NORTH CAROLINA DEPARTMENT OF TRANSPORTATION
FIELD SCOPING MEETING WORKSHEET
Design Build Process
WBS No 17BP 5 R 9
Field Scoping Meeting Date
Division 5 Location On -site
Route (US /NC /SR) SR1100 County Wake
Project Description Bridge #338 over Kenneth Creek on SR 1100
Tier SUBREGIONAL
Municipality r(kv� Attendees
Structure No 910338
1 of 4
Name
Phone No
E -mail
Division Bridge
Manager
Division Environmental
Officer
Hydraulics Engineer
Geotechnical
USACE
DENR -DWQ
TPMU
TPMU
TPMU
Bridge Management
Structure No 910338
1 of 4
Existing Features
Feature Bridged 910338 Bridge #338 over Kenneth Creek on SR 1100
Ex Bridge Clear Deck Width 24 3 (Ft) Existing Shoulders (Ft )
(Bridge / Culvert) Length 41 (Ft) Deck Width (Out To Out) 25 3
Water Depth 1 (Ft) Height Bed To -Crown 12 (Ft)
Prior Survey Date Posted SV 16 TTST
Superstructure Type ST F -BM , Substructure Type NONE
Span Type 1 - 40 5'
Historic High Water (Elev To The Existing Structure) (Ft)
Sufficiency Rating 322 , DP 55 School Bussing crossings per day
Posted Speed Limit In Project Vicinity (mph / Statutory 55mph)
Detour Off -Site Stage Construction On -site
If Detour is Off -Site Provide Description Of Detour Route
Approximate Length Of Detour? 6( Miles )
Improvements Needed To Road(s) On Detour?
Div Traffic Eng Recommend Off -site detour signing?
Improvements Needed To Bridges On Detour?
Are Bridges On Detour Currently Programmed On Tip?
Are There EMS Or Business Access Issues? No
Are There Any Railroad Crossings On Detour?
Should Work Zone Pedestrian Access Be Maintained During Construction?
Overhead Utility Lines In Conflict
Power Transmission Lines In Conflict
Telephone In Conflict
Cable Lines In Conflict
Fiber Optic In Conflict
Water In Conflict
Sewer In Conflict
Natural Gas In Conflict
Other In Conflict
(Ft )
20
Based On The Past History Near This Project Site What Is The Estimated Time Required
To Complete Utility Adjustments — Months
Is There Any Future Utility Construction Anticipated In The Project Area
Is A FEMA Buy -Out Property Being Impacted
Structure No 910338 2 of
I
Environmental
Wetlands At Site No Comments But impacts to JD stream is likely
Known Endangered Species Populations In Area? Yes Michaux's sumac, Red cockaded
woodpecker & Dwarf wedgemussel Comments Biological Conclusion for MS & RCW
were NO EFFECT DWM to be determined
Trout County N TVA County N
CAMA County N Primary Nursery Area N I
Moratoria If Yes - Duration . I
Permits Required
C�
Water Quality Classification C, Buffer No
Will A Coast Guard Permit Be Required? No Drainage Basin Cape Fear
Is The Project Site In Or Near Any Of The Following
National Forest No, Wildlife Refuge No,
State County Or Local Park No, Wild And Scenic River No,
Airport No, A Lake For Recreation Of Power Generation
Water Supply Reservoir No, Nutrient Sensitive Waters N ,
Public Use Boat Ramp Cemeteries
Known Or Potential Historic Properties in The Area Historic Archit Survey required N
, Archaeology Survey required S
Is The Bridge Structure Itself Or Any Part Thereof Considered Historic No
Will The Project Impact A Church Community Center Or Other Public Facility?
Is This Project On A Statewide Bicycle Route Or A Local Non - Marked Bicycle Route N
Any Clarification Or Comments On Items Above
Geotechnical
Are There Any Historical And / Or Vibration Sensitive Structures Near By Comments
Are There Any Known Landfills And / Or Geo- environmental Hazard Sites At Or Within
Close Proximity To The Project Site -- - - - - -- Comments
Are Any Impacts Anticipated To Natural Springs Or Artesian Wells Comments
Possible Foundation Type
Structure No 910338 3 of 4
a
Hydraulics
Will This Project Require FEMA Approval? Y (MOA )
Will This Project Require A State Stormwater Permit? N
Is There Unusual Scour Potential? Is Protection Needed?
Are Banks Stable? Is Protection Needed?
Does Stream Carry Appreciable Amount Of Large Debris?
Will The Placement Of Bents In The Water Be Allowed
Drop Inlets Flumes or Funnels?
Items To Be Discussed / Resolved At FSM By Attendees
Off Site Detour ❑ Stage ❑ New Location ❑
Type Of Environmental Document
Low Impact Data Spreadsheet ❑ Minimum Criteria Rule /MC Checklist ❑
Other
Superstructure Type (office estimate Bridge 80 triple 10 x8 RCBC which would require CLOMR)
Number Of Spans
Length Of Spans
ADT 2300 /BIR NHS 0 Tier SUBREGIONAL Func Class LOCAL
Bridge Min Clear Deck width Recommended by Div
Roadway lane width 'with ` shoulders
Will Railroad Involvement Be Required
R/W by Others DBT will be responsible for R/W acquisition and coordination of utility issues
Permits NCDOT will submit permits as prepared by DB Team
Method of Clearing
Truck Percentage _ % Reasonable Safe Speed mph
Liquidated damages will be imposed after days of closure Amt $ per day
CEI to be done by NCDOT or others
Salvageable materials
Removal of remnant abutments /piers
Additional Comments
Any priority in bridge construction sequencing?
Approach slab on skew or perpendicular?
Structure No 910338 4 of