Project Submittal Form
Please note: fields marked with a red asterisk below are required. You will not be able to submit the form until all
mandatory questions are answered.
Project Type: * r
For the Record Only (Courtesy Copy)
r
New Project
r
Modification/New Project with Existing ID
r
More Information Response
r
Other Agency Comments
r
Pre -Application Submittal
r
Re-Issuance\Renewal Request
r
Stream or Buffer Appeal
Is this supplemental information that needs to be sent to the Corps?*
r Yes r No
Project Contact Information
Name: Richard Harmon
Who is subrritting the inforrration?
Email Address: richard.harmon@woodplc.com
Project Information
Existing ID #:
20201283
20170001(no dashes)
Existing Version:
1
1
Project Name: Duke Energy Roxboro Steam Electrical Plant Ash Basin Lanfill Project
Is this a public transportation project?
r Yes
r No
Is the project located within a NC DCM Area of Environmental Concern (AEC)?
r Yes r No r Unknown
County (ies)
Person
Please upload all files that need to be submited.
aick the upload button or drag and drop files here to attach document
02.05.21 Roxboro Tables FINAL.pdf 10.03KB
Only pdf or lm7 files are accepted.
Describe the attachments
or comments:
Responses to NCDWR comments received based on the Public Notice of Individual permit application for the
Duke Energy Roxboro Steam Electric Plant Ash basin Landfill project. DWR # 20201283vl ; Corps Action ID#
SAW-2015-02646
Sign and Submit
W By checking the box and signing box below, I certify that:
■ I, the project proponent, hereby certifies that all information contained herein is true, accurate, and complete to
the best of my knowledge and belief.
■ I, the project proponent, hereby requests that the certifying authority review and take action on this CWA 401
certification request within the applicable reasonable period of time.
■ I agree that submission of this online form is a "transaction" subject to Chapter 66, Article 40 of the NC General
Statutes (the "Uniform Electronic Transactions Act');
■ I agree to conduct this transaction by electronic means pursuant to Chapter 66, Article 40 of the NC General
Statutes (the "Uniform Electronic Transactions Act');
■ I understand that an electronic signature has the same legal effect and can be enforced in the same way as a
written signature; AND
■ I intend to electronically sign and submit the online form.
Signature:
Submittal Date: Is filled in autocratically.
Table 5.3. Proposed Impacts to Wetlands within the Project Site
Wetland ID
Total Area (acres)
Impact Area (acres)
Landfill Area
Wetland R
0.09
0.09
Wetland S
0.03
0.03
Wetland V
0.08
0.08
West Ash Basin
Wetland B
0.31
0.05
Wetland C
0.19
0.07
Wetland D
0.12
0.06
Wetland J
0.08
0.08
Borrow Area 1
Wetland L
0.11
0.04
Wetland Z
AVOIDED
Wetland OW-1
AVOIDED
(Proposed impacts to Wetland Z and Wetland OW-1 in Borrow Area 1 were avoided as a
result of a followup siting visit)
Table 5.4. Proposed Impacts to Streams within the Project Site
Stream ID
Total Area (If)
Impact Area (If)
Landfill Area
Stream 16
431
431
Stream 19
732
732
Stream 33
2126
52 (permanent)40 (temporary)
West Ash Basin
Stream 5
655
52
Stream 6
398
87
Stream 8
124
102
Stream 9
167
35
Stream 35
1700
68
Stream 38
442
25
Stream 40
1933
72
Stream 50
669
44
Borrow Area 1
Stream 10
AVOIDED
Borrow Area 6
Stream SRJ
2032
56
Stream SRK
2056
59
Stream SRKA
724
63
Stream SRG
1278
51
Stream SJA
2555
121
Borrow Area 8
Stream 33
2126
511
(Proposed impacts to Stream 10 in Borrow Area 1 were avoided as a result of a followup siting
visit and detailed design)