HomeMy WebLinkAboutSW5201101_Add Info_20210105ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
BRIAN WRENN
Director
Jack Ritchie, RLA
2610 Wycliff Road, Suite 410
Raleigh, NC 27607
NORTH CAROLINA
Environmental Quality
January 5, 2021
Subject: Request for Additional Information
Stormwater Permit No. SW5201101
Duke Energy Progress Louisburg Capacitor Bank 115kV
Franklin County
Dear Mr. Ritchie:
The Division of Energy, Mineral and Land Resources (DEMLR), received a Stormwater
Management Permit Application for the subject project on November 30, 2020. A review of that
information has determined that the application is not complete. The following information is
needed to continue the stormwater review:
Please show the project area in the table in square feet instead of acres (Section IV, 10 of
the Application).
2. Please complete the Supplement-EZ Form and O&M EZ Form (Section V & Section VI,
3). The provided form is outdated (It hasn't been updated since 2009) and is not really
well suited for single lots (It was set up for subdivisions). These forms can be found at
the following link: https:Hdeq.nc.gov/about/divisions/energy-mineral-land-
resources/energy-mineral-land-permit-guidance/stormwater-bmp-manual
3. Provide pdfs of all revisions, 2 hardcopies of revised plan sheets, and 1 hardcopy of other
documents.
a. Pdfs must be uploaded using the form at:
hgps://edocs.deq.nc.gov/Forms/SW Project Submittal
b. Hard copies must be mailed or delivered to the following address:
Jim Farkas
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
D EQ �� North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
512 North Salisbury Street 1 1612 Mail Service Center I Raleigh, North Carolina 27699-1612
NORh1 CAROIJNA �
919.707.9200
Please note that this request for additional information is in response to a preliminary review.
The requested information should be received by this Office prior to February 4, 2021, or
the application will be returned as incomplete. The return of a project will necessitate
resubmittal of all required items, including the application fee. Please reference the State
assigned project number SW5201101 on all correspondence.
If you need additional time to submit the information, please submit your request for a time
extension to the Division at the contact below. The request must indicate the date by which you
expect to submit the required information. The Division is allowed 90 days from the receipt of
a completed application to issue the permit.
The construction of any impervious surfaces, other than a construction entrance under an
approved Sedimentation Erosion Control Plan, is a violation of NCGS 143-215.1 and is subject
to enforcement action pursuant to NCGS 143-215.6A.
If you have any questions concerning this matter please feel free to contact me at
Jim.Farkas@ncdenr.gov or (919) 707-3646.
Sincerely,
)&M"I JW�
Jim Farkas
Environmental Engineer
Stormwater Program
cc: Raleigh Regional Office