HomeMy WebLinkAbout20000390 All Versions_Information Letter_201001012-COD a390 UT Town Creek Mitigation Sites Sites 5 and 8 Rowan County TIP No. 1-2511 CA Site #5 provided 1,276 linear feet of stream channel. Construction was completed at Site #5 in December 2005 and planted in February 2006. The buffer was supplementally planted at Site 5 in February 2008 due to low survival of seedlings. The buffer was supplementally planted again at Site 5 in March 2009 due to beaver activity. Site 5 was monitored for 5 years from 2006 to 2010 and consisted of four permanent cross sections and a visual inspection of the stream stability and planted vegetation. During the 5 year monitoring period the site has flooded in August 2008 and January 2010. AW Site #8 provided 415 linear feet of stream channel. Construction was completed at Site #8 in December 2005 and planted in February 2006. Site #8 was monitored for 5 years from 2006 to 2010 and consisted of two permanent cross sections and a visual inspection of the stream stability and planted vegetation.