HomeMy WebLinkAbout20110428 Ver 2_Emails_20110620Dennison, Laurie
From: Mcmillan, Ian
Sent: Monday, June 20, 2011 12:56 PM
To: Dennison, Laurie; Strickland, Bev
Subject: FW: Raleigh St Construction Schedule
Hey, I need this one once it get processed. Thanks, Ian
lan J. McMillan, PWS, GISP
NCDENR/Division of Water Quality - Wetlands and Stormwater Branch
1650 Mail Service Center
Raleigh, NC 27699-1650
Office: (919) 807-6364
Fax: (919) 807-6494
Email: ian.mcmillannncdenr.Eov
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Myers, Sharon (Environment Health & Safety) [mailto:samyers@ehs.unc.edul
Sent: Monday, June 20, 20119:17 AM
To: Mcmillan, Ian
Subject: RE: Raleigh St Construction Schedule
Hi Ian,
That's sounds good. The application went out in the mail on Friday, so hopefully you will have it
today.
Sharon
From: Mcmillan, Ian [mailto:ian.mcmillan(abncdenr.govl
Sent: Monday, June 20, 20118:54 AM
To: Myers, Sharon (Environment Health & Safety)
Subject: RE: Raleigh St Construction Schedule
Sharon, I can issue by 6/22/11 if I get the application today, 6/20/11. - Ian McMillan
Ian J. McMillan, PWS, GISP
NCDENR/Division of Water Quality - Wetlands and Stormwater Branch
1650 Mail Service Center
Raleigh, NC 27699-1650
Office: (919) 807-6364
Fax: (919) 807-6494
Email: ian.mcmillan(?ncdenr.p_ov
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Myers, Sharon (Environment Health & Safety) jmailto:samyers0)ehs.unc.edu1
Sent: Friday, June 17, 20114:31 PM
To: Mcmillan, Ian
Subject: FW: Raleigh St Construction Schedule
Hi Ian,
I got your voice mail message about a turn-around of 2 weeks for the Raleigh St. 401 certification. I
also talked with the design engineer and she forwarded me the project schedule and time constraints
in the below email.
What do you think? Would it possible for us to start on other portions of the project (not in the area of
the proposed stream impact) or is that out of the question?
Sharon
From: Sheila Reeves Imailto:sreeves@rkk.com1
Sent: Friday, June 17, 20112:03 PM
To: Myers, Sharon (Environment Health & Safety)
Subject: Raleigh St Construction Schedule
Sharon,
Per our conversation ...here is list of the project construction schedule limitations:
June 20, 2011 Earliest project start date
June 22, 2011 Anticipated project start date
July 10-14, 2011 Water outages are NOT permitted by the contractor (project required waterline relocation
cannot occur during this time period)
July 29, 2011 Last day for construction completion, liquidated damages $1,000/day
Work hours shall be from 9am to 5pm on weekdays (Mon - Fri, or as otherwise approved by the University)
Sheila S. Reeves, PE
RK&K
900 Ridgefield Dr.
Raleigh, NC 27609
919.878.9560 P
919.790.8382 F
www.rkk.com
"RK&K" and "RK&K Engineers" are registered trade names of Rummel, Klepper & Kahl, LLP, a Maryland
limited liability partnership. This message contains confidential information intended only for the person or
persons named above. If you have received this message in error, please immediately notify the sender by return
email and delete the message. Thank you.