Maintenance records shall be kept on the following BMP(s). This maintenance record shall be kept in a log in a known set
location. Any deficient BMP elements noted in the inspection will be corrected, repaired, or replaced immediately. These
deficiencies can affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the BMP(s).
The BMP(s) on this project include (check all that apply & cc
Bioretention Cell Quantity:
Dry Detention Basin
Grassed Swale
Green Roof
Infiltration Basin
Infiltration Trench
Level Spreader/VFS
Permeable Pavement
Proprietary System
Rainwater Harvesting
Sand Filter
Stormwater Wetland
Wet Detention Basin
Disconnected Impervious Area
User Defined BMP
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Present:
Present:
nding O&M tables wil
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
oe aaaea autom
Lot A
I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed
for each BMP above, and attached O&M tables. I agree to notify NCDENR of any problems with the system or prior to any
changes to the system or responsible party.
Responsible Party:
Title & Organization:
Street address:
City, state, zip:
Phone number(s):
Email:
Signature: (' --
Lew Bleiweis
Executive Director, Greater Asheville Regional Airport Authority
Fletcher, NC 28732
828 684-2226
Ileiweis@flyavl.com
Date:
I, L�ftg n 19, 141eNi.Jl b d— , a Notary Public for the State of Mw t h (r,R �� �) n �✓
County of J® e-ndes f D r� , do hearby certify that Ie`62 !S) Gi vu6) S
personally appeared before me this r� °f— day of 1� P76A 6,e1 and
acknowledge the due execution of the Operations and Maintenance
Agreement .
Witness my hand and official seal, Ell l
ELLEN M HEYWO D
NOTARY PUBLIC
HENDERSON COLINTY NC
My Commission Expires 5.10024
ig e�
STOSK-#Z My commission expires l �l 8/30/2019
Version 1.4 Page 1 of 5
STORM-EZ 8/30/2019
Version 1 .4 O&M Manual Page 2 of 5
Dry Detention Pond Maintenance Requirements
Important maintenance procedures
The drainage area will be managed to reduce the sediment load to the dry extended detention basin.
Immediately after the dry extended detention basin is established, the vegetation will be watered twice weekly if needed
until the plants become established (commonly six weeks).
No portion of the dry extended detention pond will be fertilized after the first initial fertilization that is required to establish
the vegetation.
- The vegetation in and around the basin will be maintained at a height of approximately six inches.
- If cracks, seepage, or woody vegetation is present, consult a dam safety expert for a dam inspection.
The measuring device used to determine the sediment elevation shall be such that it will give an accurate depth reading and not
readily penetrate into accumulated sediments.
After the dry detention basin is established, it will be inspected quarterly. Inspection activities shall be performed as follows and
any problems identified will be remediated immediately per the table below.
BMP element:
Potential problem:
How to remediate the problem:
The entire BMP
Trash/debris is present.
Remove the trash/debris.
The perimeter of the BMP
Areas of bare soil and/or
Regrade the soil if necessary to remove the gully, and then plant a
erosive gullies have formed.
ground cover and water until it is established. Provide lime and a one-
time fertilizer application.
Vegetation is too short or too
Maintain vegetation at a height of approximately six inches.
long.
The inlet device
The pipe is clogged.
Unclog the pipe. Dispose of the sediment off -site.
The pipe is cracked or
Replace the pipe.
otherwise damaged.
Erosion is occurring in the
Regrade the swale if necessary to smooth it over and provide erosion
swale.
control devices such as reinforced turf matting or riprap to avoid future
problems with erosion.
Stone verge is clogged or
Remove sediment and replace with clean stone.
covered in sediment (if
applicable).
The forebay
Trash/debris is present.
Remove the trash/debris.
Erosion has occurred or
Provide additional erosion protection such as reinforced turf matting or
riprap is displaced.
riprap if needed to prevent future erosion problems.
Weeds are present.
Remove the weeds, preferably by hand. If pesticides are used, wipe
them on the plants rather than spraying.
STORM-EZ 8/30/2019
Version 1 .4 O&M Manual Page 3 of 5
Dry Detention Pond Maintenance Requirements (continued)
BMP element:
Potential problem:
How to remediate the problem:
The main treatment area
Sediment has accumulated
Search for the source of the sediment and remedy the problem if
and reduced the depth to 75%
possible. Remove the sediment and dispose of it in a location where it
of the original design depth
will not cause impacts to streams or the BMP. Revegetate disturbed
(per pond design data sheet)
areas immediately with sod (preferred) or seed protected with securely
staked erosion mat.
Water is standing more than
Check outlet structure for clogging. If it is a design issue, consult an
5 days after a storm event.
appropriate professional.
Weeds and noxious plants
Remove the plants by hand or by wiping them with pesticide (do not
are growing in the main
spray).
treatment area.
The embankment
Shrubs or trees have started
Remove shrubs or trees immediately.
to grow on the embankment.
Grass cover is unhealthy or
Restore the health of the grass cover — consult a professional if
eroding.
necessary.
Signs of seepage on the
Consult a professional.
downstream face.
Evidence of muskrat or
Use traps to remove muskrats and consult a professional to remove
beaver activity is present.
beavers.
An annual inspection by an
Make all needed repairs.
appropriate professional
shows that the embankment
needs repair.
The outlet device
Clogging has occurred.
Clean out the outlet device. Dispose of the sediment off -site.
The outlet device is damaged
Repair or replace the outlet device.
The receiving water
Erosion or other signs of
Contact the local NC Department of Environment and Natural
damage have occurred at the
Resources Regional Office.
outlet.
STORM-EZ 8/30/2019
Version 1.4 O&M Manual Page 4 of 5
DrY Deter fion Pond DegIO'Summary
Dry Pond Diagram
DRY POND ID FOREBAY MAIN POND
Temporary Pool El: Temporary Pool El:
Clean Out Depth: 0 Clean Out Depth: 0
Pretreatment Yes Sediment Storage El: Sediment Storage El:
Has Veg. Filter Yes Bottom Elevation: Bottom Elevation:
STORM-EZ 8/30/2019
Version 1.4 O&M Manual Page 5 of 5