Water Compliance Inspection Report
02/08/01
Permit Effective Date
07/07/31
Permit Expiration Date
Bryson Hydroelectric Plant
Name and Location of Facility Inspected (For Industrial Users discharging to POTW, also include
POTW name and NPDES permit Number)
Entry Time/Date
Exit Time/Date
Other Facility Data
Dam Rd Off US Hwy 19
Franklin NC 28734
Name(s) of Onsite Representative(s)/Titles(s)/Phone and Fax Number(s)
09:00 AM
09:40 AM
///
07/01/24
07/01/24
N
Section B: Facility Data
67 69 70 71 72 73 74 75 80
NCG500129 S
NPDES yr/mo/day Inspection Type InspectorTransaction Code
N
Fac Type
Remarks
Inspection Work Days QAB1Facility Self-Monitoring Evaluation Rating
C512311121718 19 20
21 66
---------------------------Reserved----------------------
07/01/24
Permit Operations & Maintenance Records/Reports Self-Monitoring Program
Facility Site Review
J Allen Stowe,Mail Code Ed13k - Duke Energy Corporation Charlotte NC
282011006//704-382-4309/
Name, Address of Responsible Official/Title/Phone and Fax Number
Yes
Contacted
Section C: Areas Evaluated During Inspection (Check only those areas evaluated)
Section D: Summary of Finding/Comments (Attach additional sheets of narrative and checklists as necessary)
(See attachment summary)
DateAgency/Office/Phone and Fax NumbersName(s) and Signature(s) of Inspector(s)
ARO WQ//828-296-4500 Ext.4658/Larry Frost
ARO WQ//828-296-4500/Keith Haynes
ARO WQ//828-296-4500 Ext.4659/Roy M Davis
EPA Form 3560-3 (Rev 9-94) Previous editions are obsolete.
Signature of Management Q A Reviewer Agency/Office/Phone and Fax Numbers Date
1Page #
07/01/24NCG500129
NPDES yr/mo/day Inspection Type
C
3 11 12 17 18
Section D: Summary of Finding/Comments (Attach additional sheets of narrative and checklists as necessary)
(cont.)1
Duke Energy’s Bryson Hydroelectric Powerhouse consists of the dam, powerhouse generation equipment,
central powerhouse sump and tailrace. The tailrace discharges to Tuckasegee River. The plant has
permitted discharges of generator thrust bearing cooling water and central powerhouse sump.
Mr. Keith Haynes and Mr. Larry Frost performed the inspection. The facility appeared to be well maintained
and operating properly. There were no un-permitted discharges noted during the inspection.
The purpose of the permit is to protect the receiving stream; therefore, the inspectors recommend that
Upstream, Effluent and Downstream sampling points be re-evaluated for this facility. The recommended
upstream sampling site should be at the dam inlet to the powerhouse, the effluent site from the tailrace and
the downstream at a predetermined (safe access) site downstream of the tailrace discharge point to the
stream. Possible sites were discussed during the inspection; it is recommended that these sites be
established by written policy.
Once the sampling sites are established, then the monitoring requirements and monitoring frequency for
each site should re-evaluated.
The proper reporting of flow from the powerhouse was discussed at length, during the inspection. Since
monitoring data is not required to be submitted to the State, the inspectors recommend that Duke Energy
use common units of measure for this type industry (examples discussed were; CFS and MGD, however
some other unit may be more appropriate) with regards to flow. If you should have any questions regarding
this issue please contact one of the inspectors.
Finally, a special word of thanks to Mr. Marcus Pitts for his assistance during the inspection.
2Page #
Compliance Evaluation
Bryson Hydroelectric Plant
01/24/2007
NCG500129
Inspection Type:
Owner - Facility:
Inspection Date:
Permit:
Yes No NA NEOperations & Maintenance
Is the plant generally clean with acceptable housekeeping?
Does the facility analyze process control parameters, for ex: MLSS, MCRT, Settleable Solids, pH, DO, Sludge
Judge, and other that are applicable?
Comment:
Yes No NA NEPermit
(If the present permit expires in 6 months or less). Has the permittee submitted a new application?
Is the facility as described in the permit?
# Are there any special conditions for the permit?
Is access to the plant site restricted to the general public?
Is the inspector granted access to all areas for inspection?