HomeMy WebLinkAbout20110928 Ver 1_More Info Received_20120320Strickland, Bev
From: Landry, Natalie
Sent: Tuesday, March 20, 2012 8:46 AM
To: Strickland, Bev
Subject: FW: Oxford - Henderson Airport RW Extension (AID SAW- 2010 -01453 and DWQ 11 -0928)
(UNCLASSIFIED)
Hi Bev,
Would you add this email correspondence to DWQ Project File #11 -0928 please. Thank you.
Natalie
From: Smail, Ed [ mai Ito: ESmail(a)ccroadwise.coml
Sent: Thursday, March 15, 2012 4:05 PM
To: Alsmeyer, Eric C SAW
Cc: Landry, Natalie; Elliott, Jason L; Murphy, Gordon; Williams, Brigid
Subject: RE: Oxford- Henderson Airport RW Extension (AID SAW- 2010 -01453 and DWQ 11 -0928) (UNCLASSIFIED)
Eric,
After discussing the project schedule with our engineers, it appears that while the project will be bid this year,
construction would not be complete until next year. Therefore, in order to maintain coverage under the Nationwide
Permit, the project would need to be under the 2012 Nationwide Permits.
On behalf of the Oxford- Henderson Aeronautics Authority, THE LPA GROUP is requesting the project (SAW 2010 - 01453)
be reauthorized under the 2012 Nationwide Permits to maintain permit coverage through the duration of construction.
Please let me know if you have any questions, or require additional information.
Thanks
es
From: Alsmeyer, Eric C SAW [mailto: Eric .C.Alsmeyer(a)usace.army.mill
Sent: Monday, March 12, 2012 3:32 PM
To: Smail, Ed
Cc: natalie.landry(a)ncdenr.gov; Elliott, Jason L; Murphy, Gordon; Williams, Brigid
Subject: RE: Oxford- Henderson Airport RW Extension (AID SAW- 2010 -01453 and DWQ 11 -0928) (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Ed: Based on the available information, we have determined that the Oxford - Henderson Aeronautics Authority
has made a substantial financial commitment to the subject project based on the nationwide ;eneral permit 39,
which expires on March 18, 2012. Because of this commitment, we have determined that the project qualifies
for ";randfatherin y" under that nationwide ;eneral permit, and the project will remain authorized provided the
activity is completed within twelve months of March 18, 2012.
Please reply or call if you have any questions or if I may serve you in any other way.
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at our website at
http: // pert .nwp.usace.army.mil /survey.html to complete the survey online (Paper copies available upon request).
Xzzc
Eric Alsmeyer
Project Manager
Raleigh Regulatory Field Office
US Army Corps of Engineers, Wilmington District
3331 Heritage Trade Drive, Suite 105, Wake Forest, NC 27587
Tel: (919) 554 -4884, x23
Fax: (919) 562-0421
Regulatory Homepage: http: / /www.saw.usace.army.mil /WETLANDS
From: Smail, Ed [ mai Ito: ESmail(a)ccroadwise.coml
Sent: Friday, March 02, 2012 4:57 PM
To: Alsmeyer, Eric C SAW
Cc: natalie.landry(a)ncdenr.gov; Elliott, Jason L; Murphy, Gordon; Williams, Brigid
Subject: Oxford- Henderson Airport RW Extension (SAW 2010 -01453 and DWQ 11 -0928)
Eric,
The Section 404 Nationwide Permit associated with the Runway Extension at the Oxford - Henderson Airport (SAW 2010-
01453) is set to expire with the Nationwide Permits on March 18, 2012 (copies are attached for quick reference). Due to
the funding schedule, this project is under contract for design, but is not under contract for construction.
What would need to be done in order to get this project covered under the 2012 Nationwide Permit?
Have a good weekend
Thanks
es
Edward J. Smail
Environmental Scientist
THE LPA GROUP INCORPORATED
A Unit of Michael Baker Corporation
4401 Belle Oaks Drive, Suite 105
North Charleston, SC 29405
843 - 329 -0050
www.lpagroup.com
www.mbakercorp.com
Classification: UNCLASSIFIED
Caveats: NONE