HomeMy WebLinkAboutWQ0041444_Final Permit_20210316 (4)Division of Water Resources
State of North Carolina
Department of Environmental Quality
Division of Water Resources
Flow Tracking/Acceptance for Sewer Extension Applications
(FTSE 04-16)
Entity Requesting Allocation: Town of Rutherfordton
Project Name for which flow is being requested: Rutherfordton Sewer to RS Central HS
More than one FTSE may be required for a single project if the owner of the WWTP is not responsible for all pump
stations along the route of the proposed wastewater flow.
I. Complete this section only if you are the owner of the wastewater treatment plant.
a. WWTP Facility Name: Town of Rutherfordton
b. WWTP Facility Permit #: NC0025909
All flows are in MGD
c. WWTP facility's permitted flow 3.0
d. Estimated obligated flow not yet tributary to the WWTP 0
e. WWTP facility's actual avg. flow
f. Total flow for this specific request
g. Total actual and obligated flows to the facility
h. Percent of permitted flow used
0.637
0.038
0.675
22.5%
II. Complete this section for each pump station you are responsible for along the route of this
proposed wastewater flow.
List pump stations located between the project connection point and the WWTP:
(A) (B) (C) (D)=(B+C) (E)=(A-D)
Design Obligated,
Pump Average Daily Approx. Not Yet Total Current
Station Firm Flow** Current Avg. Tributary Flow Plus
(Name or Capacity, * (Firm / pf), Daily Flow, Daily Flow, Obligated Available
Number) MGD MGD MGD MGD Flow Capacity***
* The Firm Capacity of any pump station is defined as the maximum pumped flow that
can be achieved with the largest pump taken out of service.
** Design Average Daily Flow is the firm capacity of the pump station divided by a peaking
factor (pf) not less than 2.5.
*** A Planning Assessment Addendum shall be attached for each pump station located
between the project connection point and the WWTP where the Available Capacity is < 0.
Downstream Facility Name (Sewer):
Downstream Permit Number:
Page 1 of 6
III. Certification Statement:
I rv\. \\ ', r� aS certify to the best of my knowledge that the addition of
the volume of wastewater to be permitted in this project has been evaluated along the route to the
receiving wastewater treatment facility and that the flow from this project is not anticipated to
cause any capacity related sanitary sewer overflows or overburden any downstream pump station
en route to the receiving treatment plant under normal circumstances, given the implementation of
the planned improvements identified in the planning assessment where applicable. This analysis
has been performed in accordance with local established policies and procedures using the best
available data. This certification applies to those items listed above in Sections I and II plus all
attached planning assessment addendums for which I am the responsible party. Signature of this
form indicates acceptance of this wastewater flow.
Signing Ojial Signate
Date
Page 2 of 6
FTSE 04-16