HomeMy WebLinkAboutU-4007Br•
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
BEVERLY EAVES PERDUE DIVISION OF HIGHWAYS
GOVERNOR
May 14 2012
Belinda S Henson
Regional Supervisor Surface Water Protection NCDWQ
225 Green St Suite 714
Fayetteville NC 28301 5043
Subject U 4007B Complaint and Non Compliance
Dear Ms Henson
EUGENE A CONn 7R
SECRETARY
In response to your office s letter dated May 7 2012 the Department is submitting to you the items of
correction completed by our Contractor as well as future actions that will be taken by the Department
and the Contractor to ensure the project s compliance with all environmental permits
Actions to Correct Unauthonzed Discharge
The Contractor repaired the borrow pit s dewatermg basin removing the excessive sediment deposits
noted during your office s review of the site They also repaired several exposed erodible areas that had
been noted as needing attention at or beyond the perimeter of the pit These areas were repaired and have
been properly seeded and mulched The sediment deposits down the slope at the two tributaries were
removed by the Contractor s forces utilizing shovels and buckets
Action taken to prevent further Unauthorized Discharge
Future measures will include adding additional locations for NTU readings along the path of the borrow
pit s discharge to the pond as well as checking the background readings of any water meeting the borrow
pit s discharge The dewatermg operation s NTU readings will be checked for compliance 30 minutes
after the operation starts and begins discharging All readings will be recorded by the Contractor on a
dewatermg log The NCDOT is also taking and recording several checks a week to verify the
contractor s readings The dewatering basin itself will be added as a stormwater discharge outfall during
our NPDES reviews This will insure it is closely monitored for any maintenance requirements
regardless of the NTU readings
The Department will work diligently to prevent this error from occurring in the future We have
discussed the importance of monitoring turbidity and preventing erosion at all locations along the project
5501 Barbados Boulevard Castle Hayne NC 28429
Phone (910) 341 2000 Fax (910) 675 0143
both with the Contractor s personnel and our own staff I have emphasized to them that they continue to
look for ways to go beyond the minimum requirements when ensuring compliance with our permits and
ensuring the preservation of our surrounding environment
Sincerely
Karen Eason Fussell PE
Division Engineer
KEF /nm
cc Mason Herndon DWQ
Jackson Provost PE Division Construction Engineer
David Candela PE Resident Engineer
Stoney Mathis PE DEO
Jim Gregson Wilmington Regional Office
Brad Shaver US Army Corps of Engineers Wilmington District Office
David Wainwright NCDWQ Wetlands /401 Transportation Group
Sonia Carillo NCDWQ Central Office