HomeMy WebLinkAboutNCC211090_ESC Approval Submitted_20210224ROY COOPER
w*a
Governor
r
MICHAEL S. REGAN
Secretary
S. DANIEL SMITH
Director NORTH CAROLINA
Envlranmmtal QuaUty
January 28, 2021
LETTER OF APPROVAL WITH MODIFICATIONS
Davidson Water INC.
ATTN: Robert Walters, VP of Construction and Engineering
PO Box 969
Welcome, NC 27374
RE: Project Name: Davidson Water, Inc. - Turnpike Water Line Replacement
Acres Approved: 5.81
Project ID: RANDO-2021-015
County: Randolph
City: Trinity
Address: Turnpike Road
River Basin: Yadkin-PeeDee
Stream Classification: WS-I11
Submitted By: DMP Engineers & Surveyors
Date Received by LQS: January 05, 2021
Plan Type: New
Dear Mr. Walters:
This office has reviewed the subject erosion and sedimentation control plan.
We find the plan to be acceptable and hereby issue this Letter of Approval. The
enclosed Certificate of Approval must be posted at the job site. This plan shall
expire three (3) years following the date of approval, if no land -disturbing
activity has been undertaken, as is required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and
submit an electronic Notice of Intent (NOI) form requesting a Certificate of
Coverage (COC) under the NCGO10000 Construction Stormwater General
Permit.
�D_F
North Carolina Depamnernr of Environmental Quality I Division of Energy, Mineral and Land Resources
Winston-Salem Regional Office 1 450 Hanes MW Road. Suite 3001 Winston-Salem.North Carolina 27103
�°V�� 336.776.9800
Letter of Approval with Modifications
Davidson Water Inc.
January 28, 2021
Page 2 of 4
This form MUST be submitted prior to the commencement of any land
disturbing activity on the above -named project. The NOI form maybe accessed
at deq.nc.gov/NCGO1. Please direct questions about the N0I form to Annette
Lucas at Annettelucas@ncdenr.gov or Paul Clark at Paul. clarka ncdenr. ov.
After you submit a complete and correct NOI Form, a COC will be emailed to
you within three business days. Initially, DEMLR will not charge a fee for
coverage under the NCGO1 permit. However, a $100 fee will soon be charged
annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of
periodic inspection to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented;
requiring protection of existing natural resources and adjoining properties. If,
following the commencement of this project, the erosion and sedimentation
control plan is inadequate to meet the requirements of the Sedimentation
Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through
66), this office may require revisions to the plan and implementation of the
revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance
with Federal and State water quality laws, regulations, and rules. In addition,
local city or county ordinances or rules may also apply to this land -disturbing
activity. This approval does not supersede any other permit or approval.
Letter of Approval with Modifications
Davidson Water Inc.
January 28, 2021
Page 3 of 4
Please note that this approval is based in part on the accuracy of the
information provided in the Financial Responsibility Form, which you
provided. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage
will be a violation of this permit and would require a revised plan and
additional application fee. You are requested to file an amended form if there
is any change in the information included on the form. In addition, it would
be helpful if you notify this office of the proposed starting date for this
project. Your cooperation is appreciated.
Sincerely,
e
lack Dalton
Assistant Regional Engineer
Land Quality Section
Enclosures: Certificate of Approval with Modifications
NCG01 Fact Sheet
Modifications Required for Approval
cc: Davis Martin Powell
ATTN: Andrew P. Larrick, PE
6415 Old Plank Road
High Point, NC 27265
Letter of Approval with Modifications
Davidson Water Inc.
January 28, 2021
Page 4 of 4
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Davidson Water, Inc. - Turnpike Road Water Line Replacement
Project ID: RANDO-2021-015
County: Randolph
1. Be advised the 7/14-day soil stabilization requirements apply to any section
of the project where land -disturbing activities have temporarily or
permanently ceased and shall supersede any less stringent stabilization
requirement on the plans. [G.S. 143-215.1]
2. All potentially affected property owners must be notified prior to utility
construction even though the activity is covered under an easement.
[G.S. 113A-54.1(a1)]
3. All erosion control measures must be installed within the limits of disturbance or
a revised plan must be submitted to include additional disturbed area.
[15A NCAC 413.0118]
4. Additional measures may be required - The applicant is responsible for the
control of sediment on -site. If the approved erosion and sedimentation control
measures prove insufficient, the applicant must take those additional steps
necessary to stop sediment from leaving this site.
[15A NCAC 413.0115]
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities