The I-5986 (I-5877 Section) project received 2.0 “ of rainfall on September 11, 2020 in an one-hour period, resulting in
sediment losses at 8 permit sites. The details of each site is provided in email below sent by the Assistant Resident
Engineer. Joanne, Jim, and I were able to visit all the permit sites including the impacted sites today during the
Environmental Compliance walk-through. Cleanup and sediment and erosion control repair is underway.
Gregory W. Price, PWS
Division 6 Environmental Program Supervisor
North Carolina Department of Transportation
910 364 0835 office
919 914 1200 mobile
gwprice2@ncdot.gov
500 Transportation Drive
Fayetteville, NC 28302
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
_____________________________________________________________
From: Knight, Justin M <jmknight1@ncdot.gov>
Sent: Monday, September 14, 2020 5:00 PM
To: Rerko, James J <jjrerko@ncdot.gov>; Price, Gregory W <gwprice2@ncdot.gov>
Cc: Wise, Randy K <rkwise@ncdot.gov>; Yarborough, Jerry W <jyarborough@ncdot.gov>; Matt Goldie
<MGoldie@sepiinc.com>; Timothy Smith <timothy.smith@ice-eng.com>
Subject: I-5877 Sediment Loss
Jim / Greg,
Below is a summary of sediment losses we had on the project due to a rain event on Friday evening. It rained close to 2”
in under an hour. Cleanup operations began today and will continue until all sites are restored to previous
condition. Let me know if you have any questions. Thanks.
1
Permit Site 5, 815+50 -L- RT. Sediment entered rip rap outlet pad and traveled beyond project limits. Most of
the sediment came from the headwall at structure 711 washing out. Approximately 2 CY loss.
Permit Site 7, 22+00 -Y22- RT. Rain overwhelmed special sediment control fencing on both side of
JS. Approximately 0.5 CY loss.
Permit Site 7B, 815+50 -L- RT. Sediment infiltrated rip rap outlet pad. Approximately 2 CY loss.
Permit Site 8A, 850+00 -L- RT. Sediment entered RCP on LT -L-and traveled through 48” steel pipe and
infiltrated rip rap outlet pad. Approximately 3 CY loss.
Permit Site 8 & 8B, Water entered existing 18” RCP on the -L- LT and washed sediment off project limits on -L-
RT. Approximately 2 CY loss.
Permit Site 10, 18+00 -DR5- RT. Sediment entered JS by 18” RCP. Approximately 0.5 CY.
Permit Site 11A, 20+50 -Y13- RT. 57 stone washed in ditch prior to entering JS. Unsure at this time how much if
any material entered the JS. Will monitor as the water level recedes and take appropriate action.
Thanks,
Justin Knight