Concurrence Point No. 1: Project Purpose &Need and Proposed Study Area
ProjectName/Description:Replace the existing U.S.64 Tyrrell County Bridge No. 7 (Lindsay
C. WarrenBridge)over the Alligator River in Tyrell and Dare Counties. The existing bridge is
a two-lane, swing bridge and would be removed as part of the project. The proposed
replacement structure would be a modern two-lane, high-level, fixed-span bridge. Total
project length is approximately 4.64 miles, WBS No. 49475.1.1,StateTransportation
Improvement Program (STIP) ProjectNo.HB-0001.
Purposeand Need of Proposed Project
The current bridge is experiencing substantial deterioration due to its age and structural
deficiencies resulting in ongoing maintenance problems, jeopardizing its ability to provide
a reliable connection between Columbia and Manns Harbor, Manteo, and the Outer Banks.
The NEED for the project is demonstrated by the following summary of existing and
projected conditions:
Replacement is critical due to the age and structural deficiency of the bridge. The
existing bridge is a 2.83-mile long, 2-lane bridge consisting of 343 spans with a
moveable steel swing span. The bridge was constructed in 1960 and is classified as
structurally deficient with a 31.71 rating of a possible 100.
The existing bridge requires costly, heavy maintenance on a regular basis and
requires constant smaller maintenance activities to keep the swing mechanism
operational.
Approximately 3 years ago a $17 million major rehab project was constructed,
consisting of several hundred pile jackets, concrete repair, deck surfacing, and a
major mechanical overhaul of the swing mechanism and controls. Similar
rehabilitation efforts will be needed with the next 7 years.
Even with the major rehab, the Division is required to perform regular work to
maintain the swing mechanism, which has a history of malfunction resulting in
closure of the bridge to vehicular travel. The mechanical parts, gears, and controls
are not readily available and require custom fabrication with long lead times to
acquire and replace.
The existing Lindsay C. Warren bridge traffic will need to be maintained during
construction of the new bridge. Depending on duration of construction, regular
maintenance of the existing bridge may also need to occur. Vertical navigational
clearance will need to be approved by the US Coast Guard and marine passage along
the Intracoastal Waterway will need to be maintained during construction.
HB-0001
Page 1 of3
March 10, 2021
The PURPOSE of the proposed project is to:
To replace the existing 2.83-mile-long Lindsay C. Warren Bridge, Tyrrell County
Bridge number 7, carrying US 64 across the Alligator River with a two-lane, high-
level, fixed-span bridge.
Project Study Area
Theproposedprojectstudyareawasdevelopedtoaddresstheabove-statedpurposeand
needforHB-0001.TheprojectstudyareaboundariesarefullydepictedonFigure1 ofthe
MergerPacketand are described as follows:
The project study area extends 250-feet on either side of the proposed HB-0001
centerline and 50-feet on either side of the existing Lindsay C. Warren bridge.
The Project Team members have concurred, on this date of March 10, 2021, on the
project purpose and needas stated above and theprojectstudy areafully depictedin
Figure 1 of the Merger packet.
HB-0001
Page 2 of3
March 10, 2021
Federal Highway Administration
(Lead federal agency)Seth Wilcher DATE
US Army Corps of Engineers
Kyle Barnes DATE
NC Division ofWater Resources ___________________________________________
Garcy Ward DATE
NCDepartmentof Transportation
John Conforti DATE
US Environmental Protection Agency
Amanetta Somerville DATE
US Fish &Wildlife Service
Gary Jordan DATE
US Coast Guard (Fifth District)
Hal Pitts DATE
NOAA National Marine Fisheries
Fritz Rohde DATE
NCWildlife ResourcesCommission
Travis WilsonDATE
NC Division of Coastal Management
Cathy Brittingham DATE
NC DEQ Marine Fisheries
James Harrison DATE
NCState Preservation Office
Renee Gledhill-Early DATE
Alligator River National Wildlife Refuge
Becky HarrisonDATE
Albemarle RPO
Angela Welsh DATE
HB-0001
Page 3 of3