From: James Lamb [mailto:jlamb@prestagefarms.com]
Sent: Wednesday, March 24, 2021 9:39 AM
To: Guyton, Steve <steve.guyton@ncdenr.gov>
Subject: [External] 30 Day POA Extension for 82-186
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam.
https://outlook.office365.com/mail/inbox/id/AAQkAGM2NWE3OTJmLThiOWMtNGNINC1 hYTkOLTJIZjMzZDM2ZDU 1 YwAQAPOyg8N3gkEDsdfKEFhA... 1/5
3/24/2021 Mail - Fontenot, Katie - Outlook
PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: 82-186
Facility Name: Herbert Bowden
County:
Sampson
Certified operator Name: Anthony W. Robinson Operator Number: 989092
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
Lagoon Name/ID: 1
Spillway(Y or N): N
Level(inches): 17
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 3/29/21 Weather permitting.
hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Prestage Farms Inc. Phone: 910-592-5771
Facility Owner/Manager (print)
Facility Owner/Manager (signature)
Date: 3/23/2021
https://outlook.office365.com/mail/inbox/id/AAQkAGM2NWE3OTJmLThiOWMtNGNINC1 hYTkOLTJIZjMzZDM2ZDU 1YwAQAPOyg8N3gkEDsdfKEFhA... 2/5
3/24/2021 Mail - Fontenot, Katie - Outlook
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Namelldentifier (ID):
Herbert Bowden
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
top of dike surface area according to design
d. (area at below structural freeboard elevation)
e. line c112 x line d x 7.48 gallons/ft3
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
2880
certified herd #
17.0
19.0
inches
inches
2.0 inches
69696
ft2
86888 gallons
180
94948
2880
days
ft3
actual waste produced = current herd # x line g = 94948 ft3
certified herd #
i. volume of wash water according to structural design ft3
j. excess rainfall over evaporation according to design ft3
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
1 /11 /2021
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
0
40656
169053 gallons
1.01
259 lbs. PAN
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1. Structure ID:
2. Structure ID:
3. Structure ID:
Herbert Bowden
line m =
line m =
line m =
258.5 Ib PAN
Ib PAN
Ib PAN
https://outlook.office365.com/mail/inbox/id/AAQkAGM2NWE3OTJmLThiOWMtNGNINC1 hYTkOLTJIZjMzZDM2ZDU 1YwAQAPOyg8N3gkEDsdfKEFhA... 3/5
3/24/2021
4. Structure ID:
5. Structure ID:
6. Structure ID:
Mail - Fontenot, Katie - Outlook
line m = Ib PAN
line m = Ib PAN
line m = Ib PAN
n. lines 1 + 2 + 3 + 4 + 5 + 6 =
258.5 Ib PAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS ❑URING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
❑. tract #
p. field #
q. crop
r. acres
s. remaining IRR-
2 PAN balance
(Ib/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (Ibs.)
column r x s
u. applicatian windaw1
10558
1A
CB -Hay
3.20
266.00
851.2
MAR-OCT
v. Total PAN available for all fields (sum of column t) _
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) =
x. Crop's remaining PAN balance (line v from section III) _
y. Overall PAN balance (w - x) _
851.2 Ib. PAN
258.5 Ib. PAN
851.2 Ib. PAN
-592.7 Ib. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
NARRATIVE:
https://outlook.office365.com/mail/inbox/id/AAQkAGM2NWE3OTJmLThiOWMtNGNINC1 hYTkOLTJIZjMzZDM2ZDU 1YwAQAPOyg8N3gkEDsdfKEFhA... 4/5
3/24/2021 Mail - Fontenot, Katie - Outlook
Self reported to DWR on 1/5/21. This is an extension for 30 more days.
James L. Lamb
Environment Specialist
Prestage Farms, Inc.
P.O. Box 438
4651 Taylors Bridge Hwy.
Clinton, N.C. 28329
W: 910-596-5814
https://outlook.office365.com/mail/inbox/id/AAQkAGM2NWE3OTJmLThiOWMtNGNINC1 hYTkOLTJIZjMzZDM2ZDU 1YwAQAPOyg8N3gkEDsdfKEFhA... 5/5