HomeMy WebLinkAboutSW6201003_Supplement-EZ Form_20210323
SUPPLEMENT-EZ COVER PAGE
FORMSLOADED
PROJECT INFORMATION
Project Name
Village at Rockfish
1
2Project Area (ac)21
3Coastal Wetland Area (ac)0
4Surface Water Area (ac)0
5Is this project High or Low Density?High
Does this project use an off-site SCM?No
6
COMPLIANCE WITH 02H .1003(4)
7Width of vegetated setbacks provided (feet)No surface water on project area
8Will the vegetated setback remain vegetated?N/A
9If BUA is proposed in the setback, does it meet NCAC 02H.1003(4)(c-d)?
Is streambank stabilization proposed on this project?
10
NUMBER AND TYPE OF SCMs:
11Infiltration System
12Bioretention Cell
13Wet Pond1
14Stormwater Wetland
15Permeable Pavement
16Sand Filter
17Rainwater Harvesting (RWH)
18Green Roof
19Level Spreader-Filter Strip (LS-FS)
20Disconnected Impervious Surface (DIS)
21Treatment Swale
22Dry Pond
23StormFilter
24Silva Cell
25Bayfilter
Filterra
26
FORMSLOADED
DESIGNER CERTIFICATION
27Name and Title:C. Scott Brown, PE Owner
28Organization:4D Site Solutions Inc.
29Street address:409 Chicago Dr. Ste. 112
30City, State, Zip:Fayetteville, NC 28306
31Phone number(s):910-426-6777
Email:sbrown@4dsitesolutions.com
32
Certification Statement:
I certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision; that
the information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete; and that the engineering plans,
specifications, operation and maintenance agreements and other supporting information are consistent with the information provided here.
Designer
______________________________________________
Signature of Designer
______________________________________________
Date
Seal
DRAINAGE AREAS
1Is this a high density project?Yes
ge areas/SCMs1
2 If so, number of draina
3Does this project have low density areas?No
4 If so, number of low density drainage areas0
Is all/part of this project subject to previous rule
5versions?No
FORMSLOADED
Entire Site1
DRAINAGE AREA INFORMATION
4Type of SCM wet pondwet pond
ge area (sq ft)914760704557
5Total draina
6Onsite drainage area (sq ft)914760704557
7Offsite drainage area (sq ft)00
ject(sq ft)319973 sf288473 sf
8Total BUA in pro
New BUA on subdivided lots (subject to
9permitting)(sq ft)243600 sf212100 sf
New BUA not on subdivided lots (subject to
10permitting)(sf)76373 sf76373 sf
11Offsite BUA (sq ft)
12Breakdown of new BUA not on subdivided lots:
- Parking(sq ft) sf
- Sidewalk (sq ft)40 sf40 sf
- Roof (sq ft) sf
- Roadway(sq ft)76333 sf76333 sf
- Future (sq ft) sf
- Other, please specify in the comment box
below(sq ft) sf sf
New infiltrating permeable pavement on
13subdivided lots (sq ft) sf sf
New infiltrating permeable pavement not on
14subdivided lots (sq ft) sf sf
Existing BUA that will remain (not subject to
15permitting)(sq ft) sf sf
16Existing BUA that is already permitted (sq ft) sf sf
17Existing BUA that will be removed (sq ft) sf sf
18Percent BUA35%41%
19Design storm (inches)1.0 in1.0 in
20Design volume of SCM (cu ft)35676 cf35676 cf
Calculation method for design volumeSimpleSimple
21
ADDITIONAL INFORMATION
Please use this space to provide any additional information about the
22drainage area(s):
WET POND
area number
21 Minimum required treatment volume cu ft 26591 cf
GENERAL MDC FROM 02H .3050
3
Is the SCM sized to treat the SW from all surfaces at build -out?
Yes
4
Is the SCM located away from contaminated soils?
Yes
5
What are the side slopes of the SCM H:V ?
3:1
6
Does the SCM have retaining walls, gabion walls or other
engineered side slopes?
No
7
Are the inlets, outlets, and receiving stream protected from erosion
10- ear storm)?
Yes
8
Is there an overflow or bypass for inflow volume in excess of the
desi n volume?
Yes
9
What is the method for dewatering the SCM for maintenance?
Pump preferred
10
If applicable, will the SCM be cleaned out after construction?
Yes
11
Does the maintenance access comply with General MDC 8 ?
Yes
12
Does the drainage easement comply with General MDC 9 ?
Yes
13
If the SCM is on a single family lot, does (will?) the plat comply with
General MDC 10 ?
N/A
14
Is there an O&M Agreement that complies with General MDC (11)?
Yes
15
Is there an O&M Plan that complies with General MDC 12 ?
Yes
161
Does the SCM follow the device specific MDC?
Yes
17
Was the SCM designed bX an NC licensedprofessional?
Yes
WET POND
MDC FROM 02H .1053
181
Sizing method used
SA/DA
19
Has a stage/storage table been provided in the calculations?
Yes
20
Elevation of the excavated main pool depth (bottom of sediment
removal) (fmsl
73.00
21
Elevation of the main pool bottom (top of sediment removal) (fmsl)
74.00
22
Elevation of the bottom of the vegetated shelf (fmsl)
78.00
23
Elevation of the permanent pool (fmsl)
78.50
24
Elevation of the top of the vegetated shelf (fmsl)
79.00
25
Elevation of the temporary pool (fmsl)
79.38
26
Surface area of the main permanent pool (square feet)
23872
27
Volume of the main permanent pool (cubic feet)
84269 cf
28
Average depth of the main pool (feet)
3.71 ft
29
Average depth equation used
Equation 2
301
If using equation 3, main pool perimeter (feet)
31
If using equation 3, width of submerged veg. shelf (feet)
32
Volume of the forebay (cubic feet)
14765 cf
33
Is this 15-20% of the volume in the main pool?
Yes
34
Clean -out depth for forebay (inches)
54 in
35
Design volume of SCM (cu ft)
36
Is the outlet an orifice or a weir?
Orifice
371
If orifice, orifice diameter (inches)
3 in
38
If weir, weir height (inches)
39
If weir, weir length (inches)
40
Drawdown time for the temporary pool (days)
2.8
41
Are the inlet(s) and outlet located in a manner that avoids short-
circuiting?
Yes
42
Are berms or baffles provided to improve the flow path?
No
431
Depth of forebay at entrance (inches)
67 in
44
Depth of forebay at exit (inches)
60 in
45
Does water flow out of the forebay in a non -erosive manner?
Yes
46
Width of the vegetated shelf (feet)
6 ft
47
Slope of vegetated shelf (H:V)
6:1
48
Does the orifice drawdown from below the top surface of the
permanentpool?
Yes
49
Does the pond minimize impacts to the receiving channel from the 1-
r, 24-hr storm?
Yes
50
Are fountains proposed? (If Y, please provide documentation that
MDC 9 is met.
No
51
Is a trash rack or other device provided to protect the outlet system?
Yes
52
Are the dam and embankment planted in non -clumping turf grass?
Yes
53
Species of turf that will be used on the dam and embankment
Centepede
54
Hasa plantin Ian been provided for the vegetated shelf?
Yes
ADDITIONAL
INFORMATION
55
Please use this space to provide any additional information about
the wet pond(s):
Line 37: Should read 2.8", spreadsheet is rounding
Wet Pond 1 10:04 AM 3/23/2021