14 13.5 13 12.5 12 11.5 11 10.5 10 9.5 9 8.5 � 8 7.5 -E 7 6.5 r 6 5.5 5 4.5 4 3.5 3 2.5 2 1.5 1 0.5 2.5 24 2.3 2.2 2.1 2 19 1.8 1.7 16 1.5 N 1.4 '--- 1 3 1.2 ry 1.1 1 0.9 0.0 0.7 0.6 0.5 0.4 0.3 0.2 0.1 Rainfall Intensity Graph 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 Time [hrs] Runoff Hydrograph 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 Time [hrs] Junction Input SIN Element Invert Ground/Rim Ground/Rim Initial Initial Surcharge Surcharge Ponded Minimum ID Elevation (Max) (Max) Water Water Elevation Depth Area Pipe Elevation Offset Elevation Depth Cover (ft) (ft) (ft) (ft) (ft) (ft) (ft) (ft) (in) 1 SCM-OUTLET 3071.75 3079.00 7.25 3071.75 0.00 0.00-3079.00 0.00 0.00 Junction Results SIN Element Peak Peak Max HGL Max HGL Max Min Average HGL Average HGL Time of Time of Total Total Time ID Inflow Lateral Elevation Depth Surcharge Freeboard Elevation Depth Max HGL Peak Flooded Flooded Inflow Attained Attained Depth Attained Attained Attained Occurrence Flooding Volume Attained Occurrence (cfs) (cfs) (ft) (ft) (ft) (ft) (ft) (ft) (days hh:mm) (days hh:mm) (ac-in) (min) 1 SCM-OUTLET 2.39 0.00 3072.34 0.59 0.00 6.66 3071.79 0.04 0 11:55 0 00:00 0.00 0.00 Pipe Input SIN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial ID Invert Invert Invert Invert Drop Slope Shape Diameteror Width Roughness Losses Losses Losses Flow Elevation Offset Elevation Offset Height (ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs) 1 SCM-OUTLET-LINK 10.00 3071.75 0.00 3071.50 0.00 0.25 2.5000 CIRCULAR 15.000 15.000 0.0120 0.5000 0.5000 0.0000 0.00 Flap No. of Gate Barrels No 1 Pipe Results SN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number Condition Occurrence Ratio Total Depth Ratio (cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min) 1 SCM-OUTLET-LINK 2.39 0 11:55 11.06 0.22 5.34 0.03 0.49 0.39 0.00 Calculated Storage Nodes Storage Node : SAND -CHAMBER Input Data Invert Elevation (ft)....................................................................................... 3074.00 Max (Rim) Elevation (ft)............................................................................... 3077.50 Max (Rim) Offset (ft).................................................................................... 3.50 Initial Water Elevation (ft)............................................................................. 3074.00 Initial Water Depth (ft).................................................................................. 0.00 Ponded Area (ft').......................................................................................... 0.00 EvaporationLoss......................................................................................... 0.00 Storage Area Volume Curves Storage Curve : SAND -CHAMBER Stage Storage Storage Area Volume 0 104 0.000 2.5 104 260.00 2.6 1 265.25 3.6 1 266.25 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 Storage Area Volume Curves Storage Volume (ft) 0 40 20 30 40 50 60 70 80 90 100 110 420 430 140 450 460 170 180 490 200 240 220 230 240 260 260 6----,----------------------------------------------------------------------------- v---------------- - - --- 3.6 5---------------- --------- ------------------------ --- ------- -- - - 3.5 4 ---i------ --i---r---7------- i------- ------------------------------- 7 - - - 7-------------- ------ 3.4 3--- '----------- •---'---`---`------- '--- '---`---`-- - - - - 3.3 2 --- --- - -- - -- --- --- --- --- ------ --- --- --- --- - ------ - - - - -- - -- - -- - -- - -- --- --- -- - --- -- 3.2 7---'---'---'---•---'---`---`---`-- '--- '---`---`-- - - - - 3.1 3 --- - -- - -- - -- - -- --- --- --- - - -- -- --- --- --- --- ------- - - - - -- --- - -- - -- --- - -- - -- - - -- -- -- 3 9 ---'---'---'--- I-------`---`---`-- - - - - 2.9 8 - -- *- - - * - -- -- -- - ------------- --- --- --- --- --- --- ------ -- 2.8 6----- -- ------ --- --- --- --- --- --- ------ - 2.6 4 *---*--- -- -- - --- ------------- --- --- --- --- --- --- -- -- 2.4 3-- - - - - -- - ----------------------------------------------------- - - - - ------------ 2.3 2'---"--------'---------------'---'-- '---"---"---'---'--- - - - - 2.2 7-- - - - - -- - - -------------------------------------------- - - -- -------------- ------ 2.1 2 - - - ................................. - - - 2 9-------- - --------------------------------------------------------------------- 1.9 8 ------------------------------------ - - - - 7.8 6---------*--- --------------�--- --- ---- ---- --- --- --- --- --- --- ------ -- 7.6 5-- - - - - -- - - -- ------------------- - - -- --------------------------------------- - - - -- 7.5 4'---"---"---"---'---•---•---'---'-- -----I'---"---'--- - - - - 1.4 3;---;---'---'---;---'---;---;----I--- ------------------------------- 7.3 2---'---'---'---•--- `---`---`-- '---'---'--`---`-- - - - - 1.2 7 --- --- --- - -- - -- - -- --- --- - - -- -- - -- - - -- --- - ---------- -- --- - -- - -- - -- --- --- ------ -- 7.7 9- ------------- ---- ------- - - -- -- ,---,---,------------ ,---,---.---.------ 0.9 7---- ;--- ;- - -T--- -- - -- ;--- ;- - - - - -- - --- -------- --- --- --- --- -- - --- -- 0.7 5 ---------- - -- - -- -- -- ;---;---;-- --- ------- - - -- -- I--- --- --- --- --- - -- - - - --- -- 0.5 3 ;---;-- T--- -- -- ----------- --- ------------- --- --- --- --- --- --- ------ -- 0.3 2--------------------------------------------------------------- 4.2 7 -- ------*--- --- -- --- ------�--- ------------- --- --- --- --- --- --- ------ -- 0.1 4 4 5 40 75 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 Storage Area (ft) Storage Area — Storage Volume Storage Node : SAND -CHAMBER (continued) Outflow Weirs SIN Element Weir Flap Crest Crest Length Weir Total Discharge ID Type Gate Elevation Offset Height Coefficient (ft) (ft) (ft) (ft) 1 EM-SPILLWAY Rectangular No 3076.25 2.25 8.00 0.25 3.33 Output Summary Results Peak Inflow (cfs).......................................................................................... 2.39 Peak Lateral Inflow (cfs).............................................................................. 0.00 Peak Outflow (cfs)........................................................................................ 2.39 Peak Exfiftration Flow Rate (cfm)................................................................. 0.00 Max HGL Elevation Attained (ft)................................................................... 3076.45 Max HGL Depth Attained (ft)........................................................................ 2.45 Average HGL Elevation Attained (ft)............................................................ 3075.35 Average HGL Depth Attained (ft)................................................................. 1.35 Time of Max HGL Occurrence (days hh:mm).............................................. 0 11:55 Total Exfiltration Volume (1000-ft3).............................................................. 0.000 Total Flooded Volume (ac-in)....................................................................... 0 Total Time Flooded (min)............................................................................. 0 Total Retention Time (sec)........................................................................... 0.00 Storage Node : SEDIMENT -CHAMBER Input Data Invert Elevation (ft)....................................................................................... 3072.00 Max (Rim) Elevation (ft)............................................................................... 3077.50 Max (Rim) Offset (ft).................................................................................... 5.50 Initial Water Elevation (ft)............................................................................. 3074.25 Initial Water Depth (ft).................................................................................. 2.25 Ponded Area (ft2).......................................................................................... 0.00 EvaporationLoss......................................................................................... 0.00 Storage Area Volume Curves Storage Curve : SEDIMENT -CHAMBER Stage Storage Storage Area Volume (ft) (ft2) (ft') 0 128 0.000 4.5 128 576.00 4.6 1 582.45 5.6 1 583.45 Storage Area Volume Curves S101a9e Volume (ft) 0 50 100 150 200 250 300 360 400 460 600 660 G.6 5.6 G.4-------------------- '--------'--------•--------'--------'--------- '--------------------------------------------- 6.4 1.2 ---------- ---------- --------'-----------------`--------'---------'--------'--------'--------'-------------- 5.2 6 ------- ----- ------ ------ ------ ----- ----- ----- ----- ------ ------ ---- 5 66 '--------'--------'-------- `-------- '--------- '------------------'--------'--------`----- 4.6 64 ------------------------- -- 4.4 4 -------- -------- -------- -------- -------- ------------------------- -------- -------- ------ ----- 4 1.6 '-------- '--------'--------'--------'--------`-------- '--------- -------- '--------'----- --------- ----- 3.6 1.6 ; ; ;-- - - - - -� ----- 3.6 1.4 '---------- --------'--------'-----------------`--------'---------'--------'------'----------------------- 3.4 1.2 -------------------------------------------------------------------- -------------------------------- 3.2 3 --------------------------------------------------------------------------------------------------- 3 !.8 ----------------------------------------------------------------------------------------------------- 2.8 !.6 -----------------'--------'------------------------------------------------------------------ ------ 2.6 !.4------------------------------------------------ -----------------------------------4--------------- 2.4 !.2 -------------------'--------'------------------------------------------------------------------ ------ 2.2 2 ----- ----- ------ ------ ------ ----- ----- ----- ----- ------ ------ ---- 2 I.6 '--------'--------'--------'--------'-------`--------'---------'--------'--------'--------'--------`----- 1.6 1 -------- -------- -- --- -------- -------- ------------------------- -------- -------- -------- ----- 1 1.6 -------- '--------�------- '--------'--------`-------- '--------- '-------- '--------'--------'-------- ----- 0.6 1.6 ;- - -- - - -; ; � - - - -- 0.6 1.4 ----------------'--------'--------f--------------------------------------------'---------------------- 4.4 1.2---- --------------------------------------------------------------------------------------------- 0.2 0 0 0 5 10 15 20 25 30 35 40 45 50 65 60 65 70 76 80 85 90 95 100 105 110 115 120 125 Storage Area (ft) Storage Area - Storage Volume Storage Node : SEDIMENT -CHAMBER (continued) Outflow Orifices SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation (in) (in) (in) (ft) 1 CHAMBER -CONNECTION Side CIRCULAR No 15.00 3074.00 0.61 Output Summary Results Peak Inflow (cfs).......................................................................................... 2.39 Peak Lateral Inflow (cfs).............................................................................. 2.39 Peak Outflow (cfs)........................................................................................ 2.39 Peak Exfiftration Flow Rate (cfm)................................................................. 0.00 Max HGL Elevation Attained (ft)................................................................... 3076.61 Max HGL Depth Attained (ft)........................................................................ 4.61 Average HGL Elevation Attained (ft)............................................................ 3075.35 Average HGL Depth Attained (ft)................................................................. 3.35 Time of Max HGL Occurrence (days hh:mm).............................................. 0 11:55 Total Exfiltration Volume (1000-ft').............................................................. 0.000 Total Flooded Volume (ac-in)....................................................................... 0 Total Time Flooded (min)............................................................................. 0 Total Retention Time (sec)........................................................................... 0.00