HomeMy WebLinkAbout20120079 Ver 1_More Info Received_20120302Strickland, Bev
From:
Homewood, Sue
Sent:
Friday, March 02, 2012 3:34 PM
To:
Strickland, Bev; Dennison, Laurie
Subject:
FW: WFBH - Davie Campus
For file 12 -0079
Sue Homewood
NC DENR Winston -Salem Regional Office
Division of Water Quality
585 Waughtown Street
Winston - Salem, NC 27107
Voice: (336) 771 -4964
FAX: (336) 771 -4630
E -mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be
disclosed to third parties.
From: Kelway Howard [ mailto:KHoward(a)stimmelpa.com]
Sent: Friday, March 02, 2012 2:56 PM
To: Homewood, Sue
Cc: MBrame
Subject: WFBH - Davie Campus
Sue, This email is in response to your request for additional information related to the River Hill Circle stream crossing
as it relates to avoidance and minimization. Below are our responses:
Having the River Hill Circle roadway loop around the Hospital is very important to managing the traffic around
the new Hospital. Without River Hill Circle looping through the site all outparcel traffic would have to circulate
the site via Wake Forest Baptist Way that runs in front of the Hospital; this would increase the possibility of a
pedestrian vs. vehicular accident. If River Hill Circle dead ended on each side of the stream, this would create a
great deal of confusion for the public on how to get either side of the creek to access the outparcels. It is our
opinion the single stream crossing is needed to provide the site development with a safe and practical road
network to serve the proposed outparcels and Medplex buildings.
2. The site design was performed in a way that minimizes the stream impacts. The Medplex buildings were laid out
around the stream located in the central part of the site. The site has approximately 4,348 linear feet of streams
and our proposed impacts are 200 linear feet.
3. The roadway crossing is utilizing extra tall headwalls to minimize the amount of stream impacts.
4. The side slopes of the roadway at the stream crossing were increased to their maximum slope as recommended
in the site geotechnical report to provide additional reduction in the stream impact.
Please advise if you need additional information. Thanks
Kelway L. Howard III, PE
Senior Project Manager
khowardastimmehoa. com
Stimmel Associates, P.A.
601 N. Trade St. Suite 200
Winston - Salem, NC 27101
v: 336.723.1067 ext.112
f: 336.723.1069
www.stimmelpa.com
Stimmel Associates, P.A. E -mail Disclaimer