HomeMy WebLinkAbout20090876 Ver 2_Email_20120301Ridings, Rob
From Murray Christopher A
Sent Thursday March 01 2012 4 52 PM
To Alsmeyer Eric C SAW Ridings Rob
Cc Billy Lee (blee @withersravenel com) (blee @withersravenel com) Lipscomb Brian S
Pearson Donald R Hinnant Chadwick D Griffin Benjamin R Lauffer Matthew S
Subject RE Construction issue on RSP 1 in Wake County
Attachments RSP 1 Revised Permit Drawing 3 of 9 pdf
Rob and Eric,
I was out at the site earlier this afternoon with the hydraulic engineer and Resident
Engineer We have all determined that the best option for long -term stability is to extend
the rip rap bank stabilization throughout the entire footprint of Stream Site 2 This is
depicted in revised permit drawing 3 of 9 The contractor proposes to transition from a
1 5 1 rip rap slope to a 2 1 rip rap slope in this area
This construction revision will add 35 linear feet of permanent rip rap streambank impact at
this area A review of the permits previously issued for the project indicates that the
additional rip rap bank stabilization can be added as a project impact without additional
notification to your agency The total streambank stabilization impacts remain below 500
linear feet Note that this activity does not result in additional riparian buffer impact
Please contact me if you need further information
Chris Murray
Original Message
From Murray, Christopher A
Sent Wednesday, February 29, 2012 3 37 PM
To Alsmeyer, Eric C SAW, Ridings, Rob
Cc Billy Lee (blee@withersravenel com) (blee(@withersravenel com), Lipscomb, Brian S,
Pearson, Donald R, Hinnant, Chadwick D, Griffin, Benjamin R
Subject Construction issue on RSP -1 in Wake County
Reference
Maintenance repair activity at failed hydraulic pipe system and rip rap bed and bank
stabilization along Wade Avenue in Wake County (TIP Project RSP 1), USACE Action ID No
2011 - 02227, DWQ Project No 20090876 ver 2 u� / ��-
G� D
Eric and Rob,
Construction activities have commenced at Permit Sites 1 and 2,(Wade Avenue South) I was
out at the project yesterday and wanted to provide you some information
Issue 1
Heavy rain events on February 25 and 27, 2012 resulted in the additional loss of segments of
the existing 18 inch RCP pipe structure that originates under Wade Avenue The loss of the
pipe segments resulted in deposition of sediment into the Unnamed Tributary to House Creek
Note that grading activity commenced Tuesday morning That the loss of sediment into the
stream channel is a result of the rain events that occurred on Saturday and Monday (prior to
the grading activity)
1
Issue 2
The recent loss of the pipe segments affects the ability of the contractor to install a
downstream device to dewater and manage the stream during the life of the project The
contractor was advised to do the following 1) Attach slope drain pipe to the two existing
pipe structures to convey clean water through the work area 2) Install sand bags as a
dewatering device at the tail end of the proposed in stream rock stabilization while the
contractor surges fill material into the work area This will prevent loss of material
beyond the permitted permanent stream impact footprint during this time frame A silt bag
will also be utilized at this location 3) Remove the sand bag in the near future and install
a temporary rock sediment dam (Type A) in the stream channel
The Department typically does not typically install temporary rock sediment dam (Type A) in
stream channels The device will be installed within the permitted permanent stream impact
Note that the dam is not completely effective in preventing movement of sediment off the work
limits However, this appears to be the best option due to the unstable (and dangerous)
nature of the streambanks and adjacent ground
Issue 3
Permit Drawing 3 of 9 depicts rip rap stabilization further downstream along the Unnamed
Tributary to House Creek An evaluation of the area yesterday depicted on Permit Drawing 3
of 9 revealed unstable streambanks along a portion of the streambank that was not to be
stabilized as part of this project The Department will review this area with the hydraulic
engineer and determine if it is necessary to include this area as part of the streambank
stabilization Further information regarding this activity will be provided to your offices
later this week
I wanted to provide you with this updated information Please contact me if you need further
information
Chris Murray
Email correspondence to and from this sender is subject to the N C Public Records Law and
may be disclosed to third parties
7
TND £ 9�TRAELWAY
EASTBOUND ES _
E15T OF TRAVEL WAY -
-- TRAVEL Wt_ —
- J - — T T T T T - - — T T �1 EDGE OF PVEMENT
- - -- — ET
E.i/snic Rg .IDN[ ��r�P _ ` ` ` �
BANK
STABILIZATION — — — — — —
rBANK
/-
STABILIZATION
toH
r
-- \
_r, xDl rn �u go
SITE 2A % SF 1�6h M p CLJ- \
STREAM IMPACT = 231 LF 35 LF-
®DENOTES IMPACTS IN
SURFACE WATER
SITE 2B
STREAM IMPACT =102 LF
X.
50 0 50 100
SCALE 1 50
WITHERS &- RAVENEL
ENGINEERS I PLANNERS I SURVEYORS
1 M cK DA Cary North C o11 I'll
h 919169 3310 1. 9 9 673006 www wish rs0wen I — . m I, C...
STREAM SITE IMPACT 2
N C DEPT OF TRANSPORTATION
DIVISION OF HIGHWAYS
WAKE COUNTY
PROJECT 42188 (RSP-1)
WADE AVENUE BMP
BETWEEN
BLUE RIDGE ROAD AND I 440
„F V, SHEET 3 OF 9
3/1/12
I
11