HomeMy WebLinkAbout820301_30 Day POA_20210322PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: 82-301 County: Sampson
Facility Name: Tommie Naylor Farm 1 & 2
Certified Operator Name:
James Earl Naylor Operator Number: 22404
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
Lagoon Name/ID: 2 3
Spillway(Y or N): N N
Level(inches): 17 17
2. Check all applicable items
X Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 3/23/2021
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Tommie L. Naylor Phone: 910-564-2679
Facility Owner/Manager (print)
Facility Owner/Manager (signature)
Date: 3/22/2021
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1. Structure ID:
2. Structure ID:
3. Structure ID:
4. Structure ID:
5. Structure ID:
6. Structure ID:
1
2
3
n. lines 1 +2+3+4+5+6=
line m = Ib PAN
line m = 22.8 Ib PAN
line m = 38.0 Ib PAN
line m = Ib PAN
line m = Ib PAN
line m = Ib PAN
60.8 Ib PAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR-
2 PAN balance
(Ib/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (Ibs.)
column r x s
u. application window'
3059
13
corn
2.51
128.75
323.2
Mar -Jun
3059
14
corn
4.10
141.25
579.1
Mar -Jun
3059
15
corn
2.39
141.25
337.6
Mar -Jun
3059
16
corn
1.55
141.25
218.9
Mar -Jun
3059
17
corn
1.99
141.25
281.1
Mar -Jun
3063
27
corn
2.23
128.75
287.1
Mar -Jun
3063
28
corn
4.33
128.75
557.5
Mar -Jun
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) =
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) =
x. Crop's remaining PAN balance (line v from section III) =
y. Overall PAN balance (w - x) =
PoA (30 Day) 2/21/00
2584.5 Ib. PAN
60.8 Ib. PAN
2584.5 Ib. PAN
-2524 Ib. PAN
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
1
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/ft3
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd # 0 certified herd #
19.0
inches
inches
19.0 inches
92125
ft2
1091067 gallons
180
116329
2900
days
ft3
actual waste produced = current herd # x line g = ft3
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
0
53740
ft3
ft3
66996 gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/ft'
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd # 0 certified herd #
17.0
19.0
inches
inches
2.0 inches
31250
ft2
38958 gallons
180
29012
1000
days
ft3
actual waste produced = current herd # x line g = ft'
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
18229
ft3
ft3
22725 gallons
I. current waste analysis dated 2/2/2021 0.37 Ibs/1000 gal.
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
22.8 Ibs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
3
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/ft3
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd # 0 certified herd #
17.0
19.0
inches
inches
2.0 inches
51975
ft2
64796 gallons
180
40353
1224
days
ft3
actual waste produced = current herd # x line g = ft3
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
30319
ft3
ft3
37798 gallons
I. current waste analysis dated 2/2/2021 0.37 Ibs/1000 gal.
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
38.0 Ibs. PAN
PoA (30 Day) 2/21/00
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker inches
b. designed 25 yr./24 hr. storm & structural freeboard inches
c. line b - line a (inches in red zone) = inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) ft2
gallons
e. line c/12 x line d x 7.48 gallons/ft'
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd # certified herd #
actual waste produced = current herd # x line g =
days
ft3
ft'
certified herd #
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker inches
b. designed 25 yr./24 hr. storm & structural freeboard inches
c. line b - line a (inches in red zone) = inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) ft2
gallons
e. line c/12 x line d x 7.48 gallons/ft'
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd # certified herd #
actual waste produced = current herd # x line g =
days
ft3
ft'
certified herd #
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker inches
b. designed 25 yr./24 hr. storm & structural freeboard inches
c. line b - line a (inches in red zone) = inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) ft2
gallons
e. line c/12 x line d x 7.48 gallons/ft'
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd # certified herd #
actual waste produced = current herd # x line g =
days
ft3
ft'
certified herd #
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN