Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
20200987 Ver 1_More Info Received_20210115 (2)
Anchor QEA of North Carolina, PLLC ANCHOR 231 Haywood Street QEA ` 1 Asheville, North Carolina 28801 L-4— 828.281.3350 January 15, 2021 David Brown Regulatory Specialist/Geologist U.S. Army Corps of Engineers Wilmington District -Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, North Carolina 28801-5006 Re: Lake Adger Navigation Channel Maintenance Dredging Response to USACE Comments and Provision of Additional Information Action ID: SAW-2015-007888 Dear David: On behalf of the North Carolina Wildlife Resources Commission (NCWRC), Anchor QEA of North Carolina, PLLC, is pleased to provide this response to the U.S. Army Corps of Engineers' (USACE's) comments and provide additional information for the Lake Adger navigation channel maintenance dredging (Action ID: SAW-2015-007888). The comments and request for additional information' were in response to the Application for Department of the Army Permit Form 4345 (dated June 12, 2020; received by USACE June 16, 2020); Anchor QEA received them via email on September 14, 2020. Responses to Comments on Corps Comments and Request for Additional Information - Lake Adger Dredging Project, September 14, 2020 1. Submit an Alternative Analysis USACE Comment Received September 14, 2020: Under the Section 404(b)(7), the alternative analysis requires the applicant to demonstrate there are no practicable alternatives to the proposed discharge that would have a less adverse effect on the aquatic environment. Noncompliance with this requirement is sufficient basis for the Corps to deny the project permit. Also, the unavailability of practicable alternatives does not necessarily result in issuance of a permit. Compensatory mitigation cannot be used to satisfy the alternative analysis. The applicant must demonstrate to the Corps that the proposed project is the least environmental damaging practicable alternative (LEDPA) to achieve the project's purpose. The 1 USACE, 2020. Letter to: Robert Cork, Anchor QEA of North Carolina, PLLC. Regarding: Corps Comments and Request for Additional Information — Lake Adger Dredging Project. September 14, 2020. Lake Adger Maintenance Dredging -RTC from USACE_2021-01-15.docx January 15, 2021 Page 2 404(b)(1) guidelines requires selecting the LEDPA, provided it does not result in greater adverse environmental consequences. No discharge of dredge or fill material shall be permitted if there is a practicable alternative to the proposed discharge which would have less adverse impacts on the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences. Alternatives must be practicable, feasible, and accomplish the project's purpose and need. An alternative is practicable if it is available and capable of being done taking into consideration cost, existing technology, and logistics in light of overall project purpose. Alternatives not involving discharges into special aquatic sites are presumed available and have less adverse impact on aquatic ecosystem, unless clearly demonstrated otherwise. Special aquatic sites are sanctuaries and refuges; wetlands; mud flats vegetated shallows; coral reefs; and riffle and pool complexes. The analysis must include the no action alternative, the proposed project, and a sufficient number of alternatives to demonstrate the applicant has considered alternatives to the proposed project which may impact more or less aquatic resources. The analysis should clearly state each alternative and document the rational and findings of each alternative. Each alternative should state the extent of impacts to aquatic resources, effects to federally protected species and historic properties, estimated cost, and summarize the construction methodology and logistics. Based on the submitted information for the proposed project, the Lake Adger dredging project is considered water dependent by the Corps. The activity does require access or proximity to or sitting within special aquatic sites (wetlands) which are within the Corps' project Area. Therefore, you will not need to look at off -site alternatives in your analysis. Response on Behalf of NCWRC An alternatives analysis has been provided in Attachment A. 2. Final Design and Plans USACE Comment Received September 14, 2020: Provide final design and plans for the dredging and spoils disposal activities. The plans need to include a vegetation monitor plan for the new or enhanced wetlands of the spoils disposal areas. The plans should include the estimate volume of dredged material for the initial dredging episode and the expected volumes for future maintenance dredging episodes. January 15, 2021 Page 3 Response on Behalf of NCWRC The 90% Design Set is included as Attachment B. Final design, plans, and means -and -methods will be developed following selection of the dredging contractor. The 90% Design Set references the Wetland Monitoring Plan which is included as Attachment C. The wetland monitoring plan is not included in the 90% Design Set as it is expected to be issued as a separate contract from dredging activities. The 90% Design Set includes the estimated volume of dredged material for the initial 6,800 cubic yards dredging episode. The 90% Design Set does not include expected volumes of future maintenance dredging episodes as this volume will be dependent on future accretion rate which has not been estimated, however the 90% Design Set does include an estimate of placement area volumes. 3. Aquatic Resources USACE Comment Received September 14, 2020: Provide an evaluation and discussion of the existing conditions of the aquatic resources proposed to be impacted and how these resources will change based on the proposed project. Response on Behalf of NCWRC The existing conditions that will be impacted temporarily or permanently by the proposed dredging activities are open water and wetland areas. The existing and anticipated future conditions are summarized in the below table. The initial dredging project will result in a net increase of up to 3.0 acres of wetland. Area Type Impact Type Future condition Permanent Up to 3.0 acres will be established as wetland due to sediment placement. These due to placed areas will be planted with native plant species' and monitored for wetland materials establishmentz. Open water Temporary by Up to 14.0 acres will be impacted by dredging and construction activities. It is construction anticipated that benthic populations will naturally repopulate these areas within a activities year of dredging. Up to 4.2 acres of existing wetland will be temporarily impacted by construction activities. Temporary impacts will be minimized, where possible, to impacts related to alignment of hydraulic dredging discharge hoses, pedestrian access, and Temporary by minimal seepage of placed material through the containment structure. Wetland' construction Stockpiling of sediment on the wetlands will not be allowed, and no equipment activities will be placed or used on the wetland without prior approval by NCWRC. Any areas of temporarily impacted wetlands will be replanted where deemed necessary to repair impacted wetlands following construction activities, with native plant species' and monitored for wetland establishmentz. 1. Details of the plant species are presented in Sheet C8 of the 90% Design Set (Attachment B). 2. The wetland monitoring plan is included as Attachment C. 3. Wetland conditions are described in detail within the additional information package that supplemented Application for Department of the Army Permit Form 4345, submitted to the USACE (June 12, 2020). Specifically, see Attachments E and F. January 15, 2021 Page 4 4. FEMA Floodplain USACE Comment Received September 14, 2020: The project is located within the FEMA designated 700-year floodplain. The project must comply with applicable FEMA-approved state and local floodplain management requirements. Provide a copy of the approved FEMA permit or other documentation that indicate the project meets these requirements. Response on Behalf of NCWRC A Floodplain Development Permit, issued by the Floodplain Administration for Polk County (issued December 15, 2020) is provided in Attachment D. The permit requires that a no -rise certification is provided within 30-days of project completion. 5. Schedule USACE Comment Received September 14, 2020: Provide a schedule for the dredging and disposal area activities for the initial episode of dredging and an estimate of how often future dredging activities will be conducted. Response on Behalf of NCWRC The 90% Design Set (Attachment B) includes a Sequence of Construction for the dredging contractor. Dredging and wetland establishment for the initial dredging episode is anticipated to follow the following approximate schedule: • Weeks 1 and 2: Mobilization to Site, marking of delineated wetlands extents, preparation of wetland placement areas, and preparation for turbidity monitoring • Weeks 3 to 5: Dredging activities • Weeks 6 and 7: Demobilization and complete wetland placement activities • Week 7 for several months: Monitoring of wetland placement area settlement to determine planting timing, per wetland monitoring plan • Two weeks following adequate settlement: Wetland planting activities • Up to 2 years: Implementation of wetland monitoring plan The occurrence of future dredging activities will be dependent on rates of future accretion and needs to maintain the navigation channel; however, an initial estimate is that maintenance dredging will be required every 5 years. Response to Package of Public Comments Received from USACE on September 14, 2020 The USACE issued a 51-page PDF package (Attachment E) of comments that were received during the comment period of the public notice. USACE requested that Anchor QEA "review the comments January 15, 2021 Page 5 and submit to the Corps a document which responds/addresses the comments/concerns/issues noted." Table 1 includes a summary of comments and responses; the comments have been combined into similar comments where appropriate, with the total number of similar comments identified. Please do not hesitate to contact me at rcork@anchorqea.com or (828) 450-6435. Sincerely, Robert Cork, PE MEng Managing Engineer cc: NCDEQ-DWR — Sue Homewood, sue.homewood@ncdenr.gov NCWRC —Andrea Leslie, and rea.leslie@ncwildlife.orq NCWRC —Jeff Ferguson, jeff.ferguson@ncwildlife.orq Tables Table 1 Responses to Public Comments Attachments Attachment A Lake Adger Navigation Channel Maintenance Dredging Project Alternatives Analysis Attachment B 90% Design Submittal for Lake Adger Navigation Channel Maintenance Dredging Attachment C Lake Adger Navigation Channel Maintenance Dredging Project Wetland Monitoring Plan Attachment D Flood Plain Development Permit Attachment E Package of Public Comments Received from USACE on September 14, 2020 Attachment F Lake Adger Navigation Channel Maintenance Dredging Project Turbidity Monitoring Plan January 15, 2021 Page 6 Table 1 Responses to Public Comments Total Number of Similar No. Summary of Comment Comments Response 1. Proposed project would NOT occur in vicinity of the essential fish habitat designated by the South Atlantic Fishery 1 Comment noted. No response is required. Management Council, Mid -Atlantic Fishery Management Council, or the NMFS. No further action/review is planned by NOAA. The position is neither supportive or in opposition to proposed work. 2. The application notes that a wetland monitoring plan will be developed with input from the resource agencies. We 2 The wetland monitoring plan is included as Attachment C. request that a detailed and complete monitoring plan for wetland impact areas be finalized prior to issuance of approvals. The Division acknowledges that the applicant's intent is to enhance and/or create wetlands as a result of this project, however the Division recommends that this should be monitored and that a detailed course of action should be developed should the project inadvertently cause a loss of wetlands. We recommend that the monitoring plan include a requirement for a new jurisdictional determination (in areas of dredge spoil fill) and that NCWAM evaluations be conducted to ensure that the wetlands to be filled by dredge material do not lose jurisdiction or incur a degradation of function. We recommend that any approvals include a condition that should either [result in] loss of jurisdiction or loss of function, the Permittee would be required to provide a mitigation plan to compensate for the loss. The creation of new wetland areas within the lake may be proposed as "permittee responsible mitigation" provided they satisfy mitigation site criteria at the time of proposal. The vegetation monitoring plan should be developed with the input of NCDWR, US Army Corps of Engineers, and NCWRC. 3. The Division recommends that the applicant provide a detailed phasing and/or construction sequencing plan proposed 2 A detailed phasing and/or construction sequencing plan will be developed in consultation with the selected dredging for this project. For instance, will dredging activities be confined within certain portions of the lake until contractor (i.e.: following completion of the contractor bidding process). In general, dredging and wetland establishment for completion/before progressing to the next work area? How does the construction sequencing tie into the containment the initial dredging episode is anticipated to follow the below approximate schedule: system design and turbidity monitoring proposals? . Weeks 1 and 2 — Mobilization to Site, marking of delineated wetlands extents, preparation of wetland placement areas, The NCWRC should detail the anticipated timeframe the lake Adger Main Marina and the recreational navigation and preparation for turbidity monitoring channel may be off limits to the public. • Weeks 3 to 5 — Dredging activities • Weeks 6 and 7 — Demobilization and complete wetland placement activities • Week 7 for several months — Monitor wetland placement area settlement to determine planting timing, per wetland monitoring plan • Two weeks following adequate settlement — Wetland planting activities • Up to two years — Implement wetland monitoring plan It will be the goal of the dredging activities to minimize public exclusion from the navigation channel and to maintain access to the public boat ramp. It is estimated that the navigation channel may be off limits to the public for up to 3-weeks, although efforts will be made during this time to maintain some access to the Lake. Dependent on the selection of means - and -methods by the contractor and pending approval by the project engineers and stakeholder discussions, dredging activities may require the Lake to be drawn down, which may limit access from the navigation channel to the Lake. 4. The Division recommends that a more detailed and robust turbidity monitoring plan is necessary and will coordinate 2 The turbidity monitoring plan has been updated and is included as Attachment F. with the applicant during 401 application review. The turbidity monitoring and contingency plan should be revised with the input of NC Division of Water Resources (NCDWR). 5. The applicant mentions future routine dredging activities to be covered by this approval. The Division recommends that 1 Comment noted. It is anticipated that USACE will address this comment with conditions to the permit, if approved. prior to commencement of any future dredging or disposal activities the areas to be used for disposal should be re- January 15, 2021 Page 7 Total Number of Similar No. Summary of Comment Comments Response evaluated by the regulatory agencies and may require updated jurisdictional determinations and/or NCWAM evaluations, and that updated monitoring plans to be developed for each future area which is proposed to impact wetlands, and should be conditioned to require mitigation of any future loss of jurisdiction or function as noted above. 6. Aware of no historic resources which would be affected by the project. Therefore, we have no comment on the project 1 Comment noted. No response is required. as proposed. 7. Our Historic Preservation Office reviewed this project, cross referenced the project's legal description against our 1 Comment noted. No response is required. information, and found no instances where this project intersects or adjoins such resources. Thus, the Nation does not foresee this project imparting impacts to Cherokee cultural resources at this time. 8• The Cherokee Nation requests that the USACE halt all project activities immediately and re -contact our Offices for 1 A requirement will be added to the construction specifications and 100% Design Plans that "all project activities will be further consultation if items of cultural significance are discovered during the course of this project. immediately halted and the Cherokee Nation Tribal Historic Preservation Office contacted for further consultation if items of cultural significance are discovered during the course of this project." 9. Project activities should not impact wild trout reproduction, and a moratorium is not needed. 1 Comment noted. No response is required. 0. Recommend adding Needle Spikerush and Silky Willow to the wetland plant list and Persimmon and Black Gum to the 1 These plant species have been added to the planting plans in the 90% Design Set. upland plant list. 1. Herbivory control fencing should consist of fabric that will not trap animals. NCWRC can recommend types. 1 Selection of herbivory control fencing (if required) will be addressed within specifications for vegetation planting, which will be developed following project approval. NCWRC will be consulted for recommended options. 2. Although the text notes that 3.9 acres of area will be used for sediment placement, Sheet C5 notes that 1.1 acres of 1 The placement area design has been modified in the 90% Design Set to remove the direct placement of dredged material on wetland and 3.0 acres of open water will be impacted by fill, which totals 4.1 acres. These differences should be wetland (see Sheet C6 in the 90% Design Set). rectified. 3. Request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk 10 NCWRC will plan to host a stakeholder meeting with a focus on the plans for maintenance dredging of the navigation County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other channel, use of dredged material for lake habitat enhancement and boat ramp operations and maintenance. Due to COVID interested parties like members of the fishing and boating community to receive feedback and input on the details of protocols, the meeting will need to be virtual and limited to representatives from each stakeholder group. the project including timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. 4. We support the strongest and most protective methods to contain and dewater material used to construct wetlands. 10 Various alternatives for sediment containment within the dredge material placement area were considered. The alternatives While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber analysis (Attachment A) presents several of these options. The 90% Design Set (Attachment B) includes options such as biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the haybales and coir fiber biologs. The selected contractor will submit selected means -and -methods, which will be reviewed project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these and approved by the project engineer. impacts can be mitigated. The use of haybales and coir fiber biologs has been recommended instead of inorganic or less degradable materials (such as We request the original materials approved by the Commissioners for sediment containment be used as opposed to geotubes, rock, or wood cribs) for many reasons including less construction equipment needed on the wetland area during hay bales in the plan. Refer to Option 2 - In Water Replacement - Berm Construction Alternatives - Pg. 10 of March 18, placement, the need to import materials such as rock or timber), the possibility of introducing non -biodegradable materials 2018. into the environment (in the case of geotubes and geofabrics), and the challenge of placing heavier materials on the in situ soft sediment. 5. Request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water 12 Water Willow has been removed from the planting list in the 90% Design Set. Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Wetland Plantings: a. We would request that Water Willow be removed from the wetland planting list. b. Polk County Commissioners are waiting on recommendation from Lake Adger POA citizens - On December 2, 2019, NCWRC requested Polk County Commissioners to allow planting of Water Willow into Lake Adger as a Test Site. The Commissioners deferred until Lake Adger Property Owners Board and its citizens can make a recommendation to the January 15, 2021 Page 8 Total Number of Similar No. Summary of Comment Comments Response Commissioners. Due to COVID-19; efforts to inform citizens, investigate further, and make such recommendation to Commissioners has stalled. c. Willow Weed should not be introduced as part of this project. It is not native to Lake Adger. d. We request that this application not approve specific plant species. NCWRC should be required to consult stakeholders on final plantings. 6. Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in 10 The proposed placement of dredged sediment within the Lake Adger footprint is designed as beneficial use for habitat lake levels. creation, including wetland creation and enhancement, or creation of upland areas. Once established, wetland conditions will be more ecologically diverse than the existing mud -flat conditions, and create additional habitat for bird and fish species. Additionally, NCWRC reviewed this proposed project and has not identified species that may be significantly impacted by these operations when considering the daily fluctuation in water level that the Lake experiences through power generation operations, and that "project activities should not impact wild trout reproduction, and a moratorium is not needed." 7. NCWRC should consider opportunities to expand and improve public access and education in the project area, such as 10 The agreement between NCWRC and Lake Adger Property Owners Association (LAPOA) is specific to public use of the boat boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological ramp and parking area, and maintenance dredging of the existing navigation channel from the ramp to deep water of Lake significance of the Green River and surrounding area. Adger. Additional facilities such as boardwalks and fishing piers exceed the scope of the agreement and could not be funded as part of this project. NCWRC will develop educational signage with a map of Lake Adger, information on fish and wildlife species and the ecological significance of the area to be installed at the public boat launch. 8. NCWRC should clearly communicate project details and timelines with the public as plans are finalized. 10 NCWRC will work with Polk County and LAPOA to establish channels for providing updates and information regarding project details and timelines. 9. Suggest adding silt curtains around the dredging area, not just around the wetland construction area and reducing the 12 Project design engineers and regulatory agency representatives have developed a turbidity monitoring plan (Attachment F) impact trigger from 100 NTU's to 75 NTU's. Additionally, if the trigger is activated, project specifications should clearly that will be implemented as an element of the dredging operations and will allow a response if sediment management call for ceasing all operations until corrective actions are enacted and the turbidity levels return to 50 NTU's or below. conditions are not as anticipated by the design engineers. Hydraulic dredging typically stirs up less sediment than Corrective operations must be initiated and not simply reviewed or monitored more frequently. mechanical dredging due to the suction at the intake, and project conditions (i.e., shallow even dredge cuts and low -flow conditions in Lake Adger) are expected to result in limited distribution or temporarily suspended sediment. Full time implementation of turbidity curtains around the dredging operation will add significant cost to the project, and this practice will be reserved in the event that turbidity measurements at stations defined in the monitoring plans indicate levels in excess of state water quality standards for lakes. Design plans include the installation of permanent (biodegradable) sediment barriers installed around the placement areas. 0. Request that NCWRC consult with the LAPOABOD prior to the selection of the final plantings contained on page 14 of 1 NCWRC and our project design engineers have taken comments into consideration regarding final plantings of the habitat the plan to make certain any native species selected do not become invasive. areas. The final plant list is based on surveys of reference wetlands in the forebay of Lake Adger and the mouth of Green River. An updated planting list can be distributed during a planned virtual stakeholder meeting. The distribution of plant species may be dependent on supplies that the planting contractor has available. 1• Concerning Cells BI and Cl - Protection of Culvert Between These Cells 1 Sediment will not be placed in cells 131 and C1 during initial maintenance dredging proposed for 2021 and further a. Placement and breakdown of these cell materials could over time clog or close off the drainage culvert running assessment will occur prior to future dredging events. under Silver Creek Road. Based on two-dimensional hydraulic modelling of placement in Cells Al and A2 using the USACE River Analysis System b. Clogging of this drainage culvert could directly create flooding of Polk County Tax Parcels #1- P54-199, #2- P54- (HEC-RAS), no significant modifications will occur to flow along Lake Adger Road or Silver Creek Road. HEC-RAS modelling 356, #3 - P54-132, and #4- P54-133 as identified on Impacted Parcels presentation enclosed. also indicates that once stabilized and vegetated, the maximum flow velocities are not anticipated to result in erosive c. Clogging of this drainage culvert could also result in flooding of Silver Creek Road at that point during heavy rain conditions greater than those that currently occur in the area, and therefore the constructed cells will be relatively stable. events that happen often. d. We request that this plan address this potential issue. 2• Concerning Cell Al - Approximate Area of Disturbance 1 Based on HEC-RAS modelling, the construction of the wetland areas will not significantly alter or impede the flow into Lake a. According to Plan C5, it appears that the upstream flow from the Green River will be negatively impeded from Adger. flowing into the Lake Adger. January 15, 2021 Page 9 Total Number of Similar No. Summary of Comment Comments Response b. Water must not be impeded from entering Lake Adger during this project which would negatively endanger wildlife and water quality. 3• Concerning Cell 131 - Choking off Permanent Green River flow into Lake Adger 1 Per the 90% Design Set, the placement of sediment will not occur within main flow channels, and will be contained by a. There would appear to be some danger that Cell 131 will eventually close off the branch of flow nearest Silver Creek temporary structures and long-term vegetation establishment. Road leaving only one feed into the lake. Based on HEC-RAS modelling, the placement of dredge material in Cells Al and A2 will not significantly modify flow along b. Concerns this reduction of flow will result in less turnover replacement of water in the lake resulting in stagnation, the northern channel of the Green River nearest Lake Adger Road (aka Silver Creek Road). HEC-RAS modelling also indicates reduced lake levels, and degradation to the quality of the water. that once stabilized and vegetated, the maximum flow velocities are not anticipated to result in erosive conditions greater than those that currently occur in the area, and therefore the constructed cells will be relatively stable. Sediment will not be placed in cells 131 and C1 during initial maintenance dredging proposed for 2021 and further assessment will occur prior to future dredging events. 4. Redirecting All Sediment Away from the Marina 1 Based on HEC-RAS modelling, neither the dredging from the navigation channel or placement within cells Al and A2 will a. This plan appears to recommend redirecting all sediment to travel into the deeper middle channel of the lake. result in significant changes to current sediment accretion locations. b. If allowed to occur, the sediment from upstream will then build up significantly in a new place. NCWRC is not under contract to have to dredge that portion of the lake. This would inevitably leave Polk County with the responsibility and expense of dredging. c. We request that Polk County Commissioners and citizens be made aware of this future impact before approval of application. Public Meeting 1 Due to the limited scope of the channel maintenance dredging project and COVID protocols, a public meeting prior to a. We request that a public meeting be held before application approval. application approval is unlikely. NCWRC will organize and host a virtual meeting that will include representatives from b. Citizens were denied ability to ask questions of NCWRC following the March 18, 2019, presentation to Polk County stakeholder groups including LAPOA, Polk County, Northbrook Energy, and MountainTrue. Commissioners. c. Citizens were promised by then Commission Chair Melton an opportunity to question NCWRC once a new plan application was submitted. d. As USACE does not individually respond to concerns and comments sent to them as part of public comment, citizens were not previously allowed to ask questions, and a promise was made to the citizens that questions would be allowed once the plan was developed for USACE application submission; we believe a public meeting would benefit this project. 5. The lake channels toward the Green River are getting hard to navigate due to the sediment. 3 NCWRC is responsible for maintaining adequate water depths for the public boat ramp and marina under an agreement Odd metal poles stick up in the water on the river side? When levels are low, they seem dangerous. with Polk County. This proposal is for maintenance dredging within the Lake Adger navigation channel to remove accumulated sediment. The navigation channel provides public boat access from the boat ramp at the western end of the Concerned about the area around the marina and the inlets along Silver creek are dry, muddy, and unkempt; low water lake to the main lake and is adjacent to the Lake Adger marina. Areas outside of the navigation channel will not be dredged levels resulting in limited boat access (no warning signs); slips are empty and houses aren't selling due to condition of within this proposed project. Within the navigation channel dredging will occur with obstructions removed as appropriate, lake. Commenter Does not support plan and does not understand proposal. and the channel will be remarked with new buoy placements. 6. Can we obtain a copy of the Lake Adger wetland survey? 1 Documents relating to the wetland survey were included within the additional information package that supplemented Application for Department of the Army Permit Form 4345, submitted to the USACE (June 12, 2020). Specifically, see Attachments E and F. Attachment A Lake Adger Navigation Channel Maintenance Dredging Project Alternatives Analysis Anchor QEA of North Carolina, PLLC 231 Haywood Street Asheville, North Carolina 28801 828.281.3350 ALTERNATIVES ANALYSIS Lake Adger Navigation Channel Maintenance Dredging Project Anchor QEA of North Carolina, PLLC ANCHOR ,� SIZ QEA ` L-4-1 December 18, 2020 This alternatives analysis was developed to support a permit application for the Lake Adger Navigation Channel Maintenance Dredging Project (Lake Adger Project) compliant with permit requirements under Section 404(b)(1) of the Clean Water Act. In its review of the North Carolina Wildlife Resources Commission (NCWRC)'s permit application for the proposed Lake Adger Project, the U.S. Army Corps of Engineers (USACE) requested' NCWRC analyze alternatives to the proposed project to "demonstrate there are no practicable alternatives to the proposed discharge that would have a less adverse effect on the aquatic environment" (i.e., "the proposed project is the least environmental damaging practicable alternative [LEDPA] to achieve the project's purpose"). This alternatives analysis for the Lake Adger Project includes a summary of information requested in USACE's comment letter. As stated by USACE in their September 14, 2020, comment letter, the Lake Adger Project is "considered water dependent [and] require[s] access or proximity to or sitting within special aquatic sites (wetlands) which are within the Corp's project Area. Therefore [this alternatives analysis does] not need to look at off -site alternatives." This analysis summarizes the proposed alternative and presents four additional alternatives that were considered during development of the 30% Design Submittal, with rationale for why each of the considered alternatives was not selected. Summary of Proposed Alternative Per the Application for Department of the Army Permit Form 4345 (dated June 12, 2020; received by USACE June 16, 2020), the proposed alternative includes an initial dredging event to remove 6,800 cubic yards (cy) of soft sediment from the navigation channel, with placement of the soft sediment within the Lake Adger footprint as beneficial use for habitat creation, including wetland creation and enhancement, or creation of upland areas. The dredged material placement areas will be bounded by an initial containment structure designed to hold the sediment in place. This initial structure will be constructed of biodegradable and/or temporary containment materials (e.g., coir fiber biologs, haybales, or an equally effective alternative). Secondary turbidity controls (e.g., silt fences or silt curtains depending on water levels) will assist with sedimentation control. Following dredged material placement, native emergent wetland and upland species identified at the nearby reference wetlands will be planted on the dredged material to stabilize the material and provide U.S. Army Corps of Engineers, Wilmington District, Subject: Corps Comments and Requests for Additional Information — Lake Adger Dredging Project, Action ID: SAW-2015-007888. September 14, 2020. December 18, 2020 Page 2 ecological benefits. In addition to the planting, the site will be seeded with a wetland seed mix containing a variety of obligate and facultative wetland species to provide additional species diversity and ground cover. The proposed alternative will improve the long-term environment to the aquatic ecosystem through the development of additional wetlands. The following summary information was requested by USACE in their September 14, 2020, comment letter to support evaluation of this alternative: • Extent of Impacts to Aquatic Resources — 21.2 acres • Effects to Federally Protected Species and Historic Properties — None • Estimated Cost — $1,300,000 to $1,800,000 • Summary of Construction Methodologies and Logistics — Sediment will be dredged using hydraulic dredging equipment — Dredged material slurry will be pumped through pipeline and discharged within the designated dredged material placement areas — Dredged material placement areas will be constructed using a combination of coir logs, haybales, or equally effective alternative as sediment containment with secondary turbidity measures of silt fences, silt curtains, or similarly effective materials — Native emergent wetland and upland species identified at the nearby reference wetlands will be planted on the dredged material to stabilize the material and provide ecological benefits Other Alternatives Considered The following alternatives were considered in addition to the proposed alternative: • No action • Deep -water placement within Lake Adger • Placement in an upland confined placement area • Alternative dredged material placement methodologies within the proposed dredged placement areas • Construction of Permanent Containment Structure Around the Proposed Dredged Placement Areas No Action The navigation channel provides public boat access from the boat ramp at the western end of the lake to the main lake and is adjacent to the Lake Adger marina. The accretion of sediments within the navigation channel has resulted in difficult transit for waterway users attempting to safely access Lake Adger. Channel deepening is required to facilitate a safe navigable access channel to Lake Adger. NCWRC is responsible for maintaining adequate water depths for the public boat ramp and marina under an agreement with Polk County. December 18, 2020 Page 3 This alternative was not selected due the NCWRC agreement to maintain the navigation channel, and the public support for doing so in a safe manner. The following information was requested by USACE to support evaluation of this alternative: • Extent of Impacts to Aquatic Resources — None • Effects to Federally Protected Species and Historic Properties — None • Estimated Cost — $0 • Summary of Construction Methodologies and Logistics — Not applicable Deep -Water Placement Within Lake Adger This alternative would consist of dredging approximately 6,800 cy of sediment from the navigation channel, with dredged material placement in deep -water portions of Lake Adger. The redistribution of sediment associated with this alternative would be expected to contribute to ongoing sediment buildup behind the Turner Shoals hydroelectric dam and within the Lake Adger aquatic system, result in ecological impacts, and reduce the effective storage capacity of the water -supply reservoir. It is anticipated that deep -water placement of dredged material in Lake Adger would contribute to the need for future Lake dredging activities that would be costly, result in future additional impacts to aquatic resources, and require identification of an alternative placement area. This alternative was not selected due to the potential for future dredging work being required from deep -water portions of Lake Adger. The following information was requested by USACE to support evaluation of this alternative: • Extent of Impacts to Aquatic Resources — estimated 20 to 30 acres depending on the distribution of placement • Effects to Federally Protected Species and Historic Properties — None • Estimated Cost — $1,000,000 (excluding potential future re -dredging work) • Summary of Construction Methodologies and Logistics — Sediment would be dredged using hydraulic or mechanical dredging equipment and material would be placed into a dredged material scow — Material would be placed using a long -reach excavator positioned onshore or on a barge Placement in an Upland Confined Placement Area This alternative would consist of dredging approximately 6,800 cy of sediment from the navigation channel, with dredged material placed in a confined placement area located immediately adjacent to Lake Adger. The public parking area adjacent to the boat ramp is the most suitable location for this alternative; however, this area cannot be practicably converted into an upland confined placement area without compromising and limiting the functionality of the public parking lot. Additionally, this December 18, 2020 Page 4 option would require dewatering operations resulting in additional cost and turbidity control requirements This alternative was not selected due to no appropriate placement area being identified immediately adjacent to Lake Adger. The following information was requested by USACE to support evaluation of this alternative: • Extent of Impacts to Aquatic Resources — 5.5 acres (assuming no special aquatic sites, such as wetlands, are impacted by the construction and operation of an upland confined placement area) • Effects to Federally Protected Species and Historic Properties — None (assuming no federally protected species or historical properties would be impacted in the upland confined placement area) • Estimated Cost — $1,500,000 to $4,000,000 • Summary of Construction Methodologies and Logistics — Sediment would be dredged using hydraulic or mechanical dredging equipment • If hydraulic dredging equipment is used, dredged material would be transported via pipeline and discharged within the upland confined placement area; dewatering would be required (e.g., geotubes or filter presses) to handle the quantity of water generated • If mechanical dredging equipment is used, dredged material would likely be transported in a scow; a long -reach excavator positioned in the uplands would be used to offload dredged material into the confined placement area Alternative Dredged Material Placement Methodologies within the Proposed Dredged Placement Areas This alternative would consist of dredging approximately 6,800 cy of sediment from the navigation channel, with dredged material placement in the same proposed dredged material placement as in the proposed alternative. The methodology for placement would differ from the proposed alternative as dredged material would be placed using mechanical methods such as a long -reach excavator operating from a barge or constructed work area or an amphibious excavator. This equipment would have limited placement reach, result in impacts to the placement areas, and require construction of a staging area within the existing wetlands. Additionally, the transfer of dredged sediment to the placement construction equipment would result in increased risk of turbidity impacts and transfer of the sediment in less confining equipment such as a scow rather than within a hydraulic transfer hose. This alternative was not selected because the equipment necessary to complete this work would be more invasive and destructive of special aquatic areas (i.e., wetlands and mudflats) during construction than the placement methodologies in the proposed alternative. December 18, 2020 Page 5 The following information was requested by USACE to support evaluation of this alternative: • Extent of Impacts to Aquatic Resources — 21.2 acres (same as proposed) • Effects to Federally Protected Species and Historic Properties — None • Estimated Cost — $1,300,000 to $3,000,000 • Summary of Construction Methodologies and Logistics — Mechanical dredging with placement in a dredged material scow — Dredged material offloading facility to move material from scows into dredged material placement area. — Dredged material placement area construction using biodegradable and/or temporary containment materials (e.g., coir fiber biologs, haybales, or an equally effective alternative) — Material placement within the designated dredged material placement areas using a long -reach excavator or an amphibious excavator — Native emergent wetland and upland species identified at the nearby reference wetlands will be planted on the dredged material to stabilize the material and provide ecological benefits Construction of Permanent Containment Structure Around the Proposed Dredged Placement Areas This alternative would consist of constructing the containment structure from inorganic or less degradable materials, such as geotubes, rock, or wood cribs. The use of inorganic materials found in geotubes or matting will likely result in damaged and partially broken-down material entering the environment, as removing them from the containment area following settlement will be extremely difficult. Additionally, placement and use of these products within the placement area will require additional construction traffic within the placement area that can lead to unnecessary ecological disturbances. Biodegradable geotubes are a relatively new technology, but are less suitable for containing fine sediment, and the biodegradable materials have a lower strength that may reduce containment success. Less biodegradable, natural options such as rock or wood cribs would require the import of materials from off site. The placement of these materials in a configuration to contain placed dredged material would be difficult on the in situ soft sediments. Their additional weight (compared to biodegradable alternatives such as coir tubes) would likely require additional material to build a foundation prior to constructing the containment structure. The use of timber will be difficult to secure during flood events, and likely require a secondary layer of geofabric to contain sediment. This alternative was not selected because the equipment necessary to complete this work would be more invasive and destructive of special aquatic areas (i.e., wetlands and mudflats) during December 18, 2020 Page 6 construction, and the import of either biodegradable or non -biodegradable materials from off site will introduce materials into the environment that will have an undetermined long-term effect. The following information was requested by USACE to support evaluation of this alternative: • Extent of Impacts to Aquatic Resources — approximately 25 acres (same as proposed, with additional operational areas required and larger containment structure) • Effects to Federally Protected Species and Historic Properties — None • Estimated Cost — $1,300,000 to $3,000,000 • Summary of Construction Methodologies and Logistics — Sediment will be dredged using hydraulic dredging equipment — Dredged material slurry will be pumped through pipeline and discharged within the designated dredged material placement areas — Dredged material placement areas will be constructed using either inorganic or less degradable materials as sediment containment with secondary turbidity measures of silt fences, silt curtains, or similarly effective materials Conclusion Six alternatives were evaluated on the basis of cost, environmental impact, constructability and implementability. Based on this evaluation the alternative proposed in the Application for Department of the Army Permit Form 4345 would have a less adverse effect on the aquatic environment while being implementable and constructible. The proposed project is the LEDPA to achieve the project's purpose. Attachment B 90% Design Submittal for Lake Adger Navigation Channel Maintenance Dredging 90% DESIGN SUBMITTAL LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING NORTH CAROLINA WILDLIFE RESOURCES COMMISSION i� s� ,aa bm F't Co�lar1s �Q Sunny V€ew pe9an �J p ynA rarme `�F70 NORTH CAROLINA Asheville • Charlotte Raleigh Project NOT TO SCALE DRAWING INDEX SHT # DWG # TITLE 1 G1 TITLE SHEET 2 G2 GENERAL NOTES, LEGEND, AND ABBREVIATIONS 3 E1 EXISTING CONDITIONS 4 C1 DREDGE PLAN 5 C2 PROFILE 6 1C3 ISECTIONS 7 C4 DREDGED MATERIAL PLACEMENT LAYOUT 8 C5 TURBIDITY MONITORING LOCATIONS 9 CIS IMPACTED AREAS 10 C7 DETAILS 11 C8 VEGETATION PLANTING DETAILS and Ra �� PROJECT LOCATION z ye Fo- � per ? qa �1un Rd 3 yi ,a NORTH z 0 4000 8000 Mill SPring 3 0 >w SCALE IN FEET o z SOURCE: ©2019 Microsoft Corporation ©2018 HERE z a Z o VICINITY MAP = <� V w a Z m Z O Z O s V z O w V - Z Z - V N w O � V w I QV Z_ DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH REV DATE BY APPD DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION G1 T p 7'y A �T� �-y ®p( ANCHOR al�vi` CAROLINA , , KROW whan, below. Call before yaudig. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING - IDEA i �`/ /' RESOURCES APPROVED BE: DIN (COLA, W. COMMISSION SCALE: AS NOTED DATE: JANUARY 2021 TITLE SHEET SHEET# 7 OF 77 GENERAL NOTES FOR MAINTENANCE DREDGING 1. THE CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS BEFORE BEGINNING CONSTRUCTION AND WILL IMMEDIATELY INFORM NCWRC OF ANY DISCREPANCIES FOUND BETWEEN THE PROJECT PLANS AND CONTRACT SPECIFICATIONS PRIOR TO PROCEEDING WITH THE WORK. 2. CONTRACTOR SHALL STRICTLY ENFORCE ALL APPLICABLE HEALTH AND SAFETY LAWS (I.E. OSHA) AND MAINTAIN SITE SECURITY. 3. CONSTRUCTION KICK-OFF MEETING WITH THE NORTH CAROLINA WILDLIFE RESOURCES COMMISSION, THE ENGINEER AND OTHER RELEVANT STAKEHOLDERS IDENTIFIED IS REQUIRED PRIOR TO ANY ONSITE WORK. 4. CONTRACTOR SHALL PROVIDE A SEQUENCE OF CONSTRUCTION TO BE APPROVED BY THE NORTH CAROLINA WILDLIFE RESOURCES COMMISSION, AND THE ENGINEER PRIOR TO SITE MOBILIZATION. 5. CONTRACTOR SHALL PROVIDE THE FOLLOWING SUBMITTALS TO BE APPROVED BY NCWRC PRIOR TO SITE MOBILIZATION: • HEALTH AND SAFETY PLAN • DREDGING AND DREDGED MATERIAL PLACEMENT WORK PLAN, INCLUDING MEANS -AND -METHODS TO PROTECT EXISTING WETLAND • SURVEY WORK PLAN • PROJECT CONSTRUCTION SCHEDULE • CONTRACTOR QUALITY CONTROL PLAN • SPILL PREVENTION PLAN • PRE -CONSTRUCTION SURVEYS. 6. CONTRACTOR SHALL FIELD VERIFY THE EXISTING CONDITIONS WITHIN THE LIMITS OF WORK AND WILL BE RESPONSIBLE FOR DETERMINING APPROPRIATE QUANTITIES AND REQUIRED MATERIALS TO COMPLETE THE WORK. 7. CLEARING TO BE LIMITED TO THE LIMIT OF DISTURBANCE AS SHOWN ON THE PLANS. WORK SHOULD LIMIT TREE REMOVAL BY WORKING AROUND EXISTING TREES AS POSSIBLE. CONTRACTOR MUST RECEIVE APPROVAL FROM NCWRC PRIOR TO REMOVAL OF ANY TREES. 8. ANY TREES DAMAGED OR REMOVED DURING THE WORK SHALL BE REPLACED BY THE CONTRACTOR WITH THE SAME SPECIES OR SIMILAR AS APPROVED BY NCWRC. 9. THE HORIZONTAL DATUM SHALL BE BASED ON NORTH CAROLINA STATE PLANE, NAD83, U.S. SURVEY FEET. THE VERTICAL DATUM SHALL BE BASED ON NAVD88. THE HYDROGRAPHIC SURVEY WAS COMPLETED BY HAYES, JAMES & ASSOCIATES, INC., IN OCTOBER 2018. 10. INFORMATION CONCERNING UNDERGROUND UTILITIES WAS OBTAINED FROM AVAILABLE RECORDS, BUT THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING EXACT LOCATIONS AND ELEVATIONS OF THE LINES BY DIGGING TEST PITS BY HAND AT ALL UTILITY CROSSINGS, WELL IN ADVANCE OF TRENCHING. IF CLEARANCES ARE LESS THAN SHOWN OR SIX (6) INCHES, WHICHEVER IS LESS, CONTACT NCWRC IMMEDIATELY. 11. CALL "NORTH CAROLINA 811" AT 811 OR 1-800-632-4949 FORTY-EIGHT (48) HOURS PRIOR TO BEGINNING EXCAVATION OR DREDGING TO DETERMINE THE EXACT LOCATION OF EXISTING UTILITIES. 12. ADDITIONAL UNDERWATER UTILITIES MAY EXIST ELSEWHERE WITHIN THE PROJECT EXTENTS. CONTRACTOR SHALL FIELD VERIFY ANY IN -WATER UTILITIES, CROSSINGS OR POTENTIAL IMPEDIMENTS TO THE WORK AND TAKE ADEQUATE PRECAUTIONS TO AVOID THEM. 13. REPAIR TO UTILITIES OR PROPERTY DAMAGE AS A RESULT OF THE CONTRACTOR'S NEGLIGENCE OR METHOD OF OPERATION MUST BE MADE AT THE CONTRACTOR'S EXPENSE BEFORE CONTINUING WITH CONSTRUCTION. 14. ANY DAMAGES THAT MAY OCCUR TO REAL PROPERTY OR EXISTING IMPROVEMENTS SHALL BE RESTORED BY THE CONTRACTOR TO AT LEAST THE SAME CONDITION THAT THE REAL PROPERTY OR EXISTING IMPROVEMENTS WERE IN PRIOR TO THE DAMAGES. THIS RESTORATION SHALL BE SUBJECT TO THE OWNER'S APPROVAL; MOREOVER, THIS RESTORATION SHALL NOT BE A BASIS FOR ADDITIONAL COMPENSATION TO THE CONTRACTOR. RESTORATION SHALL INCLUDE, BUT NOT BE LIMITED TO, REGRASSING, REVEGETATION, REPLACING FENCES, REPLACING TREES, ETC. 15. ALL UPLAND GRADING SHALL BE DONE IN SUCH A MANNER AS TO PROVIDE POSITIVE DRAINAGE. 16. DISTURBED UPLAND AREAS SHALL BE GRADED AND RESTORED TO ORIGINAL CONDITIONS. DISTURBED AREAS ADJACENT TO ESTABLISHED LAWNS SHALL BE SODDED. OTHER DISTURBED AREAS SHALL BE SEEDED AND MULCHED. ALL DISTURBED AREAS ARE TO BE STABILIZED AND SEEDED WITHIN 14 DAYS OF DISTURBANCE UNLESS OTHERWISE NOTED. SLOPES STEEPER THAN 3:1 MUST BE STABILIZED IN 7 DAYS. INSTALL TEMPORARY SEEDING ON ALL AREAS THAT WILL BE LEFT IDLE FOR MORE THAN 14 DAYS. HARD WOOD MULCH IS AN ACCEPTABLE TEMPORARY COVER BUT MAY NOT BE BLENDED INTO THE SUBGRADE AND WILL BE REQUIRED TO BE REMOVED PRIOR TO CONTINUATION OF THE WORK. STRAW MULCH AND TALL FESCUE SHOULD NOT BE USED IN RIPARIAN AREAS. 17. THE CONTRACTOR SHALL PROTECT ALL UTILITIES, AND EXISITNG INFRUSTRUCTURE DURING CONSTRUCTION, AND ALL WETLANDS DURING CONSTRUCTION OPERATIONS. 18. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE WETLAND BOUNDARIES ARE UNDERSTOOD PRIOR TO BEGINNING WORK. 19. THE CONTRACTOR SHALL OBEY ALL COUNTY HEIGHT, WEIGHT AND UNDERCLEARANCE RESTRICTION S.TH E CONTRACTOR SHALL OBEY ALL APPLICABLE NOISE RESTRICTIONS. 20. ALL SITE ACTIVITIES INCLUDING BUT NOT LIMITED TO CLEARING, WATER LEVEL DRAWDOWN, DREDGING, DEWATERING, WATER TREATMENT, TRANSPORTATION, AND DISPOSAL, SHALL FOLLOW ALL APPLICABLE PERMITS AND CONTRACT DOCUMENTS. 21. IF DEBRIS IS ENCOUNTERED WHILE DREDGING, CONTRACTOR SHALL TRANSPORT DEBRIS TO THE STAGING AREA WHERE IT WILL BE TRANSPORTED OFFSITE TO AN APPROVED DISPOSAL LOCATION. VEHICLES TRANSPORTING DEBRIS OFFSITE MUST FOLLOW POSTED SPEED LIMITS, TRAFFIC SIGNS AND SIGNALS, AND ALL COUNTY HEIGHT, WEIGHT AND UNDERCLEARANCE RESTRICTIONS. CONTRACTOR SHALL NOT TRACK OR DISCHARGE SEDIMENT OR DEBRIS ONTO ROADS. 22. THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL PERMITS NECESSARY FOR CONSTRUCTION NOT SUPPLIED BY THE WILDLIFE RESOURCES COMMISSION. THIS MAY INCLUDE BUT NOT BE LIMITED TO: ANY REQUIRED EROSION CONTROL OR LAND DISTURBANCE PERMITS, ARMY CORP OF ENGINEERS PERMITS, STORMWATER PERMITS, NPDES, CITY OR COUNTY BUILDING PERMITS, OR ROADWAY PERMITS. THE COSTS FOR ADDITIONAL PERMITS WILL BE THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL NOT IMPACT THE PROJECT SCHEDULE. 23. CONTRACTOR SHALL IMPLEMENT EROSION AND SEDIMENT CONTROL AND MAINTAIN EROSION AND SEDIMENT CONTROL MEASURES AS NECESSARY TO COMPLY WITH COUNTY, STATE, AND FEDERAL LAWS AND REGULATIONS. ANY SEDIMENT CONTROL MEASURES DISTURBED BY CONSTRUCTION WILL BE REPAIRED THE SAME DAY. 24. CONTRACTOR SHALL SUBMIT CONSTURCTION WORK PLAN AND ANCILLIARY WORK PLANS IN ACCORDANCE WITH THE SPECIFICATIONS. 25. STOCKPILES MAY ONLY BE PLACED IN APPROVED LOCATIONS. ALL STOCKPILES LEFT AT THE END OF THE DAY NEED TO BE STABILIZED UNTIL THE NEXT DISTURBANCE. 26. BARRICADING AND TRAFFIC CONTROL DURING CONSTRUCTION SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL CONFORM TO THE NCDOT STANDARD SPECIFICATIONS AND DRAWINGS. PEDESTRIAN AND VEHICULAR TRAFFIC FLOW SHALL BE MAINTAINED DURING ALL PHASES OF THE CONSTRUCTION. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING TRAFFIC SAFETY MEASURES FOR WORK ON PROJECT. 27. WHERE EXISTING GRADE EXCEEDS 5:1 (HORIZONTAL:VERTICAL) AND THE DEPTH OF FILL EXCEEDS 5 FEET, BENCHING SHALL BE PROVIDED. A 2-FOOT DEEP BY 10-FOOT WIDE KEY SHALL BE PROVIDED AT THE TOE OF THE FILL SLOPE. REFER TO NC BUILDING CODE SECTION 107 FOR ADDITIONAL DETAIL. 28. CERTIFICATION OF CUT AND FILL SLOPES SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL BE MADE BY GEOTECHNICAL ENGINEER LICENSED TO PRACTICE IN THE STATE OF NORTH CAROLINA. UNLESS OTHERWISE NOTED, ALL CUT AND FILL SLOPES PROPOSED BY THESE PLANS SHALL BE 2:1 (HORIZONTAL:VERTICAL) OR FLATTER. 29. CUT AND FILL SLOPES (EMBANKMENTS) SHALL BE CONSTRUCTED IN ACCORDANCE WITH NCDOT STANDARD SPECIFICATION SECTION 235 OR THE GEOTECHNICAL (SOILS) REPORT RECOMMENDATIONS, WHICHEVER IS MORE RESTRICTIVE. AT A MINIMUM, ALL FILL SLOPES SHALL BE PLACED IN 10-INCH MAXIMUM LIFTS COMPACTED TO NOT LESS THAN 95 PERCENT DENSITY (STANDARD PROCTOR). CONTRACTOR SHALL ARRANGE FOR INDEPENDENT COMPACTION TESTING RESULTS TO BE PAID FOR BY THE OWNER/DEVELOPER. 30. NO GRADING OR FILL SHALL OCCUR WITHIN 2 FEET OF A PROPERTY LINE WITHOUT WRITTEN PERMISSION FROM THE ADJACENT PROPERTY OWNER. 31. UNLESS OTHERWISE INDICATED IN THESE PLANS TERRACES SHALL BE PROVIDED AS FOLLOWS: WHERE GRADES EXCEED 3:1 (HORIZONTAL:VERTICAL), TERRACES AT LEAST 6 FEET IN WIDTH SHALL BE CONSTRUCTED AT NOT MORE THAN 30-FOOT VERTICAL INTERVALS ON ALL CUT OR FILL SLOPES. SWALES SHALL BE PROVIDED ON TERRACES IN ACCORDANCE WITH NC BUILDING CODE SECTION JI09. 32. CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT THE WORK DOES NOT RESULT IN UNACCEPTABLE INCREASES IN TURBIDITY WITHIN THE LAKE OR SURROUNDING STREAMS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR IMPLEMENTING MEASURES TO CONTROL TURBIDITYAS NEEDED AND FOR FOLLOWING THE TURBIDITY MONITORING PLAN. 33. ALL MECHANIZED EQUIPMENT OPERATED NEAR SURFACE WATERS SHOULD BE INSPECTED AND MAINTAINED REGULARLY TO PREVENT CONTAMINATION OF STREAM WATERS FROM FUELS, LUBRICANTS, HYDRAULIC FLUIDS OF OTHER TOXIC MATERIALS. 34. DISCHARGING HYDROSEED MIXTURES AND WASHING OUT HYDROSEEDERS AND OTHER EQUIPMENT IN OR ADJACENT TO SURFACE WATERS IS PROHIBITED. 35. EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSPECTED DAILY AND AFTER ANY RAINFALL. DEFICIENCIES SHALL BE CORRECTED IMMEDIATELY. A DAILY RECORD SHALL BE MAINTAINED ON THE SITE BY THE CONTRACTOR. PROJECT SITE CONDITIONS MAY REQUIRE INSTALLATION OF ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES. EROSION CONTROL MEASURES AND MAINTENANCE SHALL BE IN ACCORDANCE WITH THE NORTH CAROLINA EROSION AND SEDIMENT CONTROL MANUAL. 36. CONTRACTOR WILL MAINTAIN PUBLIC ACCESS TO BOAT RAMP AND FACILITIES AT ALL TIMES, OR LIMIT BLOCKING OF ACCESS WITH ADVANCED NOTICE TO THE PUBLIC. NORTH CAROLINA /� (\p,T�'�®R , , Knowwhaesbelow. ru /� R /' call before you dig. ��l i �L/ R^SOURCEu DATUMS: 1. HORIZONTAL DATUM: NORTH CAROLINA, NORTH AMERICAN DATUM (NAD83), U.S. SURVEY FEET 2. VERTICAL DATUM: NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88), FEET SOURCES: 1. AERIAL PHOTOGRAPH ©2019 MICROSOFT CORPORATION ©2019 DIGITALGLOBE ©CNESS (2019) DISTRIBUTION AIRBUS DS 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED AUGUST 27, 2018. GENERAL LEGEND: PROPOSED: 14+00 PROJECT STATIONING H I I I H DREDGE AREA (PRIMARY) 905 DREDGE CONTOURS (1' INTERVAL) - • - DREDGE AREA (CONTINGENCY) EXAMPLE COIR LOG OR HAYBALE LOCATION S EXAMPLE SILT CURTAIN OR SILT FENCE LOCATION LIMITS OF DISTURBANCE SITE ACCESS ROAD - - - - STAGING AREA EXISTING: 905 TOPOGRAPHY (1' INTERVAL) 00 CHANNEL MARKERS > ----{ CULVERT ROAD ---- ----- ----- SHORELINE (NORMAL POOL ELEVATION 911.61') DETAIL AND SECTION REFERENCING: DETAIL REFERENCE NUMBER 1 DRAWING ON WHICH DETAIL APPEARS C1 '-" INDICATES TYPICAL OR ON SAME DRAWING DETAIL REFERENCE NUMBER 1 DETAIL SCALE: 1" = 10' XA DICATES DIRECTION CUTTING PLAN SECTION "A" IS SHOWN ON DRAWING "C-2"_ C2 SECTION REFERENCE LETTER A SECTION PLAN NUMBER WHICH SECTION WAS TAKEN SCALE: r' = 10' ABBREVIATIONS: FEET, MINUTES " INCHES, SECONDS DEGREES 0 DIAMETER # NUMBER APPROX APPROXIMATE CONC CONCRETE CY CUBIC YARDS DIA DIAMETER DU DREDGE UNIT DWG DRAWING E EAST, EASTING ELEV ELEVATION EX EXISTING FG FINISHED GRADE FL FLOW LINE GALV GALVANIZED HOR HORIZONTAL L LENGTH LF LINEAR FEET MAX MAXIMUM MIN MINIMUM MLLW MEAN LOWER LOW WATER N NORTH, NORTHING NAD NORTH AMERICAN DATUM NAVD NORTH AMERICAN VERTICAL DATUM P.E.A. PROFESSIONAL ENGINEER R, RAIDRADIUS REINF REINFORCED, REINFORCEMENT ROW RIGHT-OF-WAY S SLOPE, SOUTH STA STATION SY SQUAREYARD TESC TEMPORARY EROSION AND SEDIMENT CONTROL TYP TYPICAL W WEST, WATER W/ WITH WSEL WATER SURFACE ELEVATION SEQUENCE OF CONSTRUCTION: SPECIFIC ACTIVITIES CONDUCTED BY THE CONTRACTOR TO COMPLETE THE WORK INCLUDE, BUT ARE NOT LIMITED TO: 1. PREPARE AND SUBMIT FINAL WORK PLANS AND ALL OTHER REQUIRED PRE -CONSTRUCTION SUBMITTALS. 2. ATTEND A PRE -CONSTRUCTION MEETING WITH THE OWNER, THE ENGINEER AND OTHER RELEVANT STAKEHOLDERS IDENTIFIED. 3. PERFORM AND SUBMIT ALL REQUIRED PRE -CONSTRUCTION SURVEYS. IDENTIFY AND FLAG ALL WETLANDS WITHIN 100 FEET OF THE LIMITS OF DISTURBANCE IDENTIFIED IN THE DRAWINGS. 4. ATTEND A CONSTRUCTION KICKOFF MEETING WITH THE OWNER'S REPRESENTATIVE AND OTHER RELEVANT STAKEHOLDERS IDENTIFIED. 5. MOBILIZE CREWS, FACILITIES, EQUIPMENT, AND MATERIALS REQUIRED TO COMPLETE THE WORK. 6. INSTALL AND MAINTAIN ENVIRONMENTAL CONTROLS AND APPROVED PLACEMENT AREA CONTAINMENT FEATURES. 7. PERFORM ALL REQUIRED DREDGING AND PLACEMENT WITHIN THE LIMITS SPECIFIED ON THE DRAWINGS. 8. PERFORM AND SUBMIT ALL REQUIRED POST -CONSTRUCTION SURVEYS. 9. PERFORM SITE RESTORATION AND DEMOBILIZATION IN ACCORDANCE WITH THE TECHNICAL SPECIFICATIONS. w� 10. PLANTING WORK WILL BE COMPLETED UNDER A SEPARATE z o z CONTRACT FOLLOWING ADEQUATE CONSOLIDATION AND o , SETTLING OF PLACED DREDGED MATERIAL. s Z - o V - V _ w O � V LL I QV Z_ DRAFT -NOT FOR CONSTRUCTION REVISIONS DESIGNED BY: CORK,R. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE: AS NOTED NORTH CAROLINA WILDLIFE RESOURCES COMMISSION �� Z �� DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING GENERAL NOTES, LEGEND, AND ABBREVIATIONS DATE: JANUARY 2021 SHEET# OF 0 J i, PUBLIC ACCESS BOAT RAMP i •. 0 FL_...... _ .909 DOCK .° � o EXISTING t ° CULVERT LAKEADGER ° r (FULL POOL ELEVATION 911.61) 0 Qom\ I P�CF� o LEGEND: —905— EXISTING TOPOGRAPHY (1' INTERVAL) — ---- — SHORELINE (NORMAL POOL ELEVATION 911.61') 00 CHANNEL MARKERS - SUMMER 2019 LAKEADGER O 0 nQ j' 0 on o °. i' NORTH i 0 100 200 .'; .. e O '��p''� : r �� � o �. .o► �).. �.:i ` i; ;... f' J � � SCALE IN FEET 70 r�^p i�ao�� �ii r. ?. ° r`p r: ♦.. y ,'i, ; / .:''y..: s �r'a ,'. !, �!� ° , f, .. • _ r ..r .p ,' •S r a ° 910 0 ,.. :: Rio - V i i J i �1 ♦.$� r: a r..._...1 0. °e r % • ` + 6 S »moo .;:• � ,.: ,. r� ' ��� ��• Ji <! .[dam �:d�.�t `�' o° �� � `r'� i L "� ��'Irr• ids � \ur���\� � ���� �� • � r.. d: � r.%r.J ��,:: �.... r ��� //� ., �' �O: ..T (7 ° - ,1 r. •' (7 wl O ° fi.r w !oi J' / ! a Q °• , 1 / a. °..1 'v - .r � �'� � 1 e. � � •`•°�1 � .;1 ° - �'��^per :I . J�. �•.3 r ± ° LiD „>, m v _ 70._..._ c a o r"+ i•L`'�•• I Sp ��A.; r fl o ° o n Sr46 �7opr:` z¢ �e • - r - J.. 9 A �...�;; " ...�:' ° •• _ , j .rl `d7% J't► L>, \ • t •r i�,`\ e ¢ m o o �.. t.. �. ..� /.: '1 ♦:i i' 1 r ' .r',0�' •j4:>e eoR or • 0 .-�f _ E ?Z r x. LPO , �. •: .r .�a-�..:.� :^c. ,�' 1 � O O .._ ..r��. y- a �t l':,( old 9' v. • �' j �; ..i, . _ `Q ;;.:� ! i t % , ...:ter.:: iv s ° 91� z . + oz 41 - z LL� r C r w J^.� `ab + �. r r J� �QQF i''r .� _s� ` QF� `i z • �t -- w ° �... :x :1, . _ :. ..t:a� \...� �.,.: ® _ DRAFT -NOT FOR CONSTRUCTION z REVISIONS NORTH REV DATE BY AP P D DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION E1 ANCHOR �•y CAROLINA DRAWN BY: HOrMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING r-y ®Lr / , Know Whans below. CHECKED BY: REEMTS, M. a l�vi\ / ' CBII before you dig. - QEA �`/ RESOURCES APPROVED BE DIN (COLA, W. COMMISSION SCALE: AS NOTED DATE: IANUARY1011 EXISTING CONDITIONS SHEET# 3 of 11 ♦� —D--ACCESS BOAT RAMP PROPO D / - STAGIN AREA 4 �1 _ \ v 0 ����� �(O. ACRES) . m DU-8 DU-6 \ \ \ \ \ DU-5 \ x� O B• 1 DU-4 \ r 0 LAKE ADGER 1 r DU-1 DU-213 'I�+00 Ile11+00 12+00 13+00 14+00 I 15+00 2911 k Os \ DU-2A \ LEGEND: 14�� PROJECT STATIONING NAVIGATION CHANNEL DREDGE AREA APPROXIMATE EXTENTS • — • — DREDGE AREA APPROXIMATE EXTENTS — APPROXIMATE LIMITS OF DISTURBANCE - DREDGING AREA — — — WETLAND DELINEATION — —--- — SHORELINE (NORMAL POOL ELEVATION 911.61') 0 NORTH 0 60 120 SCALE IN FEET \ NOTES: o� 1. HORIZONTAL DATUM: NORTH CAROLINA, NORTH \ AMERICAN DATUM (NAD83), U.S. SURVEY FEET 50 ow V 2. VERTICAL DATUM. NORTH AMERICAN VERTICAL o a i DATUM OF 1988 (NAVD88), FEET o 0 w¢ SOURCES: z z o z o Q V 1. AERIAL PHOTOGRAPH 02019 MICROSOFT E� z y CORPORATION 02019 DIGITALGLOBEOCNESS R\JAR r \i (2019) DISTRIBUTION AIRBUS DS 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED J o z r o = CIO �. AU AUGUST 27, 2018. z ? o o z °\) % J ' DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION REV DATE BY AP DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING ANCHOR CAROLINA , , KROW Whans below. Call before you dig. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. - �v QEA --1`/ /' RESOURCES APPROVED B: DIN (COLA, W. COMMISSION SCALE: AS NOTED DATE: JANUARY 2021 DREDGE PLAN SHEET# 4 OF 11 LAKE ADGER CHANNEL CENTERLINE 920 920 z 910 910 w 1L— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — Z_ 3 z O 900 ELEVATION 905.61' NAVD88 FROM STATION 9+90 TO END 900 w ELEVATIONS SLOPE FROM 905.61' TO 904.61' NAVD88 w z V H 890 890 -0+5C 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 HORIZONTAL DISTANCE IN FEET 5X VERTICAL EXAGGERATION LAKE ADGER CHANNEL CENTERLINE 920 920 _... _... ¢ 910 910 z w w z 0 � 900 900 w ELEVATION 904.61' NAVD88 z w V H 890 89C 10+00 10+50 11+00 11+50 12+00 12+50 13+00 13+50 14+00 14+50 15+00 HORIZONTAL DISTANCE IN FEET 5X VERTICAL EXAGGERATION o� V � O 0 Z z Q w I 0 z_ 0 Z 0 ¢ V Z m LEGEND: EXISTING MUDLINE w� NAVIGATION CHANNEL DESIGN DREDGE ELEVATION 0 z 0 — — — — NAVIGATION CHANNEL 6" ALLOWABLE OVERDEPTH s ° o V LL V NAVIGATION CHANNEL DREDGED MATERIAL TO BE REMOVED z N w 0 — --- _...— ..— LAKE ADGER FULL POOL ELEVATION 911.61' J LLs ¢ z NOTE: ALL DESIGN SLOPES ARE 3H:1V UNLESS OTHERWISE NOTED. DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION REV DATE BY AP DESCRIPTION CAROLINA DRAWN BY: HOMER, D. �� LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING �I AANCHOR , f ' , Kno/w�whaPsbelow. Call before youd19. CHECKED BY: DINICO, M. APPROVED BY : DIN (COLA, W. � RESORCES COMDATE: SCALE: AS NOTED IANDARV2011 PROFILE SHEET# 5 OF 11 STA 0+20 930 920 0 z " 910 z z H a 900 w 890 STA 2+00 920 920 920 920 ¢ DU-5 DU-6 ¢ z z w w ..4..._.. _... _... _... _... _..._.._ ... _... _.._..._..._..._..._ .._ .._..._... 910 910 z 910 910 z � a 3 � a 900 900 w 900 900 w 890 890 890 890 930 930 920 920 0 a z W W 910 910 z_ z 0 a 900 900 w 890 890 -20 -10 0 10 20 30 40 50 60 -20 -10 0 10 20 30 40 50 60 -20 -10 0 10 20 30 40 50 OFFSET IN FEET (NO VERTICAL EXAGGERATION) OFFSET IN FEET (NO VERTICAL EXAGGERATION) OFFSET IN FEET (NO VERTICAL EXAGGERATION) STA 12+00 STA 13+20 930 3 m 920 a z H - W W = z_ 910 = z - o _ a 900 w 890 -70 -60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 - OFFSET IN FEET (NO VERTICAL EXAGGERATION) 920 910 900 89C -20 -10 0 10 20 30 40 50 60 70 80 90 100 -20 -10 0 10 20 30 40 50 -20 -10 0 10 20 30 40 50 OFFSET IN FEET (NO VERTICAL EXAGGERATION) OFFSET IN FEET (NO VERTICAL EXAGGERATION) OFFSET IN FEET (NO VERTICAL EXAGGERATION) 930 0 920 a z W W z_ 910 z 0 a 900 w 890 930 930 920 920 0 a z W W 910 910 z_ z 0 a 900 900 w 890 890 930 m 920 0 a z H W z_ 910 z 0 a 900 900 Y � O O Z � Q 890 89C 0 0 50 -40 -30 -20 -10 0 10 20 30 40 50 w OFFSET IN FEET (NO VERTICAL EXAGGERATION) z o oW Z V J Q - LEGEND: a Z m EXISTING MUDLINE DESIGN DREDGE ELEVATION 00 -_ 0 — — — — 6" ALLOWABLE OVERDEPTH s V ° o LL V DREDGED MATERIAL TO BE REMOVED z N w — --- _...— ..— LAKE ADGER FULL POOL ELEVATION 911.61' z 0 J LLs ¢ z NOTE: ALL DESIGN SLOPES ARE 3H:1V UNLESS OTHERWISE NOTED. DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH REV DATE BY AP P D DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION ^� CAROLINA DRAWN BY: HOLMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING J ANCHOR / ' , , KROW Whans below. CBII before you dig. CHECKED BY: REEMTS, M. APPROVED BE DIN (COLA, W. RESOURCES COMMISSION SCALE: AS NOTED SECTIONS DATE: JANUARY 2021 SHEET# 6 OF 11 / O PROPOSEG D ; �P ° 2TF LEGEND: O STAGIN' j � � 4x• o•X � ! ♦ �� C 92 PROPOSED DREDGED MATERIAL PLACEMENT ♦e r �\� AREA i v \ \ Al AREA DESIGNATION 0 " d:' ♦: YYY ' i o 1 P� n.: \. f EXAMPLE COIR LOG OR HAYBALE LOCATION j�• Q° 14+00 PROJECT STATIONING 2p0 / / \ \ \ \ d NAVIGATION CHANNEL DREDGE AREA APPROXIMATE EXTENTS t o 907 ° � ' • � — • — • — DREDGE AREA APPROXIMATE EXTENTS .1 / JI ga$ D \ ok>� APPROXIMATE LIMITS OF DISTURBANCE - o C1 DREDGING AREA p Og EXISTING CHANNEL ° `• e \ MARKER (TYPICAL) < O \ '\'\ • — WETLAND DELINEATION � i f FLOATING DOCK � p ° \ SHORELINE (NORMAL POOL ELEVATION 911.61') Q 1 CULVERT p o 0 o O \ \ I S \ OP. Q NORTH 0 60 120 LAKEADGER ° = o Q rt� 'i�+00 SCALE IN FEET B1 p (FULL POOL ELEVATION 911.61) 4 r ck,q.7 NOTES: J s o c 1. PLACEMENT AREAS ARE APPROXIMATE, O ` ��� p 1 CONTRACTOR TO INSTALL SEDIMENT CONTROL ° ° FEATURES AS NEEDED TO CONTAIN SEDIMENT WITHIN TARGET AREAS TO THE ELEVATIONS SHOWN. r•rjr ��Jrrr.=.F 5�1 �, ° • APPROXIMATE AREA OF DISTURBANCE ° o o• 2. CONTRACTOR TO UTILIZE COMBINED COIR LOGS, c� r S' FOR MATERIAL PLACEMENT 17.3 ACRES HAYBALES, SILT CURTAINS, SILT FENCES, OR OTHER ♦ a ° CONTROL STRUCTURES TO MANAGE SEDIMENTS WITHIN PLACEMENT AREA EXTENTS. Q3. CONTRACTOR MAY ADJUST ALIGNMENTS AS NEEDED TO BALANCE PLACEMENT OPERATIONS D j ;.3 1 , :'+"J n ° ap AND SEQUENCE THE WORK. 4. CONTRACTOR SHALL NOT BLOCK FLOW FROM ° CULVERT AND GREEN RIVER BRANCHES DURING MATERIAL PLACEMENT OPERATIONS. O < v 5. ONLY BIODREGRADABLE FEATURES MAY BE LEFT IN ` PLACE FOLLOWING MATERIAL PLACEMENT. ANY / / J iE ♦. a J J Cl Q A. SILT CURTAINS, SILT FENCES, ANCHORS, METAL � _ /"' o i. ��e � • 1�.: �•� � � p .�O ` o STAKING, OR OTHER INSTALLED ITEMS MUST � `^ Q,OTHERWISE BE REMOVED. o ' S i O 1: Q• 3 1` :'`' 4`':'1 • A2 O , 0�� �� / ^ 6. CONTRACTOR MATERIAL TRANSPORT LINE SHOULD o w ♦ f r ^ p e� °•� BE ROUTED THROUGH WORK AREAS IDENTIFIED o a r�.(: .�.fJ ( !. �'' "y ° ^:� WHERE 1 POSSIBLE. , � ♦ ., ...; .``.,0 / i .° d ° l. • :.r .. 1 i; o n.n ��.:..\ Q_....�� o a :a r ...1 ...' ♦'. ..lr \ o i.r .:`i'� z ° e .:♦ ..♦. .. :_,:.../' SOURCES. °� ���<..A''�.�'' 1. AERIAL PHOTOGRAPH ©2019 MICROSOFT � z t: p ') �'S♦ .. (:: !' jam. GR p '_. ` r.. '.ti \ ji,i ` e� .Z e:;j .. ° o / CORPORATION ©2019 DIGITALGLOBE ©CNESS --/ p$'' .r' (2019) DISTRIBUTION AIRBUS DS 70 > v i ♦ ♦ 1 1 ' \ '1 / O z 1 a D ^1 O.1 a Q .� r.�f z0 c /o Or.: "' 1.:'�:w .i' QO . C• ,� C I .,. v / `o / r. • /t i' ; , 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED o E WETLANDS EXTEND BEYOND i...♦ ". o ♦�' %' 1•:.1 1 r'' i r .i 1. !' /" O oQ Fe 4" r 0 / UJ AUGUST 27, 2018. z o LIMITS OF DISTURBANCE z LL i r' o '.^.g ,♦ \ veoQ r ; "�',� .i. WETLANDS EXTEND BEYOND ��/:r 1 ° / 1 1 �S / Q z z "Ao o r.:....\ ;, , LIMITS OF DISTURBANCE c�, '-r1 / ' DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH REV DATE BY AP DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION A T p �•y CAROLINA DRAWN BY: HOMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING 4 A �T� �-y ®Lr r , Know Whans below. CHECKED BY: REEMTS, M. ANCHOR al�vi\ /' Call before you dig. - IDEA i �`/ RESOURCES APPROVED BE DIN (COLA, W. COMMISSION SCALE: AS NOTED DATE: JANDARY2021 DREDGED MATERIAL PLACEMENT LAYOUT HEET# 7 of 11 LEGEND: EXAMPLE COIR LOG OR HAYBALE LOCATION 8 EXAMPLE SILT CURTAIN OR SILT FENCE n LOCATION 14�� PROJECT STATIONING NAVIGATION CHANNEL DREDGE AREA OQO APPROXIMATE EXTENTS \ �..� O�<cQ' \ ' / • • ' • � - — • — • — DREDGE AREA APPROXIMATE EXTENTS APPROXIMATE LIMITS OF DISTURBANCE TURBIDITY MONITORING LOCATION CULVERT \\ \ �\ DOWNSTREAM TURBIDITY MONITORING \. LAKEADGER �'\ STATION: (FULL POOL ELEVATION 911.61') V N35.335345° I \ W82.2233970 NORTH LAKE ADGER 0 150 300 SCALE IN FEET � � F = PO _ �O O V r � O 0 Z UPSTREAM TURBIDITY MONITORING STATION: w N 35.330801 ° z o W82.235823° SOURCES: Q = a z m i 1. PHOTOGRAPH ©2019 AERIAL IMAGERY N RIVER (NC ONE MAP) Y i GREE _ r .... _ ;;. - _ ._. _ _ m 00 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES o 27 2 DATED AUGUST 018. z o LL J Z V w - N w - w V LL to DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION C5 REV DATE BY AP DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING ��®� CAROLINA ' Knowwhaesbelow. Call betas you dig. DRAWN BY : HOLMER, D. CHECKED BY: REEMTS, M. 7 - QEA(`�, ® �`� �v RESOURCES APPROVED BY : DINICOLA, W. COMMISSION SCALE: AS NOTED DATE: JANUARY2021 TURBIDITY MONITORING LOCATIONS HEET# 8 of 11 CULVERT Aj B1 H / /-- PROPOSEDI ' STAGING o AREA ' O� T � 0 F \•� tea' �.� \ '\� / EXISTING CHANNEL \• MARKER (TYPICAL) \ '\ il FLOATING DOCK O \ x^ LAKEADGER CP \ LAKE (FULL POOL ELEVATION 911.61) � \ ' �00 / • "r+00 12+00 13+00 14+00 APPROXIMATE AREA OF DISTURBANCE . .. . .. FOR MATERIAL PLACEMENT 17.4 ACRES \ \ GR�E�R\vv / s I 15+00 MAXIMUM APPROXIMATE IMPACTED AREAS (ACRES) IMPACT TYPE AREA TYPE DESCRIPTION Al A2 31 C1 DREDGING PERMANENT DUE TO OPEN WATER AREA BETWEEN WETLAND DELINEATION EXTENTS 0.7 1.1 0.4 0.8 N/A PLACED MATERIALS AND CELL BOUNDARY TEMPORARY BY WETLAND AREA BETWEEN WETLAND DELINEATION EXTENTS 2.0 2.2 >0.1 N/A N/A CONSTRUCTION ACTIVITIES AND UPGRADIENT LIMITS OF DISTURBANCE TEMPORARY BY AREA BETWEEN CELL BOUNDARY AND CONSTRUCTION ACTIVITIES OPEN WATER DOWNGRADIENT LIMITS OF DISTURBANCE 1.8 4.5 LEGEND: PROPOSED DREDGED MATERIAL Al PLACEMENT AREA DESIGNATION EXAMPLE COIR LOG OR HAYBALE LOCATION S EXAMPLE SILT CURTAIN OR SILT FENCE LOCATION - — APPROXIMATE LIMITS OF DISTURBANCE - PLACEMENT AREA 14+00 I PROJECT STATIONING NAVIGATION CHANNEL DREDGE AREA APPROXIMATE EXTENTS - • — • - DREDGE AREA APPROXIMATE EXTENTS — • • — APPROXIMATE LIMITS OF DISTURBANCE — — — WETLAND DELINEATION 0 NORTH 0 80 160 SCALE IN FEET NOTES: 1. PLACEMENT AREAS ARE APPROXIMATE, CONTRACTOR TO INSTALL SEDIMENT CONTROL FEATURES AS NEEDED TO CONTAIN SEDIMENT WITHIN TARGET AREAS TO THE ELEVATIONS SHOWN. 2. CONTRACTOR TO UTILIZE COMBINED COIR LOGS, HAYBALES, SILT CURTAINS, SILT FENCES, OR OTHER CONTROL STRUCTURES TO MANAGE SEDIMENTS WITHIN PLACEMENT AREA EXTENTS. 3. CONTRACTOR MAY ADJUST ALIGNMENTS AS NEEDED TO BALANCE PLACEMENT OPERATIONS AND SEQUENCE THE WORK. 4. CONTRACTOR SHALL NOT BLOCK FLOW FROM CULVERT AND GREEN RIVER BRANCHES DURING MATERIAL PLACEMENT OPERATIONS. 5. ONLY BIODEGRADABLE FEATURES MAY BE LEFT IN PLACE FOLLOWING MATERIAL PLACEMENT. ANY SILT CURTAINS, SILT FENCES, ANCHORS, METAL STAKING, OR OTHER INSTALLED ITEMS MUST OTHERWISE BE REMOVED. 6. CONTRACTOR MATERIAL TRANSPORT LINE SHOULD BE ROUTED THROUGH WORKAREAS IDENTIFIED WHERE POSSIBLE. 7. TEMPORARY IMPACTS WILL BE MINIMIZED, WHERE o POSSIBLE, TO IMPACTS RELATED TO ALIGNMENT OF HYDRAULIC DREDGING DISCHARGE HOSES, > o PEDESTRIAN ACCESS, AND MINIMAL SEEPAGE OF PLACED MATERIAL THROUGH THE CONTAINMENT o w STRUCTURE. STOCKPILING OF SEDIMENT ON THE o a WETLANDS WILL NOT BE ALLOWED, AND NO E Z< EQUIPMENT WILL BE PLACED OR USED ON THE zo WETLAND WITHOUT PRIOR APPROVAL BY NCWRC. z o w Q V m a z SOURCES: 1. AERIAL PHOTOGRAPH ©2019 MICROSOFT CORPORATION ©2019 DIGITALGLOBE ©CNESS z� o z (2019) DISTRIBUTION AIRBUS DS o s V 0 1 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED Z z V N w AUGUST 27, 2018. o 1 QV Z DRAFT -NOT FOR CONSTRUCTION ANCHOR �v - IDEA i �`/ NORTH CAROLINA , /' RESOURCES COMMISSION , KROW Whans below. Call before you dig. REVISIONS DESIGNED BY: CORK,R. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. APPROVED BE: DIN (COLA, W. SCALE: AS NOTED DATE: ,ANUARvzozi NORTH CAROLINA WILDLIFE RESOURCES COMMISSION C6 V SHEET# 9 OF 11 REV DATE By AP P D DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING IMPACTED AREAS 20" DIAMEI COIR LOGS fv FAKE TO ONLY FE NETTING IEXISTING SURFACE JOINT DETAIL NOT TO SCALE 20" DIAMEI COIR LOGS MI STAKING DETAIL NOT TO SCALE NOTES: 1. COIR LOGS SHALL BE PLACED AS SHOWN ON DRAWING C4, AND IN A ROW WITH ENDS TIGHTLY ABUTTING ADJACENT COIR LOGS. COIR LOGS SHALL BE USED WITH SILT CURTAINS AS SHOWN IN THESE COIR LOG AND SILT CURTAIN DETAILS AND DRAWING C4. 2. COIR LOGS SHALL BE SECURELY ANCHORED IN PLACE BY TWO STAKES DRIVEN THROUGH THE COIR LOG NETTING AS SHOWN IN THE COIR LOG DETAIL. STAKES SHALL BE DRIVEN FLUSH WITH THE COIR LOG. 3. INSPECTION SHALL BE DAILYAND REPAIR/REPLACEMENT SHALL BE MADE PROMPTLY AS NEEDED. 4. COIR LOGS SHALL BE REMOVED AS DIRECTED BY THE ENGINEER 1 COIR LOG DETAIL C07 SCALE: NOT TO SCALE . Y 1'8„ 't 't 't 't 't ' 'i.. % „IQ (TYP.) TF i 4i 4i 4i 4i 4i 4i 4i 4i 4i 4i 4i 4i 4i 4� 11 41 I I I I• 41 1 41 41 1 41 41 1' i 4i 4Qi 4i 4i 4j� 44i 4i 4i 4iI 41 ' 18" (TYP.) ,q r i 4i 4i 4i 4itl 41 4 41 41 CI 41 4i 4i 4i u � TOP VIEW 6" (APPROX) 0 H Al STAKE PROTECTED AREA AREA OF DISTURBANCE STAKE TO ONLY METAL CONNECTOR HEAVY DUTY CORD SEWN IN SILT SILT FENCE POST 2ATE NETTING CABLE 1/8"0 MIN FENCE FABRIC (TOP AND BOTTOM) AND LOOPED AROUND POST. (SEE MISTING DETAIL "A" FOR TOP CORD TO ;URFACE EVERY OTHER SILT FENCE POST) 2"x 2"x 4'-0" MAX OAK POST DRIVEN INTO SUPPORT NETTING (HEAVY DUTY SILT FABRIC AND TRENCH, SEE NOTE 2 PLASTIC MESH) LOOP CABLE OVER POST 0 SILT FENCE FABRIC DRIVEN COMPLETELY THROUGH BOTTOM ROW OF BALES CED SEDIMENT UP TO 2" BELOW HAYBALES :ES, 2 PER BALE, DRIVEN AT LEAST 1.5' OR SEDIMENT INTO COMPETENT GROUND 16" (TYP.) I ANGLE FIRST STAKE TOWARD PREVIOUSLY LAID BALE FRONT VIEW NOTES: 1. HAYBALES SHALL BE PLACED AS SHOWN ON DRAWING C4, AND IN A ROW WITH ENDS TIGHTLY ABUTTING THE ADJACENT HAYBALES. HAYBALES SHALL BE USED WITH SILT FENCES AS SHOWN IN HAYBALES AND SILT FENCE DETAIL UNLESS OTHERWISE INDICATED ON DRAWING C4. 2. EACH HAYBALE SHALL BE PLACED SO THE BINDINGS ARE HORIZONTAL. 3. HAYBALES SHALL BE SECURELY ANCHORED IN PLACE BY TWO STAKES DRIVEN THROUGH THE HAYBALE. THE FIRST STAKE IN EACH HAYBALE SHALL BE DRIVEN TOWARD THE PREVIOUSLY LAID HAYBALE AT AN ANGLE TO FORCE THE HAYBALES TOGETHER. STAKES SHALL BE DRIVEN FLUSH WITH THE HAYBALE. 4. INSPECTION SHALL BE DAILYAND REPAIR/REPLACEMENT SHALL BE MADE PROMPTLY AS NEEDED. 5. HAYBALES SHALL BE REMOVED AS DIRECTED BY THE ENGINEER. 6. KEY HAYBALES 6'' INTO SOFT SEDIMENT. 3 TYPICAL DOUBLE STACK HAYBALE DETAIL C07 NOT TO SCALE NORTH CAROLINA , ANCHOR � � Know Wnacsbelow. ' CBII before you dig. RESOURCES COMPACTED BACKFILL IN TRENCH EXISTING GRADE ANCHORBUOY BUOY — NYLON ROPE ANCHOR DEVICE 1 12" MIN FLOTATION DEVICE SILT CURTAIN CHAIN CIE1C \/IC\A/ GENERAL NOTES: 1. THE DETAILS SHOWN IN THESE ENGINEERING DRAWINGS ARE CONCEPTUAL IN NATURE. THE CONTRACTOR SELECTED METHODOLOGIES FOR CONTAINING DREDGED MATERIAL AND TURBIDITY CONTROL WILL BE DETAILED IN THE DREDGING WORK PLAN TO BE APPROVED BY NCWRC. 2. THE CONTRACTOR METHODOLOGIES FOR CONTAINING DREDGED MATERIAL AND TURBIDITY CONTROL SHALL BE ALTERED TO MEET PROJECT OBJECTIVES AND REQUIREMENTS, AS DETERMINED BY NCWRC DURING PERFORMANCE OF THE WORK. CONTAINMENT OF PLACED SEDIMENT WILL AIM TO PREVENT THE MIGRATION OF PLACED MATERIAL INTO DELINEATED WETLANDS ADJACENT TO THE PLACEMENT AREAS. REVISIONS DESCRIPTION FILTER FABRIC UNDISTURBED GROUND (TYP) DETAIL A BURY FLAP OF FILTER FABRIC NOTE: IN BOTTOM OF TRENCH POSTS FOR SILT FENCE MUST BE LOCATED EIGHT FEET MAXIMUM. ON -CENTER. z SILT FENCE DETAIL C07 SCALE: NOT TO SCALE SILT CURTAIN TOP LOAD LINE TOP LOAD LINE (OPTIONAL) WATER LEVEL (OPTIONAL) CONNECTOR WATER LEVEL ..jFLOTATION DEVICE 1'-5' (TYP) BALLAST LINE (GALVANIZED CHAIN) BOTTOM SEDIMENT CONNECTION GROMMETS 1'-5' (TYP) V-5 (TYP) ............ BALLAST LINE BOTTOM SEDIMENT (GALVANIZED CHAIN) .. .n. ... .. .. . ...:'.Y.! ... .. .. .. CC/'TInKI \/IC\A/ NOTE: IF THE SEDIMENT ALONG THE SILT CURTAIN ALIGNMENT IS EXPOSED DURING CONSTRUCTION, SILT FENCES SHALL BE USED IN PLACE OF SILT CURTAINS. TYPICAL SILT CURTAIN DETAIL o z C07 NOT TO SCALE O m zo V LL V z — V w O V LL� x Q V z DRAFT -NOT FOR CONSTRUCTION DESIGNED BY: CORK, R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION �� LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE: AS NOTED DETAILS DATEJANUARY 2021 : SHEET# 10 OF ff TABLE 1: PLANTING ELEVATIONS TABLE 2: EMERGENT VEGETATION SPECIES TABLE 4: TREE AND SHRUB SPECIES PLANTING ZONE MIN. ELEVATION (FT, NAVD88) MAX. ELEVATION (FT, NAVD88) A 912.0 913.7 B 911.3 912.10 USE PILOT STAKE TO MAKE HOLE, AND PLANT PLUG DIRECTLY IN BACKFILL PLANT FLUSH 1 WETLAND PLANTING DETAIL NOT TO SCALE CONTAINERIZED TREE OR SHRUB (TYP) SET ROOT CROWN AT 1" ABOVE FINISHED GRADE SHRUB PLANTING PIT PREPARATION = ROOTBALL DEPTH & WIDTH PLUS V-0" MIN 3" MULCH ADDITIONAL ALL SIDES FINISH GRADE n ROOTBALL + + + + + + + TOPSOIL DEPTH `++++i +++++ + + + + + + + + + REMOVE CONTAINER + + + + COMPLETELY UNDISTURBED SUBGRADE ROOTBALL + V-0"MIN (PROVIDES FIRM BASE SO THAT ALL SIDES ROOTBALL WILL NOT SINK) NOTE: STAKE ALL TREES 4 FT & TALLER. z SMALL TREE/SHRUB DETAIL NOT TO SCALE NORTH CAROLINA /� %, CHO Know what'sb0I0W. r�.�call before youdig. QEA�v RESOURCES Common Name Scientific Name Planting Zone Broadleaf Cattail Typha latifolia B Common Arrowhead Sagittaria latifolia B Wool Grass Scirpus cyperinus A, B Soft Stem Bulrush Schoenoplectus tabernaemontani A B Fringed Sedge Carexcrinita A Pickerelweed Pontederia cordata B Soft Rush Juncus effusus A, B NOTES: 1. ALL LISTED PLANTS ARE OBLIGATED WETLAND PLANTS z. PLANTS SHALL BE 2-INCH PLUGS AND PLANTED AT A DENSITY OF 10,900 (z-FOOT SPACING) PER ACRE. 3. SIMILAR SPECIES CAN BE SUBSTITUTED BASED ON SITE CONDITIONS WITH APPROVAL OF THE CONSTRUCTION MANAGER. 4. A 1-YEAR WARRANTY SHALL APPLY TO ALL EMERGENT VEGETATION SPECIES. AT THE END OF 1-YEAR, ANY EMERGENT SPECIES THAT DOES NOT SURVIVE SHALL BE REPLACED BY THE CONTRACTOR WITH A SPECIES PERFORMING WELL AT THE SITE. TABLE 3: WETLAND SEED MIX Common Name Scientific Name Planting Zone Common Water Plantain Alisma subcordatum A, B Swamp Milkweed Asclepias incarnata A, B Common Hop Sedge Carexlupulina A, B Lance -Fruited Oval Sedge Carexscoparia A, B Brown Fox Sedge Carex vulpinoidea A, B Turtlehead Chelone glabra A, B Common Wood Reed Cinna arundinacea A, B Flat -Top Aster Doellingeria umbellata A, B Virginia Wild Rye Elymus virginicus A, B Common Boneset Eupatorium perfoliatum A, B Hollow Joe-Pye Weed Eutrochium fistulosum A, B Sneezeweed Helenium autumnale A, B False Sunflower Heliopsis helianthoides A, B Common Rush Juncus effusus A, B Great Blue Lobelia Lobelia siphilitica A, B Monkey Flower Mimulus ringens A, B Ditch Stonecrop Penthorum sedoides A, B Dark Green Rush Scirpus atrovirens A, B Wool Grass Scirpus cyperinus A, B Side -Flowering Aster Symphyotrichum lateriflorum A, B New England Aster Symphyotrichum novae-angliae A, B Marsh Shield Fen Thelypteris palustris A, B Blue Vervain Verbena hastata A, B Boneset Eupatorium perfaliatum A, B Needle Spikerush Eleocharis acicularis A, B Silky Willow Salixsericea A, B NOTE: A 1-YEAR WARRANTY SHALL APPLY TO ALL SEEDING AREAS. AT THE END OF 1-YEAR, ANY BARE AREAS GREATER THAN 5 SQUARE FEET SHALL BE RESEEDED BY THE CONTRACTOR WITH A SPECIES PERFORMING WELL AT THE SITE. REVISIONS VI DATE I BY IAPPDI DESCRIPTION Common Name Scientific Name Planting Zone Trees American Elm Ulmus americana A River Birch Betula nigra A Black Willow Salixnigra A Red Maple Acer rubrum A Box Elder Acer negundo A American Sycamore Plantanus occidentalis A American Persimmon Diospyros viginiana A Black Gum Nyssa sylvatica A Shrubs Spicebush Lindera benzoin A Smooth Alder Alnus serrulata A Silky Dogwood Comus amomun A NOTES: 1. TREES SHALL BE 5-GALLON CONTAINER AND INSTALLED ON 25 FT CENTERS. z. SHRUBS SHALL BE 1-GALLON CONTAINER AND INSTALLED ON 10 FT CENTERS. 3. A 1-YEAR WARRANTY SHALL APPLY TO ALL TREES AND SHRUBS. AT THE END OF 1 YEAR, ANY TREE OR SHRUB THAT DOES NOT SURVIVE SHALL BE REPLACED BY THE CONTRACTOR WITH A SPECIES PERFORMING WELL AT THE SITE. REFERENCE WETLAND DATA LOCATIONS NAVIGATION CHANNEL NORTH LAKE ADGER RP-9 s 1 At 1. • ..}�e .q S . �, s;,w: x >. SCALE IN FEET SOURCE: AERIAL PHOTOGRAPH ©2020 MICROSOFT CORPORATION ©2020 DIGITALGLOBE ©CNESS (2020) DISTRIBUTION AIRBUS IDS LEGEND: *RP_1 REFERENCE WETLAND DATA LOCATION AND DESIGNATION NOTE: VEGETATION SPECIES AND WETLAND SEED MIXES LISTED IN TABLES z AND 3 ARE GENERALLY BASED ON THE INFORMATION COLLECTED DURING THE REFERENCE WETLAND SURVEY COMPLETED BY CLEARWATER ENVIRONMENTAL CONSULTANTS, INC., ON AUGUST 21-22, z018. REFERENCE ELEVATION (FT, NAVD88) RP-1 913.2 RP-2 911.9 RP-3 913.7 RP-4 912.2 RP-5 913.4 RP-6 911.3 DRAFT -NOT FOR CONSTRUCTION DESIGNED BY: CORK, R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION C8 DRAWN BY: HOLMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE: AS NOTED DATE: JANUARY2021 VEGETATION PLANTING DETAILS SHEET# 11 OF 11 Attachment C Lake Adger Navigation Channel Maintenance Dredging Project Wetland Monitoring Plan Anchor QEA of North Carolina, PLLC ANCHOR 231 Haywood Street�z Asheville, North Carolina 28801 QEA �i 828.281.3350 WETLAND MONITORING PLAN January 12, 2021 Lake Adger Navigation Channel Maintenance Dredging Project Anchor QEA of North Carolina, PLLC, in Consultation with North Carolina Wildlife Resources Commission A plan for maintenance dredging of the public boat ramp and marina navigation channel has been developed by engineering consultant Anchor QEA of North Carolina, PLLC in consultation with North Carolina Wildlife Resources Commission (NCWRC). A component of this plan involves in -lake placement of dredged material to create stable habitat features in proximity to existing wetlands and transitional areas in the forebay of Lake Adger. The placement areas have been identified on sheet C4 of the 90% Design Set submitted with the Response to USACE Comments and Provision of Additional Information'. Monitoring the stability of the placement areas and the success of planted vegetation will be performed by NCWRC staff or a qualified contractor according to the following protocol: 1. Prior to any dredging or placement activity under this permit, NCWRC will send notification to the North Carolina Division of Water Resources (DWR) Environmental Specialists and the U.S. Army Corps of Engineers (USACE) representative with jurisdiction over this project. This notification will describe the proposed dates of dredging and placement activity and include a map identifying the locations and extents of the proposed maintenance dredge and material placement for habitat creation. 2. The dredging contractor will perform a certified as -built survey of the extents and topography of the completed placement area(s) at the end of the dredging and placement phase. The contractor's surveyor will set and locate a benchmark at the high point of each placement area. As -built surveys will be submitted to NCWRC for each dredging and placement operation for inclusion in the monitoring reports. 3. Prior to planting, the elevation benchmarks will be monitored to assess settlement and consolidation of the placed sediment over time. Monitoring of settlement on a weekly and/or monthly basis will allow project engineers to estimate that adequate settlement has occurred prior to planting. 4. Following adequate assessment, the planting contractor and project engineers will estimate total areas and numbers of each planting type, and submit a plan to NCWRC prior to initiating planting. 1 Anchor QEA, 2021. Letter to: David Brown, USACE. Regarding: Response to USACE Comments and Provision of Additional Information. Lake Adger Navigation Channel Maintenance Dredging Project. January 15, 2021. Att C_Wetland Monitoring Plan_2021-01-11.docx January 12, 2021 Page 2 5. Following planting, the planting contractor will prepare a report for NCWRC listing the date, species, and numbers of plantings at each placement area. Once this report has been received, DWR and the USACE will be notified that planting operations have been completed. 6. Six months following completion of planting operations, NCWRC (or contractor) will perform an assessment and report on the condition of the placement area(s) and any other related temporary impacts that will have been replanted. Starting with the initial report, this information will be compiled and forwarded to DWR and the USACE. A standard form will be developed to include the following information for planted placement areas associated with each dredging operation: a. The dredging contractor's as -built survey map, estimates of pre -planting settlement, and the planting contractor's record. b. A visual and photo assessment of the planted areas. Photos may be taken from a boat as viewed from different perspectives and/or from the air by an unmanned aerial system. If significant issues of plant community failure are observed, then NCWRC will map and note the problems in the report and will coordinate corrective actions, if needed. c. The elevations and coordinates of benchmarks previously set on the placement areas will be surveyed and recorded. The elevations and positions will be assessed relative to those surveyed and recorded for the contractor as -built report to measure the extent of any consolidation or movement of the placed material. Any apparent instabilities will be documented. 7. During the monitoring period, any observed problems, instabilities or significant plant mortalities will be noted and communicated to DWR and the USACE. NCWRC staff will begin an evaluation of problems and develop a plan for remediation, if required. 8. Subsequent monitoring of planted areas will take place at 6-month intervals for a period of 3 years after the initial report for the specific activity. Photos, survey data, and observations will be appended to the initial report. At the end of monitoring Year 2, NCWRC, DWR, and the USACE may review conditions of the wetland plantings and decide if the monitoring interval can be reduced to once per 12 months or if there is a need for additional monitoring. 9. Each new dredging episode will require monitoring reports for the resulting placement and planting. Subsequent placement area(s) will be subject to the monitoring plan and time frame described in the above steps. Attachment D Flood Plain Development Permit FLOODPLAIN DEVELOPMENT PERMIT Permit Number 2020-01 Issuance Date 12/15/2020 PIN P41-15 In accordance with the Polk County Flood Damage Prevention Ordinance, a Floodplain Development Permit is hereby granted to: North Carolina Wildlife Resources Commission, Robert Cork, Anchor Oea of North Carolina, PLLC to conduct development activities within the area of special flood hazard on property located at: Lake Adger, N 35.335496, W-82.229212 recorded in Book 383 Page 1925, and Book 364, Page 1582 Registry of Polk County. This Permit is issued to the aforementioned individual, firm, partnership, etc. for the purpose noted above and in accordance with the Polk County Flood Damage Prevention Ordinance, Floodplain Development Permit No. 2020-01 and attachments (13 page letter to U.S. Army Corps of Engineers from Robert Cork, P.E., dated June 12, 2020, and Lake Adger Navigation Channel Maintenance Dredging 10 page document dated June 11, 2020) thereto; and is subject to the following modifications and/or performance reservations: 1. Permit issued for the following development only. Excavation: 6,800 cubic yards Fill: 6,800 cubic yards Grading: Utility Construction: Road Construction: Residential Construction: Nonresidential Construction: Addition: Renovation: Other (specify): dredging and placement of dredge material 2. The lowest floor and all attendant utilities shall be at or above N/A feet Mean Sea Level (MSL). 3. Pursuant to Section 6.5-52e of the Polk County Flood Damage Prevention Ordinance, it shall be the duty of the permit holder to submit to the Floodplain Administrator the Elevation/Floodproofmg Certification within 21 calendar days after establishment of the lowest floor. N/A 4. Proper Erosion and Sediment control measures shall be installed and maintained in accordance with North Carolina State Standards during fill operations. 5. Must comply with attached plans. 6. Provide a no -rise certification, signed and sealed by an engineer within 30 days of completion. Failure to comply with the Polk County Flood Damage Prevention Ordinance including any modifications and/or performance reservations could result in assessment of civil penalties or initiation of civil or criminal court actions. Issued this 15th day of December, 2020 i� Floodplain Administrator for Polk County AnchorQEAof North Carolina, PLLC ANCHOR 231 Haywood Streetkz Asheville, North Carolina 28801 QEAi 828.281.3350 June 12, 2020 David Brown Regulatory Specialist/Geologist U.S. Army Corps of Engineers Wilmington District -Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, North Carolina 28801-5006 Re: Lake Adger Navigation Channel Maintenance Dredging Standard Department of Army Application Form 4345 To Whom It May Concern, On behalf of the North Carolina Wildlife Resources Commission (NCWRC), Anchor QEA of North Carolina, PLLC, is pleased to provide this Application to the U.S. Army Corps of Engineers (USACE) for the Lake Adger navigation channel maintenance dredging. This letter provides additional information to supplement the attached Application for Department of the Army Permit Form 4345 from October 2012 (the Application; Attachment A). Background Lake Adger is located in Polk County, North Carolina. The lake is on the Green River and impounded by the Turner Shoals Dam. The lake is approximately438 acres. AVicinity Map and a Project Area Map are included on sheets G1 and E1, respectively, in the provided 30% Design Submittal for Lake Adger Navigation Channel Maintenance Dredging (30% Design Submittal; Attachment B). NCWRC has estimated that an initial dredging event in 2020/2021 will remove 6,800 cubic yards (cy) of soft sediment from the navigation channel. This includes 3,800 cy to maintain adequate water depths in the navigation channel for recreational use and 3,000 cy to address sediment loss incurred during the lower Big Hungry dam removal in 2014. It is proposed to place the initial estimated 6,800 cy of soft sediment within the Lake Adger footprint as beneficial use for habitat creation, including wetland creation and enhancement, or creation of upland areas. To facilitate future maintenance dredging activities, the 30% Design Submittal includes defined areas referred to as cells (Al, A2, 131, and Cl) with a total estimated capacity for approximately 12,000 cy1 For the purposes of estimated volume of removed versus placed sediment during the 30% design stage, a one-to-one volume is assumed (i.e., no bulking or compaction will occur during the dredging and placement process). It is also assumed that average placement depth will be up to the full pool elevation of 911.61 feet. Lake Adger Maint Dredge Letterdoa June 12, 2020 Page 2 of soft sediment placement. Future maintenance dredging within the navigation channel or sediment discharge within the design cells may occur under this permit through a renewal/modification process. Additional Information to the Application The following subsections address specific blocks of the Application (Attachment A). Block 17. Directions to the Site Attachment C includes directions to the Lake Adger boat ramp from Asheville, North Carolina. Block 18. Nature of Activity The NCWRC is proposing maintenance dredging within the Lake Adger navigation channel to remove accumulated sediment. The navigation channel provides public boat access from the boat ramp at the western end of the lake to the main lake and is adjacent to the Lake Adger marina. During initial proposed dredging activities in 2020/2021 an estimated 6,800 cy of soft sediment will be dredged from the navigation channel and placed for beneficial use within the Lake Adger footprint for habitat creation, specifically wetland creation and enhancement, or creation of upland areas. The 30% Design Submittal depicts the Activity, including existing conditions, project areas, and design details associated with the proposed maintenance dredging. After comments are received from USACE, the 30% Design Submittal will be updated to a 60% Design Submittal, followed by the 100% Design Submittal for construction. Anticipated disturbance for the Activity area will be approximately 22.3 acres, which includes the following: • Staging area: 0.5 acres • Navigation channel dredging disturbance area: 4.5 acres • Material placement disturbance area: 17.3 acres, including 3.9 acres of dredged material placement areas, allowance for sedimentation control, and access The following subsections summarize aspects of the activities. Pre -Design Investigations The following pre -design investigations have been completed to support development of the 30% Design Submittal and will be further used for developing the 60% Design Submittal followed by the 100% Design Submittal for Construction. June 12, 2020 Page 3 Bathymetric and Topographic Surveys Bathymetric and topographic surveys were completed of the Activity area, and of an area of naturally occurring wetlands and uplands near the proposed Activity (the reference wetland) in September and October 2018. The majority of the topographic survey was performed using an unmanned aerial system to collect LiDAR (Light Detection and Ranging) and RGB (red, green, blue) imagerywhen the lake's water level was drawn down 5 feet below normal. Traditional bathymetry surveying methods were used in areas that could not be dewatered, including in the navigation channel. The topographic contours developed by the survey (Attachment D) are included in the 30% Design Submittal. The survey determined that the top of the overflow at the Turner Shoals Dam is at elevation 911.61 feet North American Vertical Datum of 1988 (NAVD88), as surveyed by Hayes, James & Associates, Inc, dated October 9, 2018 (Attachment Q. The elevation of 911.61 feet NAVD88 is considered the full pond level. Wetland Delineation A delineation of jurisdictional wetlands was completed byClearWater Environmental Consultants, Inc. (CEC) August 21 through 22, 2018, and revised for submission to USACE on January 11, 2019. Wetland function was evaluated utilizing the North Carolina Wetland Assessment Method (NC WAM) and data sheets, including the USACE Regional Supplement to the 1987 Manual (Eastern Piedmont and Mountains) Data Form and the NC WAM Field Assessment Form. The USACE issued a Notification of Jurisdictional Determination on February 11, 2019 (Attachment Q. Reference Wetland and Upland Assessment An assessment of naturally occurring wetlands and uplands (the reference wetland) near the proposed Activity was completed by CEC August 21 through22, 2018. This reference wetland is upstream (west) of the Activity area where the Green River enters Lake Adger, and it has developed and regenerated since the creation of the lake in 1925. As presented in Attachment F, six locations within the reference wetland (reference point [RP] 1 to RP6) were assessed using NC WAM methodology to determine the level of function in this wetland area regarding habitat, water quality, and hydrology. The data obtained from the RPs along with the elevation data for these areas will be used to determine vegetation reestablishment within material placement areas, as discussed in the following subsections. Sediment Sampling Study An assessment was performed within the dredging footprint by Anchor QEAon October 5, 2017, to characterize the chemical nature of the sediments. Details are provided in Attachment G. The June 12, 2020 Page 4 analytical results were compared to North Carolina Department of Environmental Quality, Inactive Hazardous Sites Branch, preliminary soil remediation goals (PSRGs) for soil. As discussed in Attachment G, the assessment determined that volatile organic compounds, semivolatile organic compounds, chlorinated herbicides, pesticides, and polychlorinated biphenyls were not detected at concentrations that exceed their laboratory reporting limit in the discrete or composited sediment samples. Multiple metals were detected in the composited sediment samples, but only one constituent (arsenic) exceeded its industrial/commercial PSRG but was less than the estimated arithmetic mean for background concentrations for soil in the eastern United States. Geotechnical Investigations Anchor QEA assessed sediment depth and thickness and physical properties on October 5, 2017, September 20, 2018, and October 18, 2018. The results of the geotechnical investigations have been used in developing the 30% Design Submittal and will be used for the 60% Design Submittal. Hydraulic Modelling A two-dimensional hydraulic model (HEC-RAS 2D) has been created for the Activity area. The model development started with the existing, publicly available USACE HEC-RAS model and was enhanced using the bathymetric and topographic data collected. This enhanced model can be used to simulate velocities and water surface elevations over a range of flow conditions in the Green River and Lake Adger. The developed hydraulic model will be used during the development of the 60% Design Submittal to assess the impact on flow regimes of constructing the placement area. Staging Area The proposed staging area for the Activity will be placed on the southwestern extent of the existing public parking lot, adjacent to the public access boat ramp. The contractor will access the lake from the public access boat ramp or a floating dock. Following dredging activities, the parking lotwill be restored to its current condition or developed for an alternative use, as approved by applicable stakeholders. Navigation Channel Dredging The navigation channel dredging area is approximately 1,500 feet long, with a base width of 20 feet, slope of 1 (vertical) to 3 (horizontal), and elevation of 6 feet below the full pool elevation of 911.61 feet. The navigation channel will be widened in strategic locations to improve navigation by removing 3,000 cy of sediment related to the lower Big Hungry dam removal. Hydraulic dredging techniques are proposed, which will facilitate pumping of the dredged material over a distance of approximately 1,500 feet directly to the material placement area. June 12, 2020 Page 5 During operation of the Turner Shoals Dam for power generation by Northbrook, the lake's surface elevation can vary by 2 to 3 feet during a week. Additionally, the lake can be drawn down and held at 5 feet below the normal level. Northbrook will continue to be consulted during the design stages to discuss managing the lake's surface elevation during dredging and construction of the placement area. Dredged Material Placement Area Throughout the Activity, the dredged material will be placed within the Lake Adger footprint as beneficial use for habitat creation, specifically wetland creation and enhancement, or creation of upland areas. Placing the material using hydraulic dredging discharge will allow course placement within approximate depth and finished level ranges so that the design will include areas of wetland and upland, channels and inlets, and various elevations to enhance hydraulic connectivity to the lake to ensure frequent and prolonged presence of water at or near the soil surface, intermittent flooding, and diverse vegetation establishment. The 30% Design Submittal defined four areas for dredged material placement (Al and A2, B1, and Cl) with a total estimated capacity for approximately 12,000 cy2 of soft sediment placement, up to full pool elevation. During material placement, these cells will be bordered by up to three separate structures (as shown in Sheet C5 of the 30% Design Set): 1. An initial structure designed to hold the sediment in place will be constructed of biodegradable and/or temporary containment materials. Containment materials may include haybales stacked up to two layers high with a base width of two haybales, coir fiber biologs, or an equally effective alternative. Containment materials will be secured in place with biodegradable stakes, or an equally effective alternative method. 2. A second structure constructed similarly to the firstwill create a secondary dewatering barrier to reduce sediment in discharged water. 3. After the two initial structures a silt curtain will be placed downgradient to assistwith sedimentation control. Based on the 30% Design Submittal, it is anticipated that the initially dredged 6,800 cywill be placed in cells Al and A2. These two cells will allow improved management of the dewatering process by allowing the discharge to be alternated between the two cells. For construction of cells Al and A2, it is estimated that 840 feet of initial containment structures will be required, followed by 700 feet of secondary containment structures, and up to 900 feet of silt curtain. z For the purposes of estimated volume of removed versus placed sediment during the 30% design stage, a one-to-one volume is assumed (i.e., no bulking or compaction will occur during the dredging and placement process). It is also assumed that average placement depth will be up to the full pool elevation of 911.61 feet. June 12, 2020 Page 6 Following the initial dredging effort of 6,800 cy, additional capacity will remain in areas Al and A2, 131, and C1 for future maintenance dredging events. These areas will only be delineated with containment structures when needed for dredged material placement. Monitoring During Dredging and Placement Activities3 Turbidity will be monitored during the Activity using hand-held or automated turbidity meters to record Nephelometric Turbidity Units (NTU). Background data will be collected at a station located upstream of the dredging and dredge material placement area. A monitoring location will be established 1,000 feet downstream of dredging and material placement operations. During the first week of operations data will be collected daily at the upstream background location, and twice daily at the downstream monitoring location. The turbidity criteria will be that turbidity measured downstream of dredging operations at the monitoring location are less than 50 NTUs above turbidity measured atthe upstream background location. If turbidity downstream of dredging and dredge material placement operations is more than 100 NTUs above the upstream background location, it will trigger review/evaluation of the Activity, and response actions. An evaluation will be conducted to assess the cause of the exceedance and the need for operational changes or other response actions. The evaluation may result in one or more of the following actions, to be determined in the field: • Increase frequency of monitoring at both background and downstream locations to hourly • Review work operations and best management practices • Identify additional best management practices to employ (e.g., additional containment around the placement area) • Reduce dredging and/or dredge material placement rate(s) If no issues or exceedances are observed during the firstweek, data collection at the downstream monitoring location will be reduced to once daily. Habitat Establishment Establishing habitat including beneficial wetlands and upland, is a common approach in lakes, rivers, and estuaries to stabilize shorelines, restore habitat, and beneficially use dredged materials. After the dredged soft sediment is placed in the cells, habitat establishment will include native wetland and/or upland vegetation species dependent on the final elevation of placed sediment. Placed sediment depth and final elevation will vary based on placement of the hydraulic dredging discharge line, variable rates of passive dewatering, and compaction and subsidence. Varied final elevations will promote establishment of plant species that differ in their ability to withstand prolonged inundation or dry periods. The material's final elevation will be determined with a finished level survey. a Details of the monitoring plan proposed herein will be refined with inputfrom the regulatory agencies. June 12, 2020 Page 7 Native emergent wetland and upland species identified at the nearby reference wetlands (Table 1) will be planted on the dredged material to stabilize the material and provide ecological benefits. In addition to the planting, the site will be seeded with a wetland seed mix containing a variety obligate and facultative wetland (FACW) species (similar to the mix shown in Table 2) to provide additional species diversity and ground cover. Non-native and invasive species will not be planted. Planting will occur in the next suitable planting season following placement of the dredge material to allow for passive dewatering and settlement. Plants will be 2-inch plugs and planted on two -foot centers (i.e.: 10,890 plants per acre). During vegetation establishment, herbivory control measures will be installed as required to reduce predation bywildlife and waterfowl. Herbivory control measures are anticipated to include construction fencing attached to posts around the perimeter of the planted area, and possible covering by grid of wire/string to which flagging tape is attached. Signage and flagging may be added as appropriate to minimize public access until the plants have established resiliency to foot traffic and seasonal variations (generallyfor one or two growing seasons). Emergentwetland vegetation has relatively lowtolerance for wave energy and currents because they can break the plants and wash away finer material, making the substrate too coarse. Therefore, the containment structures (such as hay bales or coir fiber biologs) will be left in place until they biodegrade to allow establishment of vegetation. Table 1 Emergent Vegetation Species Common Name Scientific Name Broadleaf cattail Typha latifolia Common arrowhead Sagittaria latifolia Wo o I grass Scirpus cyperinus Soft stem bulrush Schoenoplectus tabernaemontani Fringed sedge Carex crinita Pickerelweed Pontederia cordata Soft rush Juncus effusus Water willow Justicia americana June 12, 2020 Page 8 Table 2 Wetland Seed Mix Common Name Scientific Name Common Water Plantain Alisma subcordatum Swamp Milkweed Asclepias incarnata Common Hop Sedge Carex lupulina Lance -Fruited Oval Sedge Carex scoparia Brown Fox Sedge Carex vulpinoidea Turtlehead Chelone glabra Common Wood Reed Cinna arundinacea Flat -Top Aster Doellingeria umbellata Virginia Wild Rye Elymus virginicus Common Boneset Eupatorium perfoliatum Hollow Joe-Pye Weed Eutrochium fistulosum Sneezeweed Helenium autumnale False Sunflower Heliopsis helianthoides Common Rush Juncus effusus Great Blue Lobelia Lobelia siphilitica Monkey Flower Mimulus ringens Ditch Stonecrop Penthorum sedoides Dark Green Rush Scirpus atrovirens Wool Grass Scirpus cyperinus Side -Flowering Aster Symphyotrichum lateriflorum New England Aster Symphyotrichum novae-angliae Marsh Shield Fen Thelypteris palustris Blue Vervain Verbena hastata Boneset Eupatorium perfaliatum June 12, 2020 Page 9 Table 3 Tree and Shrub Species Common Name Scientific Name Trees American elm Ulmus americana River birch Betula nigra Black willow salix nigra Red maple Acer rubrum Box elder Acer negundo American sycamore Plantanus occidentalis Shrubs Spicebush Lindera benzoin Smooth alder Alnus serrulata Silky dogwood Corpus amonum Post -Construction Monitoring Plan Following habitat establishment and planting activities, the following monitoring activities are anticipated in the areas planted and seeded with vegetation: • Herbivory controls, signage, and flagging will be inspected biweekly during the growing season and repaired as needed. • Annual monitoring for 3 years to document vegetation coverage and establishment. The details of the monitoring plan will be developed with input from regulatory agencies. Block 19. Proposed Project Purpose Maintenance dredging of the navigation channel is required to maintain adequate water depths in the navigation channel for recreational use and to remove 3,000 cy of sediment related to the lower Big Hungry dam removal. Performing wetland and upland creation with dredged material will enhance habitat within the lake footprint by extending existing wetland areas. Enhancing natural functions can include helping to reduce frequency and intensity of floods, thereby protecting the area against storm surges; providing critical habitat, breeding grounds, and food resources for organisms; improving water quality, and offering commercial, recreational, and aesthetic benefits. Dredging and construction activities are anticipated to begin fall/winter 2020 and to be completed early 2021. Block 20. Reasons for Discharge Dredged material will be discharged to the area designated on the 30% Design Submittal. This in - lake placement will occur because no viable option has been identified for ex situ transport to and June 12, 2020 Page 10 placement of dredged material. Hauling the material outside of the Activity area would require a dewatering process, an estimated 480 to 680 truck movements4, with additional placement, compaction, stabilization, and revegetation activities required in area of placement. Dredged material placement within the lake's footprint provides the following benefits: • Efficient relocation of dredged material with minimal double handling and in situ dewatering rather than requiring a separate dewatering operation • Creation of a natural habitat • A long-term solution of possible future dredging needs through the use of cells for placement Block 21. Types of Material Being Discharged and the Amount of Each Type in Cubic Yards During the initial proposed dredging activities in 2020/2021, approximately 6,800 cy of dredged material generally comprised of 50% sand, 30 to 40% gravel, and 10 to 20% silt and clay will be dredged from the navigation channel. Debris encountered during dredging will be disposed of outside of the Activity area if inorganic (e.g., trash and treated timber) or placed in the placement area if it is organic and natural (e.g., logs and tree branches). Block 22. Surface Areas of Wetlands or Other Waters Filled Approximately 3.0 acres of water within areas Al, A2, B1, and C1 may be filled with the dredged material, with the initial dredging of 6,800 cy filling approximately 1.8 acres within areas Al and A2. Based on the delineation of jurisdictional wetlands and pending completion of the 60% Design Submittal, it is anticipated that 1.1 acres of wetland below the full pond level (911.61) will be filled within areas Al and A25. Dredged material will be pumped to the placement area using hydraulic dredging techniques. Management of the placed materials is described in Block 18 and the attached 30% Design Submittal. Block 23. Description of Avoidance, Minimization, and Compensation Avoidance and minimization of impacts to waters of the United States are described in Block 18. Strategies include the use of silt curtains to contain impacts to the project area, and monitoring. The contractor will be trained in a safety and environmental procedures, which includes strict containment protocol to minimize the potential for surface water impacts. Compensation for wetland impacts is not required as the Activity will result in a gain of wetlands and habitat development. Per Block 22, approximately 1.1 acres of wetland will be filled, with an 4 Based on dump truck capacities of 10 to 14 cy and an assumed requirementto transport6,800 cy of material (dependent on volume bulking and reduction during dredging and dewatering activities). s No wetland within Areas B1 orC1 is anticipated to be filled. June 12, 2020 Page 11 additional 3.0 acres of delineated wetlands will possibly be impacted by operational activities required for access and placement of the hydraulic dredge discharge. Block 24. Is Any Portion of the Work Already Complete? During August 2019, approximately 600 cy of dredged material was removed using mechanical dredging methods and transported outside of the Activity area to the Polk County landfill. This work occurred under the oversight of the NCWRC, with approval from Polk County and the USACE. Block 25. Names and Addresses of Adjoining Property Owners, Lessees, etc., Whose Property Adjoins the Project Site. Adjacent property owners have been added to the Adjoining Property Owners List (Attachment H). Maps depicting the parcel boundaries and ownership are included with this submittal (Attachment 1). Owner and additional stakeholders of Lake Adger include: • Polk County: owner • NCWRC: responsible for maintaining adequate water depths for the public boat ramp and marina under an agreementwith Polk County, and holding a perpetual easement to the public parking area and boat ramp • Northbrook Energy (Northbrook): Turner Shoals Hydropower facility operator • Lake Adger Property Owner's Association: responsible for routine maintenance of the public parking area and boat ramp Block 26. Information About Approvals or Denials by Other Agencies No other certificates or approvals/denials from federal, state, or local agencies pertaining to the activities described in the Application have been received at the time of writing. Anchor QEA understands that USACE will initiate contact with the following regulatory agencies as a part of the Department of the Army Permit process. NCWRC and Anchor QEA will respond and coordinate with other agencies as requested by the USACE. Other permit approvals will be acquired by Anchor QEA as indicated in Table 4. June 12, 2020 Page 12 Table 4 Other Permits Approvals Agency Transmittal State Stand and Individual Permit AppIicationforActivities USACE Affecting Waters of the United States USACE to contact; consultation letters provided by U.S. Fish and Wildlife Service Anchor QEA; Endangered Species Act Review USACE to contact; consultation letters provided by North Carolina State Historic Preservation Office Anchor QEA; Section 106 Project Review North Carolina Department of Environmental Quality USACE to contact North Carolina Department of Environmental Quality, Division of Water Resources USACE to contact Eastern Band of Cherokee Indians USACE to contact Polk County Soil & Water Conservation District USACE to contact North Carolina Division of Parks and Recreation USACE to contact June 12, 2020 Page 13 Conclusion The NCWRC plan to initially dredge 6,800 cy of sediment in fall/winter 2020 or early 2021 upon receipt of a Department of the Army Permit. This letter is being submitted in support of the Application (Attachment A) for your review. Please contact me at 828-281-3350 or rcork@anchorgea.com if you have any questions. Sincerely, Robert Cork, PE MEng Managing Engineer Attachments Attachment A Application for Department of the Army Permit Form 4345 Attachment B 30% Design Submittal for Lake Adger Navigation Channel Maintenance Dredging Attachment C Directions to Lake Adger Boat Ramp from Asheville, North Carolina Attachment D Lake Adger Topographic Worksheet (survey) Attachment E Notification of Jurisdictional Determination Attachment F Reference Wetland Data Forms Attachment G Lake Adger Sediment Sampling Summary Attachment H Adjoining Property Owner Map Attachment I Adjoining Property Owners List 30% DESIGN SUBMITTAL LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING NORTH CAROLINA WILDLIFE RESOURCES COMMISSION i� s� ,aa peyan � 7 y:�P �ar+nE o PROJECT LOCATION er S ea 3 yi 0 NORTH 0 4000 8000 SCALE IN FEET F't Co�larrs �Q Sunny V€ew SOURCE: ©2019 Microsoft Corporation ©2018 HERE VICINITY MAP NORTH CAROLINA Asheville • Charlotte Raleigh Project NOT TO SCALE NORTH CAROLINA , ®/-/Q� ryEA ANCHOR KnowWhaesbelow. l [ call before yaudig. RESOURCES COMMISSION REVISIONS DESCRIPTION DRAWING INDEX SHT # DWG # TITLE 1 G1 TITLE SHEET 2 G2 GENERAL NOTES, LEGEND, AND ABBREVIATIONS 3 E1 EXISTING CONDITIONS 4 C1 DREDGE PLAN 5 C2 PROFILE 6 1C3 ISECTIONS 7 C4 DREDGED MATERIAL PLACEMENT LAYOUT 8 C5 IMPACTED AREAS 9 CIS DETAILS 10 C7 VEGETATION PLANTING DETAILS o� V �o 0Z o¢� 00 w¢ z z0 zoo Q V w a Z m w � Z O Z O V Z O w V Z - V N w O V w I QV Z_ DRAFT -NOT FOR CONSTRUCTION DESIGNED BY: CORK, R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION G1 DRAWN BY: HOLMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE AS NOTED TITLE SHEET �0 DATE: JUNE 2020 SHEET# OF GENERAL NOTES FOR MAINTENANCE DREDGING 1. THE CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS BEFORE BEGINNING CONSTRUCTION AND WILL IMMEDIATELY INFORM THE SERVICE OF ANY DISCREPANCIES FOUND BETWEEN THE PROJECT PLANS AND CONTRACT SPECIFICATIONS PRIOR TO PROCEEDING WITH THE WORK. 2. CONTRACTOR SHALL STRICTLY ENFORCE ALL APPLICABLE HEALTH AND SAFETY LAWS (I.E. OSHA) AND MAINTAIN SITE SECURITY. 3. CONSTRUCTION KICK-OFF MEETING WITH THE NORTH CAROLINA WILDLIFE RESOURCES COMMISSION, THE ENGINEERAND OTHER RELEVANT STAKEHOLDERS IDENTIFIED IS REQUIRED PRIOR TO ANY ONSITE WORK. 4. CONTRACTOR SHALL PROVIDE A SEQUENCE OF CONSTRUCTION TO BE APPROVED BY THE NORTH CAROLINA WILDLIFE RESOURCES COMMISSION, AND THE ENGINEER PRIOR TO SITE MOBILIZATION. 5. CONTRACTOR SHALL FIELD VERIFY THE EXISTING CONDITIONS WITHIN THE LIMITS OF WORK AND WILL BE RESPONSIBLE FOR DETERMINING APPROPRIATE QUANTITIES AND REQUIRED MATERIALS TO COMPLETE THE WORK. 6. CLEARING TO BE LIMITED TO THE LIMIT OF DISTURBANCE AS SHOWN ON THE PLANS. WORK SHOULD LIMIT TREE REMOVAL BY WORKING AROUND EXISTING TREES AS POSSIBLE. CONTRACTOR MUST RECEIVE APPROVAL FROM THE SERVICE PRIOR TO REMOVAL OF ANY TREES. 7. THE HORIZONTAL DATUM SHALL BE BASED ON NORTH CAROLINA STATE PLANE, NAD83, U.S. SURVEY FEET. THE VERTICAL DATUM SHALL BE BASED ON NAVD88. THE HYDROGRAPHIC SURVEY WAS COMPLETED BY HAYES, JAMES & ASSOCIATES, INC., IN OCTOBER 2018. 8. INFORMATION CONCERNING UNDERGROUND UTILITIES WAS OBTAINED FROM AVAILABLE RECORDS, BUT THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING EXACT LOCATIONS AND ELEVATIONS OF THE LINES BY DIGGING TEST PITS BY HAND AT ALL UTILITY CROSSINGS, WELL IN ADVANCE OF TRENCHING. IF CLEARANCES ARE LESS THAN SHOWN OR SIX (6) INCHES, WHICHEVER IS LESS, CONTACT THE SERVICE IMMEDIATELY. 9. CALL "NORTH CAROLINA 811" AT 811 OR 1-800-632-4949 FORTY-EIGHT (48) HOURS PRIOR TO BEGINNING EXCAVATION OR DREDGING TO DETERMINE THE EXACT LOCATION OF EXISTING UTILITIES. 10. ADDITIONAL UNDERWATER UTILITIES MAY EXIST ELSEWHERE WITHIN THE PROJECT EXTENTS. CONTRACTOR SHALL FIELD VERIFY ANY IN -WATER UTILITIES, CROSSINGS OR POTENTIAL IMPEDIMENTS TO THE WORK AND TAKE ADEQUATE PRECAUTIONS TO AVOID THEM. 11. REPAIR TO UTILITIES OR PROPERTY DAMAGE AS A RESULT OF THE CONTRACTOR'S NEGLIGENCE OR METHOD OF OPERATION MUST BE MADE AT THE CONTRACTOR'S EXPENSE BEFORE CONTINUING WITH CONSTRUCTION. 12. ANY DAMAGES THAT MAY OCCUR TO REAL PROPERTY OR EXISTING IMPROVEMENTS SHALL BE RESTORED BY THE CONTRACTOR TO AT LEAST THE SAME CONDITION THAT THE REAL PROPERTY OR EXISTING IMPROVEMENTS WERE IN PRIOR TO THE DAMAGES. THIS RESTORATION SHALL BE SUBJECT TO THE OWNER'S APPROVAL; MOREOVER, THIS RESTORATION SHALL NOT BE A BASIS FORADDITIONAL COMPENSATION TO THE CONTRACTOR. RESTORATION SHALL INCLUDE, BUT NOT BE LIMITED TO, REGRASSING, REVEGETATION, REPLACING FENCES, REPLACING TREES, ETC. 13. ALL UPLAND GRADING SHALL BE DONE IN SUCH A MANNER AS TO PROVIDE POSITIVE DRAINAGE. 14. DISTURBED UPLAND AREAS SHALL BE GRADED AND RESTORED TO ORIGINAL CONDITIONS. DISTURBED AREAS ADJACENT TO ESTABLISHED LAWNS SHALL BE SODDED. OTHER DISTURBED AREAS SHALL BE SEEDED AND MULCHED. ALL DISTURBED AREAS ARE TO BE STABILIZED AND SEEDED WITHIN 14 DAYS OF DISTURBANCE UNLESS OTHERWISE NOTED. SLOPES STEEPER THAN 3:1 MUST BE STABILIZED IN 7 DAYS. INSTALL TEMPORARY SEEDING ON ALL AREAS THAT WILL BE LEFT IDLE FOR MORE THAN 14 DAYS. HARD WOOD MULCH IS AN ACCEPTABLE TEMPORARY COVER BUT MAY NOT BE BLENDED INTO THE SUBGRADE AND WILL BE REQUIRED TO BE REMOVED PRIOR TO CONTINUATION OF THE WORK. STRAW MULCH AND TALL FESCUE SHOULD NOT BE USED IN RIPARIAN AREAS. 15. THE CONTRACTOR SHALL PROTECT ALL UTILITIES, AND EXISITNG INFRUSTRUCTURE DURING CONSTRUCTION, AND ALL WETLANDS DURING CONSTRUCTION OPERATIONS. 16. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE WETLAND BOUNDARIES ARE UNDERSTOOD PRIOR TO BEGINNING WORK. 17. THE CONTRACTOR SHALL OBEY ALL COUNTY HEIGHT, WEIGHT AND UNDERCLEARANCE RESTRICTION S.TH E CONTRACTOR SHALL OBEY ALL APPLICABLE NOISE RESTRICTIONS. 18. ALL SITE ACTIVITIES INCLUDING BUT NOT LIMITED TO CLEARING, WATER LEVEL DRAWDOWN, DREDGING, DEWATERING, WATER TREATMENT, TRANSPORTATION, AND DISPOSAL, SHALL FOLLOW ALL APPLICABLE PERMITS AND CONTRACT DOCUMENTS. 19. VEHICLES TRANSPORTING DEWATERED MATERIAL FROM THE STAGING AREA TO THE FINAL SELECTED AND APPROVED LOCATION MUST FOLLOW POSTED SPEED LIMITS, TRAFFIC SIGNS AND SIGNALS, AND ALL COUNTY HEIGHT, WEIGHT AND UNDERCLEARANCE RESTRICTIONS. CONTRACTOR SHALL NOT TRACK OR DISCHARGE SEDIMENT ONTO ROADS. NORTH CAROLINA ANCHOR , �2EAa�b .v q \ RESOURCES 20. THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL PERMITS NECESSARY FOR CONSTRUCTION NOT SUPPLIED BY THE WILDLIFE RESOURCES COMMISSION. THIS MAY INCLUDE BUT NOT BE LIMITED TO: ANY REQUIRED EROSION CONTROL OR LAND DISTURBANCE PERMITS, ARMY CORP OF ENGINEERS PERMITS, STORMWATER PERMITS, NPDES, CITY OR COUNTY BUILDING PERMITS, OR ROADWAY PERMITS. THE COSTS FOR ADDITIONAL PERMITS WILL BE THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL NOT IMPACT THE PROJECT SCHEDULE. 21. CONTRACTOR SHALL IMPLEMENT EROSION AND SEDIMENT CONTROL AND MAINTAIN EROSION AND SEDIMENT CONTROL MEASURES AS NECESSARY TO COMPLY WITH COUNTY, STATE, AND FEDERAL LAWS AND REGULATIONS. ANY SEDIMENT CONTROL MEASURES DISTURBED BY CONSTRUCTION WILL BE REPAIRED THE SAME DAY. 22. CONTRACTOR SHALL SUBMIT CONSTURCTION WORK PLAN AND ANCILLIARY WORK PLANS IN ACCORDANCE WITH THE SPECIFICATIONS. 23. STOCKPILES MAY ONLY BE PLACED IN APPROVED LOCATIONS. ALL STOCKPILES LEFT AT THE END OF THE DAY NEED TO BE STABILIZED UNTIL THE NEXT DISTURBANCE. 24. BARRICADING AND TRAFFIC CONTROL DURING CONSTRUCTION SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL CONFORM TO THE NCDOT STANDARD SPECIFICATIONS AND DRAWINGS. PEDESTRIAN AND VEHICULAR TRAFFIC FLOW SHALL BE MAINTAINED DURING ALL PHASES OF THE CONSTRUCTION. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING TRAFFIC SAFETY MEASURES FOR WORK ON PROJECT. 25. WHERE EXISTING GRADE EXCEEDS 5:1 (HORIZONTAL:VERTICAL) AND THE DEPTH OF FILL EXCEEDS 5 FEET, BENCHING SHALL BE PROVIDED. A 2-FOOT DEEP BY 10-FOOT WIDE KEY SHALL BE PROVIDED AT THE TOE OF THE FILL SLOPE. REFER TO NC BUILDING CODE SECTION 107 FOR ADDITIONAL DETAIL. 26. CERTIFICATION OF CUT AND FILL SLOPES SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL BE MADE BY GEOTECHNICAL ENGINEER LICENSED TO PRACTICE IN THE STATE OF NORTH CAROLINA. UNLESS OTHERWISE NOTED, ALL CUT AND FILL SLOPES PROPOSED BY THESE PLANS SHALL BE 2:1 (HORIZONTAL:VERTICAL) OR FLATTER. 27. CUT AND FILL SLOPES (EMBANKMENTS) SHALL BE CONSTRUCTED IN ACCORDANCE WITH NCDOT STANDARD SPECIFICATION SECTION 235 OR THE GEOTECHNICAL (SOILS) REPORT RECOMMENDATIONS, WHICHEVER IS MORE RESTRICTIVE. AT A MINIMUM, ALL FILL SLOPES SHALL BE PLACED IN 10-INCH MAXIMUM LIFTS COMPACTED TO NOT LESS THAN 95 PERCENT DENSITY (STANDARD PROCTOR). CONTRACTOR SHALL ARRANGE FOR INDEPENDENT COMPACTION TESTING RESULTS TO BE PAID FOR BY THE OWNER/DEVELOPER. 28. NO GRADING OR FILL SHALL OCCUR WITHIN 2 FEET OF A PROPERTY LINE WITHOUT WRITTEN PERMISSION FROM THE ADJACENT PROPERTY OWNER. 29. UNLESS OTHERWISE INDICATED IN THESE PLANS TERRACES SHALL BE PROVIDED AS FOLLOWS: WHERE GRADES EXCEED 3:1 (HORIZONTAL:VERTICAL), TERRACES AT LEAST 6 FEET IN WIDTH SHALL BE CONSTRUCTED AT NOT MORE THAN 30-FOOT VERTICAL INTERVALS ON ALL CUT OR FILL SLOPES. SWALES SHALL BE PROVIDED ON TERRACES IN ACCORDANCE WITH NC BUILDING CODE SECTION JI09. 30. CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT THE WORK DOES NOT RESULT IN UNACCEPTABLE INCREASES IN TURBIDITY WITHIN THE LAKE OR SURROUNDING STREAMS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR IMPLIMENTING MESURES TO CONTROL TURBIDITYAS NEEDED. 31. ALL MECHANIZED EQUIPMENT OPERATED NEAR SURFACE WATERS SHOULD BE INSPECTED AND MAINTAINED REGULARLY TO PREVENT CONTAMINATION OF STREAM WATERS FROM FUELS, LUBRICANTS, HYDRAULIC FLUIDS OF OTHER TOXIC MATERIALS. 32. DISCHARGING HYDROSEED MIXTURES AND WASHING OUT HYDROSEEDERS AND OTHER EQUIPMENT IN OR ADJACENT TO SURFACE WATERS IS PROHIBITED. 33. EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSPECTED DAILY AND AFTER ANY RAINFALL. DEFICIENCIES SHALL BE CORRECTED IMMEDIATELY. A DAILY RECORD SHALL BE MAINTAINED ON THE SITE BY THE CONTRACTOR. PROJECT SITE CONDITIONS MAY REQUIRE INSTALLATION OF ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES. EROSION CONTROL MEASURES AND MAINTENANCE SHALL BE IN ACCORDANCE WITH THE NORTH CAROLINA EROSION AND SEDIMENT CONTROL MANUAL. 34. CONTRACTOR WILL MAINTAIN PUBLIC ACCESS TO BOAT RAMP AND FACILITIES AT ALL TIMES, OR LIMIT BLOCKING OF ACCESS WITH ADVANCED NOTICE TO THE PUBLIC. 15Know what'sb0I0W. , Call before you dig. DATUMS: ABBREVIATIONS: 1. HORIZONTAL DATUM: NORTH CAROLINA, NORTH AMERICAN DATUM (NAD83), FEET, MINUTES U.S. SURVEY FEET INCHES, SECONDS 2. VERTICAL DATUM: NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88), FEET DEGREES 0 DIAMETER # NUMBER SOURCES: APPROX APPROXIMATE CONC CONCRETE 1. AERIAL PHOTOGRAPH ©2019 MICROSOFT CORPORATION ©2019 DIGITALGLOBE CY CUBIC YARDS ©CNESS (2019) DISTRIBUTION AIRBUS DS DIA DIAMETER DWG DRAWING 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED AUGUST 27, 2018. E EAST, EASTING ELEV ELEVATION GENERAL LEGEND: EX EXISTING FG FINISHED GRADE FL FLOW LINE PROPOSED: GALV GALVANIZED 14+00 PROJECT STATIONING HOR HORIZONTAL H I I I H L LENGTH LF LINEAR FEET DREDGE AREA (PRIMARY) MAX MAXIMUM 905 DREDGE CONTOURS (1' INTERVAL) MIN MINIMUM MLLW MEAN LOWER LOW WATER N NORTH, NORTHING - • - • - DREDGE AREA (CONTINGENCY) NAD NORTH AMERICAN DATUM NAVD NORTH AMERICAN VERTICAL DATUM EXAMPLE HAYBALE LOCATION P.E.A. PROFESSIONAL ENGINEER S EXAMPLE SILTFENCE LOCATION R, RAID RAID RADIUS RE REINFORCED, REINFORCEMENT - - - - LIMITS OF DISTURBANCE ROW RIGHT-OF-WAY S SLOPE, SOUTH SITE ACCESS ROAD STA STATION SY SQUAREYARD - - - - STAGING AREA TESC TEMPORARY EROSION AND SEDIMENT CONTROL TYP TYPICAL EXISTING: W WEST, WATER W/ WITH 905 TOPOGRAPHY (1' INTERVAL) WSEL WATER SURFACE ELEVATION 0 0 CHANNEL MARKERS > ----{ CULVERT ROAD ---- - ---- --- ----- SHORELINE (NORMAL POOL ELEVATION 911.61') DETAIL AND SECTION REFERENCING: DETAIL REFERENCE NUMBER 1 DRAWING ON WHICH DETAIL APPEARS C1 '-" INDICATES TYPICAL OR ON SAME DRAWING DETAIL REFERENCE NUMBER 1 DETAIL _ SCALE: 1" = 10' DICATES DIRECTION o CUTTING PLAN 3 t XA o mm SECTION "A" IS SHOWN ON DRAWING "C-2"_ w C2 o¢I < w z z o SECTION REFERENCE LETTER A SECTION zo_ SCALE: 1" = 10' PLAN NUMBER WHICH SECTION WAS TAKEN ¢ V J a z w� z oz o zo V LL V Z - V w O � V LLs QV Z_ DRAFT -NOT FOR CONSTRUCTION REVISIONS DESIGNED BY: CORK,R. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE: AS NOTED DATE: JUNE 2020 NORTH CAROLINA WILDLIFE RESOURCES COMMISSION �� SHEET# Z OF f0 DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING GENERAL NOTES, LEGEND, AND ABBREVIATIONS M 0 PUBLIC ACCESS BOAT RAMP 0 LEGEND: —905— EXISTING TOPOGRAPHY (1' INTERVAL) — ---- — SHORELINE (NORMAL POOL ELEVATION 911.61') 00 CHANNEL MARKERS - SUMMER 2019 907 J FLOATING e909 c •o a • r ° ° DOCK .° 0 o a O � � o EXISTING t CULVERT o �° •o' 1 LAKEADGER 1 a (FULL POOL ELEVATION 911.61) ��.i8.�p o LAKEADGER 1 �� r.i0 O .10 (: J: o NORTH _. � •p �.�p�.. :,.: � ' ., d,,...1':°.,i `�;�;,. f' r SCALE IN FEET 70 p ,'L ; I. .:'' .:.� .� s �C'a r•. !, fir'! ° . f� ..F , _ r... .O 1' .S � r a o 910 % ..r K ....! . 1 / R ! ; ' ... • J l i ..r ifj� ...� r' p�..�.:r°. ,. �' J. c' P i o- Ji i• Ji' �1 /.$� r: O O :.r..._..,1 0.` f.. J.:yl'`r aC a �,j//� ��•° ! .i• i o�$�'•.5:. CP\ ..moo .�'•.i�, J.' �i � i .[d .�:1�.� .l.r.: p0•. _�.1 ° :� fi.r w !pi / ! a ♦ 1 0� .� �: t`.^ `. 'v • Ill J l ,{:.e.� .� y 1 '.1 r�'J' • V T o i /' ,r a ..�-. / -.��1 _ t... .I. J♦ '.s rf, Ltc w : .i :o / a \. .I.:� � e• �� 0 Y � z m r=: o i 91 o ' r" F 0 ° •m b • r 1 Jo � f .. r..• .��1 . .. r:',A ° • I..L .� \� �' o' Oar .i' �`� /�� J w �. L..x `•• r P DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH REV DATE BY AP P D DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION E1 ANCHOR �•y CAROLINA DRAWN BY: HOLMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING r-y ®r.lr r , Know Whans below. CHECKED BY: REEMTS, M. a l�vi\ / ' CBII befareyaudig. QEA�`/ RESOURCES APPROVED BE DIN (COLA, W. COMMISSION SCALE: AS NOTED DATE: IUNE1010 EXISTING CONDITIONS SHEET# 3 OF 10 - � .. aQ ♦�E PUBLIC ACCESS �. Q� i. BOAT RAMP W}l / PRO/NA D �P� �l \ IjP Kr �0 i y STAGIREA 0 (0. ACRES) f .04 •K _ /. .\ •�•\ •\ xoLl ..-�i ��-axe° / • � • ' \ • \ ,\ \ , �l \ \ \ 51 \ LAKE ADGER o / \ 00 !. _ . �1+,OfL • — - —12+00 13+00 I 14+00 LAKEADGER — (FULL POOL ELEVATION 911.61) \ I• APPROXIMATE AREA OF DISTURBANCE \ I = FOR DREDGING: 4.5 ACRES LEGEND: 14�� PROJECT STATIONING NAVIGATION CHANNEL DREDGE AREA APPROXIMATE EXTENTS — • — MITIGATION DREDGE AREA APPROXIMATE EXTENTS — APPROXIMATE LIMITS OF DISTURBANCE - DREDGING AREA — — — WETLAND DELINEATION — —--- — SHORELINE (NORMAL POOL ELEVATION 911.61') 15+00 0 NORTH 0 60 12C SCALE IN FEET \ NOTES: 1. HORIZONTAL DATUM: NORTH CAROLINA, NORTH AMERICAN DATUM (NAD83), U.S. SURVEY FEET w m mw T 2. VERTICAL DATUM: NORTH AMERICAN VERTICAL o a i DATUM OF 1988 (NAVD88), FEET o 0 w¢ = SOURCES: z ? ° zo? Q V � 1. AERIAL PHOTOGRAPH ©2019 MICROSOFT E� z F y CORPORATION ©2019 DIGITALGLOBE©CNESS \i (2019) DISTRIBUTION AIRBUS DS 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED J 00 r o = CIO�Q �. AUGUST 27, 2018. z ? o z DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH REV DATE BY AP DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION ANCHOR CAROLINA , , KIIDW WI13��5 bP.IOW. Call before yaudig. DRAWN BY: HOMER, D. CHECKED BY: REEMTS, M. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING �v QEA�`/ /' RESOURCES APPROVED BE DIN (COLA, W. SCALE: NOTED COMMISSION JU DATE: ,uNEzozo DREDGE PLAN sHEETre 4 of 10 LAKE ADGER CHANNEL CENTERLINE 920 920 z 910 910 w w�U\ ----- ------ ------ ----- ------ ------ ----- ------ ------ ----- ------ ------ ----- ------ ------ ----- ------ ------ ----- ----- Z_ 3 Z O 900 900 � ww w Z V H 890 4 890 0+5C 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 HORIZONTAL DISTANCE IN FEET 5X VERTICAL EXAGGERATION LAKE ADGER CHANNEL CENTERLINE 920 920 _... _... ¢ 910 910 z w w w— — — — — — — — — — — — — — — — ————————------ ---- z 0 � 900 900 z u, — V H 890 89C 10+00 10+50 11+00 11+50 12+00 12+50 13+00 13+50 14+00 14+50 15+00 HORIZONTAL DISTANCE IN FEET 5X VERTICAL EXAGGERATION o� V � O 0 Z z Q w I 0 z_ 0 Z 0 ¢ V Z m LEGEND: EXISTING MUDLINE w� DESIGN DREDGE ELEVATION 0 z 0 — — — — — — — V ALLOWABLE OVERDEPTH s o V LL V DREDGED MATERIAL TO BE REMOVED z N w 0 — --- _...— ..— LAKE ADGER FULL POOL ELEVATION 911.61' J LLs ¢ z NOTE: ALL DESIGN SLOPES ARE 3H:1V UNLESS OTHERWISE NOTED. DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION REV DATE BY AP DESCRIPTION CAROLINA DRAWN BY: HOMER, D. �� LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING �I AANCHOR , f ' , Kno/w�whaPsbelow. Call before youd19. CHECKED BY: DINICO, M. APPROVED BY : DIN (COLA, W. � RESORCES COMDATE: SCALE: AS NOTED JUNE2020 PROFILE SHEET# 5 OF 10 STA 0+00 930 920 0 a z z 910 z O a 900 w 890 920 920 0 a z w w 910 910 z_ z O a 900 900 w 890 890 STA 2+00 STA 4+00 930 920 910 900 890 -20 -10 0 10 20 30 40 50 60 70 80 90 100 -20 -10 0 10 20 OFFSET IN FEET (NO VERTICAL EXAGGERATION) OFFSET IN FEET (NO VERTICAL EXAGGERATION) STA 6+00 STA 8+00 930 co 920 0 a z w " 910 z_ z O a 900 w 890 MITIGATION APPROXIMATE DREDGE EXTENTS AREA 3 930 930 920 920 0 a z w 910 910 z_ z O a 900 900- MI APPROXIMATE IGATION DREDGE AREA EXTENTS 930 920 910 900 890 -20 -10 0 10 20 30 40 50 60 -20 -10 0 10 20 30 40 50 60 OFFSET IN FEET (NO VERTICAL EXAGGERATION) OFFSET IN FEET (NO VERTICAL EXAGGERATION) 930 STA 12+00 930 3 920 920 0 MITIGATION DREDGE AREA MITIGATION DREDGE AREA ¢ z APPROXIMATE EXTENTS APPROXIMATE EXTENTS FIT 910 = z 910 0 Z ' O - iu J1 ----- ---- _ 3 Q 900 - w 900 890 890 -70 -60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 - OFFSET IN FEET (NO VERTICAL EXAGGERATION) 930 co 920 910 z z O a 900 w 890 930 co 920 0 a z " 910 z z O H a 900 w 890 930 920 0 z w z 910 Z O a 930 920 910 900 89C -20 -10 0 10 20 30 40 50 60 70 80 OFFSET IN FEET (NO VERTICAL EXAGGERATION) 930 920 910 900 89C -20 -10 0 10 20 30 40 OFFSET IN FEET (NO VERTICAL EXAGGERATION) STA 14+00 w 900 900 Y O O w � Q 890 890 0 0 -20 -10 0 10 20 w zo OFFSET IN FEET (NO VERTICAL EXAGGERATION) o w z V J Q - LEGEND: z m EXISTING MUDLINE w� i DESIGN DREDGE ELEVATION 00 0o ___ ------- V ALLOWABLE OVERDEPTH s V ° o LL V DREDGED MATERIAL TO BE REMOVED z w _ z N �_ —..._...4..— LAKE ADGER FULL POOL ELEVATION 911.61' 0 J � LL� s ¢ z NOTE: ALL DESIGN SLOPES ARE 3H:1V UNLESS OTHERWISE NOTED. DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH REV DATE BY AP P D DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION ^� CAROLINA DRAWN BY: HOLMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING J /I, %ANCHOR , /' , KROW whae5 below. Call before you dig. CHECKED BY: REEMTS, M. APPROVED BY : DINICOLA, W. RESOURCES COMMISSION SCALE: AS NOTED DATE: JUNE2020 SECTIONS SHEET# 6 OF 10 �' ' � 'I _ °q �� °o .. � • • �+OUP • • � o �� �` .o �../ QO \ PROPOSED �; ` o Gj LEGEND: Q STAGING N AREA �.. — ^ . e' YYY �0 �p C \ '9 PROPOSED DREDGED MATERIAL Q� �♦�\r j 1 1t / \ A� PLACEMENT AREA DESIGNATION EXAMPLE HAYBALE LOCATION E� -�� .� .�"/ / • . \ , • • � • � • o � S EXAMPLE SILT FENCE LOCATION � 1' / /. d+� • \ � O —APPROXIMATE LIMITS OF a 0 \ DISTURBANCE - PLACEMENT AREA 14+00 907 Q ° �--�� PROJECT STATIONING Jt 1 \ J • :y'� 9�$ _ ' / / O Q k\� NAVIGATION CHANNEL DREDGE P ❑C1 O pg EXISTING CHANNEL ° \ AREA APPROXIMATE EXTENTS MARKER (TYPICAL) MITIGATION DREDGE AREA APPROXIMATE EXTENTS FLOATING DOCK f p Q _ .. _ APPROXIMATE LIMITS OF DISTURBANCE DREDGINGAREA Q , CULVERT -S— -S� o ° Oa 0 \ WETLAND DELINEATION — ---- — SHORELINE (NORMAL POOL ELEVATION 911.61') 5 NORTH 0 60 120 SCALE IN FEET �J o oe Q LAKEADGER \ o o Q T7"00 o (FULL POOL ELEVATION 911.61') ° D 4 LAK / °k`l`� VA \ p 4 a J r t':W NOTES: � / '�.: °Y o N o r � � o 0 1. PLACEM ENT AREAS ARE APPROXI MATE, i r �r Z1 O O ` d U ° ��� p o CONTRACTOR TO INSTALL SEDIMENT CONTROL FEATURES AS NEEDED TO CONTAIN SEDIMENT WITHIN TARGET AREAS TO THE ELEVATIONS G'ala • N Q SHOWN. �rjr ��Jrrr.=.F 5�1 -o, ° • APPROXIMATE AREA OF DISTURBANCE ° I, o o• 2. CONTRACTOR TO UTILIZE COMBINED HAYBALES, FOR MATERIAL PLACEMENT 17.3 ACRES SILT CURTAINS, OR OTHER CONTROL STRUCTURES I ° TO MANAGE SEDIMENTS WITHIN PLACEMENT AREA EXTENTS. 3. CONTRACTOR MAYADJUST ALIGNMENTS AS NEEDED TO BALANCE PLACEMENT OPERATIONS AND SEQUENCE THE WORK. ,C ' I I • Al o . e g / �, 4. CONTRACTOR SHALL NOT BLOCK FLOW FROM r / n �'1 O y ° CULVERT AND GREEN RIVER BRANCHES DURING ! MATERIAL PLACEMENT OPERATIONS. 0 .1.��i / 6. ONLY BIODREGRADABLE FEATURES MAYBE LEFT IN ° PLACE FOLLOWING MATERIAL PLACEMENT. ANY SILT CURTAINS, ANCHORS, METAL STAKING, OR 3 / O _ / o • L' . 10 \ ` OTHER INSTALLEDITEMS MUST OTHERWISE BE T � A�...� d is / . � ` �. .\ _,/..�' � � / o • Q, REMOVED. 3 � T r... O / ° j y \` '�:I O O • 0 o 6. CONTRACTOR MATERIAL TRANSPORT LINE SHOULD m :J / e e� / BE ROUTED THROUGH WORKAREAS IDENTIFIED p O �y� .9.�•::'� r . '�.. „�.t .( _ . AA.7 .. �.. / WHERE POSSIBLE. z a s r' 1 r `)'� .� SOURCES z o r' r jl - P /... j' ^ 0 � z0 ��� ` A '�.�'!' ° b °p� 1. AERIAL PHOTOGRAPH 02019 MICROSOFT z v e G.1 ` . `: r �e,'..� ' e / o CORPORATION 02019 DIGITALGLOBE OCNESS / 1 % / 70 (2019) DISTRIBUTION AIRBUS DS r Q• O ,,.. -o r. v. ,. P Z / /� / /... 2. TOPOGRAPHIC SURVEY BY HAYES JAMES DATED o WETLANDS EXTEND BEYOND �' )�' I / r / S �o Q e o o '� .' r''. .i I. (` /" ° 0Q �l` /' 4 OJ AUGUST 27, 2018. o LIMITS OF DISTURBANCE � 1'� \" '.l �`/ ���� r � ' � /' LL � i o �'. Pe Q ; "� •,� :r WETLANDS EXTEND BEYOND /: 1 0 / I / ; ., �," ; LIMITS OF DISTURBANCE ��/ -�' ' , / ' DRAFT -NOT FOR CONSTRUCTION ¢ z REVISIONS NORTH REV DATE BY AP DESCRIPTION DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION A CAROLINA DRAWN BY: HOMER, D. LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING 4 ANCHORr , Know Whans bP.IOW. CHECKED BY: REEMTS, M. �v/' Call before you dig. IDEA i �`/ RESOURCES APPROVED BE DIN (COLA, W. COMMISSION SCALE: JU NOTED DATE: ,uNEzozo DREDGED MATERIAL PLACEMENT LAYOUT SHEET# 7 of 10 CULVERT // / /-- �' --1 PROPOSEDI ' STAGING AREA ' 0� Q�e�OP�/i...... .� •per'' /�. � `^ 00, EXISTING CHANNEL \ \ \ \ / MARKER (TYPICAL) \ FLOATING DOCK ° \ \ S---S _.._.._ LAKE ADGER (FULL POOL ELEVATION 911.61') \ \ oo� 10,60 e-11+00 12+00 13+00 • �1 +00 15+00 APPROXIMATEAREA OF DISTURBANCE \ \ FOR MATERIAL PLACEMENT 17.3 ACRES N V R�� v MAXIMUM APPROXIMATE IMPACTED AREAS (ACRES) IMPACT TYPE AREA TYPE DESCRIPTION Al A2 31 C1 DREDGING PERMANENT DUE TO WETLAND AREA BETWEEN FULL POND AND DOWNGRADIENT 0.7 0.4 >0.1 N/A N/A PLACED MATERIALS WETLAND DELINEATION EXTENTS PERMANENT DUE TO OPEN WATER AREA BETWEEN WETLAND DELINEATION EXTENTS 0.7 1.1 0.4 0.8 N/A PLACED MATERIALS AND CELL BOUNDARY TEMPORARY BY WETLAND AREA BETWEEN FULL POND AND UPGRADIENT 1.3 1.7 N/A N/A N/A CONSTRUCTION ACTIVITIES LIMITS OF DISTURBANCE TEMPORARY BY AREA BETWEEN CELL BOUNDARY AND CONSTRUCTION ACTIVITIES OPEN WATER DOWNGRADIENT LIMITS OF DISTURBANCE 1.8 4.5 LEGEND: PROPOSED DREDGED MATERIAL Al PLACEMENT AREA DESIGNATION EXAMPLE HAYBALE LOCATION S EXAMPLE SILT FENCE LOCATION APPROXIMATE LIMITS OF DISTURBANCE PLACEMENTAREA 14+00 �— 4 PROJECT STATIONING NAVIGATION CHANNEL DREDGE AREA APPROXIMATE EXTENTS MITIGATION DREDGE AREA APPROXIMATE EXTENTS — • • — APPROXIMATE LIMITS OF DISTURBANCE — — — WETLAND DELINEATION 0 NORTH 0 80 160 SCALE IN FEET NOTES: 1. PLACEMENT AREAS ARE APPROXIMATE, CONTRACTOR TO INSTALL SEDIMENT CONTROL FEATURES AS NEEDED TO CONTAIN SEDIMENT WITHIN TARGET AREAS TO THE ELEVATIONS SHOWN. 2. CONTRACTOR TO UTILIZE COMBINED HAYBALES, SILT CURTAINS, OR OTHER CONTROL STRUCTURES TO MANAGE SEDIMENTS WITHIN PLACEMENT AREA EXTENTS. 3. CONTRACTOR MAY ADJUST ALIGNMENTS AS NEEDED TO BALANCE PLACEMENT OPERATIONS AND SEQUENCE THE WORK. 4. CONTRACTOR SHALL NOT BLOCK FLOW FROM CULVERT AND GREEN RIVER BRANCHES DURING MATERIAL PLACEMENT OPERATIONS. 5. ONLY BIODREGRADABLE FEATURES MAY BE LEFT IN PLACE FOLLOWING MATERIAL PLACEMENT. ANY SILT CURTAINS, ANCHORS, METAL STAKING, OR OTHER INSTALLED ITEMS MUST OTHERWISE BE REMOVED. wm 6. CONTRACTOR MATERIAL TRANSPORT LINE SHOULD o w BE ROUTED THROUGH WORKAREAS IDENTIFIED o a WHERE POSSIBLE. o 0 w¢ SOURCES: z z o Z O 1. AERIAL PHOTOGRAPH ©2019 MICROSOFT Q V w a z CORPORATION ©2019 DIGITALGLOBE ©CNESS (2019) DISTRIBUTION AIRBUS DS > z� oz 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES DATED o AUGUST 27, 2018. z o z V z z w N o LL s QV Z DRAFT -NOT FOR CONSTRUCTION ANCHOR �v IDEA i �`/ NORTH CAROLINA , /' RESOURCES COMMISSION , KROW Whans below. Call before you dig. JAPPROVED REVISIONS DESIGNED BY: CORK,R. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. BE: DIN (COLA, W. SCALE: AS NOTED DATE: JUNE 2020 NORTH CAROLINA WILDLIFE RESOURCES COMMISSION 7 C5 SHEET# 8 OF 10 REV DATE BY AP P D DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING IMPACTED AREAS ... .N . . . ... .\ . .N . .\ . .N . .\ . .N . . //,/,/,//Nm\, Nm\ / .'. '....'. ' °: .. ............ .. l'� : / 0: . 18" (TYP.) � � '� � '� 14141Te14141 le4 41e 414141 14141 I• •/; •/; i; 'i; i — 1414Qi414i414I414i4i4i4!4141I//'/ //'/'/ 18" (TYP.) ) — — — — — — — — — — 1. Nm\....`..1 . . . . . . . . .--------- /; 6" (APPROX) O TOP VIEW "2" STAKES, 2 PER BALE, DRIVEN COMPLETELY 2OUGH BOTTOM ROW OF BALES TOP OF PLACED SEDIMENT UP TO 2" BELOW HAYBALES 2"X2" STAKES 2 PER BALE, DRIVEN AT LEAST 1.5' OR THROUGH SEDIMENT NTO COMPETENT GROUND 7 16" (TYP.) I ANGLE FIRST STAKE TOWARD PREVIOUSLY LAID BALE FRONT VIEW 1 TYPICAL DOUBLE STACK HAYBALE DETAIL C05 NOT TO SCALE NOTES: 1. HAYBALES SHALL BE PLACED AS SHOWN ON DRAWING C4, AND IN A ROW WITH ENDS TIGHTLY ABUTTING THE ADJACENT HAYBALES. HAYBALES SHALL BE USED WITH SILT FENCES AS SHOWN IN HAYBALES AND SILT FENCE DETAIL UNLESS OTHERWISE INDICATED ON DRAWING C4. 2. EACH HAYBALE SHALL BE PLACED SO THE BINDINGS ARE HORIZONTAL. 3. HAYBALES SHALL BE SECURELY ANCHORED IN PLACE BY TWO STAKES DRIVEN THROUGH THE HAYBALE. THE FIRST STAKE IN EACH HAYBALE SHALL BE DRIVEN TOWARD THE PREVIOUSLY LAID HAYBALE AT AN ANGLE TO FORCE THE HAYBALES TOGETHER. STAKES SHALL BE DRIVEN FLUSH WITH THE HAYBALE. 4. INSPECTION SHALL BE DAILY AND REPAIR/REPLACEMENT SHALL BE MADE PROMPTLY AS NEEDED. 5. HAYBALES SHALL BE REMOVED AS DIRECTED BY THE ENGINEER. 6. KEY HAYBALES 6" INTO SOFT SEDIMENT. NORTH CAROLINA ANCHOR Know whaes below. //��, a..b..v f'15, call beforeyoudig. QE[A (�L/ RESOURCES SIDE VIEW / / ANCHORBUOY BUOY — NYLON ROPE CANCHOR DEVICE 1 REVISIONS IN �. W.".. / �II :1 O TOP VIEW FLOTATION DEVICE SILT CURTAIN CHAIN FRONT VIEW 18" (TYP.) FLOW 18" (TYP.) 6" (APPROX) C3, C YCK DHLC, UKIVCIN HI LCH31 I.D UK SEDIMENT INTO COMPETENT GROUND TOP OF PLACED SEDIMENT UP TO 2" BELOW HAYBALES 16" (TYP.) ------ T—j AIC 1 TYPICAL SINGLE STACK HAYBALE DETAIL C05 NOT TO SCALE SIDE VIEW 4LINE,, ILT CURTAIN TOP LOAD LINE TOP LOAD(OPTIONACONNECTOR (OPTIONAL) WATER LEVEL WATER LEVEL 7 FLOTATION DEVICE 1'-5' (TYP) BALLAST LINE (GALVANIZED CHAIN) BOTTOM SEDIMENT '.t.! .. .. .. SIDE VIEW CONNECTION GROMMETS V-5' (TYP) V-5' (TYP) BALLAST LINE (GALVANIZED CHAIN) BOTTOM SEDIMENT z TYPICAL SILT CURTAIN DETAIL C05 NOT TO SCALE DESCRIPTION DESIGNED BY: CORK, R. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE: AS NOTED DATE: JUNE 2020 SECTION VIEW DRAFT -NOT FOR CONSTRUCTION NORTH CAROLINA WILDLIFE RESOURCES COMMISSION C6 LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING 0]*rAIW-y SHEET# 9 OF 10 WETLAND PLANTING WETLAND PLANTING, SEE(D 'if 1�ff --------- - Iffififi DREDGE MATERIAL `SLOPE VARIES 1 TYPICAL EMERGENT WETLAND CONSTRUCTION CROSS SECTION NOT TO SCALE USE PILOT STAKE TO MAKE HOLE, AND PLANT PLUG DIRECTLY IN BACKFILL PLANT FLUSH z WETLAND PLANTING DETAIL NOT TO SCALE NORTH CAROLINA CH®R Know wnacsbelow. �, ®�' call beforeyoudig. QEA�v RESOURCES TABLE 1: EMERGENT VEGETATION SPECIES Common Name Scientific Name Broadleaf cattail Typha latifolia Common arrowhead Sagittarialatifolia Wool grass Scirpus cyperinus Soft stem bulrush Schoenoplectus tabernaemontani Fringed sedge Carexcrinita Pickerelweed Pontederia cordata Soft rush Juncus effusus Water Willow Justicia Americana NOTES: 1. ALL LISTED PLANTS ARE OBLIGATED WETLAND PLANTS 2. PLANTS SHALL BE 2-INCH PLUGS AND PLANTED AT A DENSITY OF 10,900 (2-FOOT SPACING) PER ACRE. 3. SIMILAR SPECIES CAN BE SUBSTITUTED BASED ON SITE CONDITIONS WITH APPROVAL OF THE CONSTRUCTION MANAGER. 4. A 1-YEAR WARRANTY SHALL APPLY TO ALL EMERGENT VEGETATION SPECIES. AT THE END OF 1-YEAR, ANY EMERGENT SPECIES THAT DOES NOT SURVIVE SHALL BE REPLACED BY THE CONTRACTOR WITH A SPECIES PERFORMING WELL AT THE SITE. TABLE 2: WETLAND SEED MIX Common Name Scientific Name Common Water Plantain Alismasubcordatum Swamp Milkweed Asclepias incarnata Common Hop Sedge Carexlupulina Lance -Fruited Oval Sedge Carexscoparia Brown Fox Sedge Carex vulpinoidea Turtlehead Chelone glabra Common Wood Reed Cinna arundinacea Flat -Top Aster Doellingeria umbellata Virginia Wild Rye Elymus virginicus Common Boneset Eupatorium perfoliatum Hollow Joe-Pye Weed Eutrochium fistulosum Sneezeweed Helenium autumnale False Sunflower Heliopsis helianthoides Common Rush Juncus effusus Great Blue Lobelia Lobelia siphilitica Monkey Flower Mimulus ringens Ditch Stonecrop Penthorum sedoides Dark Green Rush Scirpus atrovirens Wool Grass Scirpus cyperinus Side -Flowering Aster Symphyotrichum lateriflorum New England Aster Symphyotrichum novae-angliae Marsh Shield Fen Thelypteris palustris Blue Vervain Verbena hastata Boneset Eupatorium perfaliatum NOTE: A 1-YEAR WARRANTY SHALL APPLY TO ALL SEEDING AREAS. AT THE END OF 1-YEAR, ANY BARE AREAS GREATER THAN 5 SQUARE FEET SHALL BE RESEEDED BY THE CONTRACTOR WITH A SPECIES PERFORMING WELL AT THE SITE. REVISIONS TABLE 3: TREE AND SHRUB SPECIES Common Name Scientific Name Trees American elm Ulmus americana River birch Betula nigra Black willow Salixnigra Red maple Acer rubrum Box elder Acer negundo American sycamore Plantanus occidentalis Shrubs Spicebush Lindera benzoin Smooth alder Alnus serrulata Silky dogwood Comus amomun NOTES: 1. TREES SHALL BE 5-GALLON CONTAINER AND INSTALLED ON 25 FT CENTERS. 2. SHRUBS SHALL BE 1-GALLON CONTAINER AND INSTALLED ON 10 FT CENTERS. 3. A 1-YEAR WARRANTY SHALL APPLY TO ALL TREES AND SHRUBS. AT THE END OF 1 YEAR, ANY TREE OR SHRUB THAT DOES NOT SURVIVE SHALL BE REPLACED BY THE CONTRACTOR WITH A SPECIES PERFORMING WELL AT THE SITE. REFERENCE WETLAND DATA LOCATIONS MAINTENANCE DREDGING LOCATION NORTH 1 LAKE ADGER • RP-1 • RP-6 9RP-5 *RP-2 P-4 0 RP-3 0 500 1000 • R SCALE IN FEET SOURCE: AERIAL PHOTOGRAPH ©2020 MICROSOFT CORPORATION ©2020 DIGITALGLOBE ©CNESS (2020) DISTRIBUTION AIRBUS IDS LEGEND: ,RP-1 REFERENCE WETLAND DATA LOCATION AND DESIGNATION NOTE: VEGETATION SPECIES AND WETLAND SEED MIXES LISTED IN TABLES 1 AND 2 ARE GENERALLY BASED ON THE INFORMATION COLLECTED DURING THE REFERENCE WETLAND SURVEY COMPLETED BY CLEARWATER ENVIRONMENTAL CONSULTANTS, INC., ON AUGUST 21-22, 2018. DESCRIPTION DESIGNED BY: CORK, R. DRAWN BY: HOLMER, D. CHECKED BY: REEMTS, M. APPROVED BY: DINICOLA, W. SCALE: AS NOTED DATE: JUNE 2020 DRAFT -NOT FOR CONSTRUCTION NORTH CAROLINA WILDLIFE RESOURCES COMMISSION �� LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING VEGETATION PLANTING DETAILS I SHEET# 10 OF 10 Attachment E Package of Public Comments Received from USACE on September 14, 2020 Brown, David W CIV USARMY CESAW (USA) From: Pace Wilber - NOAA Federal <pace.wiiber@noaa.gov> Sent: Wednesday, July 8, 2020 8:49 AM To: Brown, David W CIV USARMY CESAW (USA) Cc: Fritz Rohde - NOAA Federal; Twyla Cheatwood - NOAA Federal Subject: [Non-DoD Source] NMFs no staff letter for NCWR Lake Adger SAW-2015-00788 Attachments: NCWRC-LakeAdger SAW-2015-00788_NoStaffingNoEFHPresent.pdf (UNITED STATES DEPARTMENT OF COMMERCE �+�"f °`Q•�4 National Oceanic and Atmospheric Administration k0 NATIONAL MARINE FISHERIES SERVICE Southeast Regional Office ` _ I ' 263 131h Avenue South •�*�°.� St. Petersburg, Florida 33701-5505 https://www.fisheries.noaa.gov/region/southeast (Sent via Electronic Mail) Colonel Robert J. Clark, Commander USACE Wilmington District 69 Darlington Avenue Wilmington, North Carolina 28403-1398 Dear Colonel Clark: July 8, 2020 NOAA's National Marine Fisheries Service (NMFS) reviewed the project described in the public notice listed below. Based on the information in the public notice, the proposed project would NOT occur in the vicinity of essential fish habitat (EFH) designated by the South Atlantic Fishery Management Council, Mid -Atlantic Fishery Management Council, or the NMFS. Present staffing levels preclude further analysis of the proposed work and no further action is planned. This position is neither supportive of nor in opposition to authorization of the proposed work. Notice No. Applicant(s) Notice Date SAW-2015-00788 NC Wildlife Resources July 7, 2020 Commission; Lake Adger Please note these comments do not satisfy consultation responsibilities under section 7 of the Endangered Species Act of 1973, as amended. If an activity "may effect" listed species or critical habitat under the purview of the NMFS, please initiate consultation with the Protected Resources Division at the letterhead address. /for Sincerely, Digitally signed by WILBER.THOMASY WILBER31-10MAS.PAYSON.136582 AYSON.1365820186 0186 Date: 2020.07.08 08:4S:S6 -000' Virginia M. Fay Assistant Regional Administrator Habitat Conservation Division Brown, David W CIV USARMY CESAW (USA) From: Homewood, Sue <sue.homewood@ncdenr.gov> Sent: Thursday, August 6, 2020 3:40 PM To: Brown, David W CIV USARMY CESAW (USA) Cc: Leslie, Andrea J; Hamstead, Byron A; Robert Cork, Yankura, Kaylie Subject: [Non-DoD Source] Lake Adger Maintenance Dredging Comments Attachments: 20200987 Ver 1-Comments to USACE_20200803.pdf Please see attached. Hard copies will not be sent unless specifically requested. Sue Homewood Division of Water Resources, Winston Salem Regional Office Department of Environmental Quality 336 776 9693 office 336 813 1863 mobile Sue.Homewood@ncdenr.gov 450 W. Hanes Mill Rd, Suite 300 Winston Salem NC 27105 )ocuSign Envelope ID: AD52759E-03A9-40A5-B5B0-4EBBC29A50E7 ROY COOPER Governor MICHAEL S. REGAN seartary S. DANIEL SMITH DUector NORTH CAROLINA Environmental Quality August 3, 2020 Corps Action ID# SAW-2015-00788 DWR# 20200987 Polk County Mr. David Brown U.S. Army Corps of Engineers Asheville Regulatory Field Office 151 Patton Ave, Room 208 Asheville, North Carolina 28801-5006 Subject Project: Lake Adger Channel Maintenance Dredging Dear Mr. Brown, On behalf of the NC Division of Water Resources, we respectfully request that you consider the following comments within your review of the 404 Individual Permit request for the above referenced property: The application notes that a wetland monitoring plan will be developed with input from the resource agencies. We request that a detailed and complete monitoring plan for wetland impact areas be finalized prior to issuance of approvals. 2. The Division acknowledges that the applicant's intent is to enhance and/or create wetlands as a result of this project, however the Division recommends that this should be monitored and that a detailed course of action should be developed should the project inadvertently cause a loss of wetlands. We recommend that the monitoring plan include a requirement for a new jurisdictional determination (in areas of dredge spoil fill) and that NCWAM evaluations be conducted to ensure that the wetlands to be filled by dredge material do not lose jurisdiction or incur a degradation of function. We recommend that any approvals include a condition that should either loss of jurisdiction or loss of function occur, the Permittee would be required to provide a mitigation plan to compensate for the loss. The creation of new wetland areas within the lake may be proposed as "permittee responsible mitigation" provided they satisfy mitigation site criteria at the time of proposal. North Carolina Department of Environmental Quality I Division of Water Resources 512 North Salisbury Street " 1617 Mail Service Center Raleigh, North Carolina 27699-1617 919.707.9000 locuSign Envelope ID: AD52759E-03A9110A5-B5B0-4EBOC29A50E7 Corps Action ID# SAW-2015-00788 DWR# 20200987 Page 2 of 2 3. The Division recommends that the applicant provide a detailed phasing and/or construction sequencing plan proposed for this project. For instance, will dredging activities be confined within certain portions of the lake until completion/before progressing to the next work area? How does the construction sequencing tie into the containment system design and turbidity monitoring proposals? 4. The Division recommends that a more detailed and robust turbidity monitoring plan is necessary and will coordinate with the applicant during 401 application review. The applicant mentions future routine dredging activities to be covered by this approval. The Division recommends that prior to commencement of any future dredging or disposal activities the areas to be used for disposal should be re-evaluated by the regulatory agencies and may require updated jurisdictional determinations and/or NCWAM evaluations, and that updated monitoring plans to be developed for each future area which is proposed to impact wetlands, and should be conditioned to require mitigation of any future loss of jurisdiction or function as noted above. Thank you for your considering the Division's comments during your review of this Individual Permit. Please note that the Division received the 401 application on July 31, 2020 and has not conducted a complete technical review at this time. Upon detailed review, additional information may be necessary prior to issuance of a 401 individual certification. if you have any questions, please contact Sue Homewood at 336-776-9693 or sue.homewood@ncdenr.gov. Sincerely, DoeuS9dned by: We 949D91 BA53EF4E0... Paul Wojoski, Supervisor 401 & Buffer Permitting Unit cc: Robert Cork, Anchor QEA of North Carolina LLC (via email) Andrea Leslie, NCWRC (via email) Byron Hamstead, USFWS (via email) DWR ARO DWR — Wetlands and Buffer Permitting Branch Brown, David W CIV USARMY CESAW (USA) From: DCR - Environmental -Review <Environmental.Review@ncdcr.gov> Sent: Monday, August 3, 2020 2:36 PM To: Wallace, Nancy L CIV USARMY CESAW (US); Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Re: [External] US Army Corps of Engineers Wilmington District Public Notice (UNCLASSIFIED) Attachments: GS 17-2950.pdf Our response is attached. Thank you. Devon L. Borgardt Environmental Review Assistant North Carolina Historic Preservation Office 109 E Jones St MSC 4619 Raleigh, NC 27699 919 814 6586 office Devon.boreardt(a,ncdcr.gov 0 #StayStrongNC Learn more @ nc.gov/covidl9 And don't forget your Ws! Wear. Wait. Wash. WEAR a face covering. WAIT 6 feet apart from other people. WASH your hands often. Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. Facebook Twitter Instagram YouTube From: Wallace, Nancy L CIV USARMY CESAW (US) <Nancy.Wallace@usace.army.mil> Sent: Monday, July 6, 2020 7:46 AM Subject: [External] US Army Corps of Engineers Wilmington District Public Notice (UNCLASSIFIED) CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov<mailto:report.spam@nc.gov> CLASSIFICATION: UNCLASSIFIED As you requested, you are hereby notified that Wilmington District, United States Army Corps of Engineers has issued a Public Notice. The text of this document can be found on the Public Notices portion of the Regulatory Division Home Page. Each Public Notice is available in ADOBE ACROBAT (.pdf) format for viewing, printing or download at Blockedhttps://urldefense.com/v3/ http://www.saw.usace.army.mil/Missions/Regulatory-Permit-Program/Public- Notices/;!IHYmSToo!PUn9iBNStoiRnYpXKOcZVRYC1SFpzYlaaDtnmuGwZEPIAcLgDz74UCvy0cQxNloUlBdugUoy3n8$ As with anything you download from the internet, be sure to check for viruses prior to opening. The current notice involves: Corps Action ID#: SAW-2015-00788 (Lake Adger Dredging) Issue Date: July 6, 2020 Applicant: Mr. Jeff Ferguson of the North Carolina Wildlife Resources Commission Expiration Date: 5:00 p.m., August 7, 2020 Point of Contact: Mr. David Brown, 828-271-7980 Ext 4232 Project Description: The Wilmington District, Corps of Engineers (Corps or USACE) received an application from Mr. Jeff Ferguson of the North Carolina Wildlife Resources Commission (NCWRC or WRC) seeking Department of the Army (DA) authorization for 7.5 acres (ac) of permanent impacts to open waters (dredging and conversion to wetlands); 9.5-ac of temporary impacts to open waters (dredging); 1.1-ac of permanent impacts to wetlands (fill); and 3.0-ac of temporary impacts to wetlands (dredging), associated with dredging of the recreational navigation channel between the Lake Adger public boat access area and the lake's main channel adjacent to the Lake Adger Marina in Mill Spring, Polk County, North Carolina. Subscribe/Unsubscribe: This email was sent out as a result of subscribing to the Wilmington District regulatory program public notices. Please reply to this email with the subject or message "unsubscribe" to remove your address from future mailings. CLASSIFICATION: UNCLASSIFIED North Carolina Department of Natural and Cultural Resources State Historic Preservation Office Ramona M. Banos, Administrator Governor Roy Cooper Secretary Susi H. Hamilton August 3, 2020 Mr. David Brown USACE Wilmington District Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, North Carolina, 28801 Re: Lake Adger Dredging Project, Polk County, ER GS 17-2950 Dear Mr. David Brown: Thank you for your email of July 6, 2020 concerning the above project. Office ofArchives and History Deputy Secretary Kevin Cherry david.w.brown@usace.army.mil We have conducted a review of the project and are aware of no historic resources which would be affected by the project. Therefore, we have no comment on the project as proposed. The above comments are made pursuant to Section 106 of the National Historic Preservation Act and the Advisory Council on Historic Preservation's Regulations for Compliance with Section 106 codified at 36 CFR Part 800. Thank you for your cooperation and consideration. If you have questions concerning the above comment, contact Renee Gledhill -Earley, environmental review coordinator, at 919-814-6579 or environmental.review@ncdcr.gov. In all future communication concerning this project, please cite the above referenced tracking number. Sincerely, 6'LR/amona Bartos, Deputy State Historic Preservation Officer Location: 109 East Jones Street, Raleigh NC 27601 Mailing Address: 4617Mail Service Center, Raleigh NC 17699-4617 Telephone/Pax (919) 807-6I70/807-6199 Brown, David W CIV USARMY CESAW (USA) From: Elizabeth Toombs <elizabeth-toombs@cherokee.org> Sent: Tuesday, August 4, 2020 2:14 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] SAW-2015-00788 Attachments: 080420 USACE COR SAW-2015-00788 Lake Adger.pdf Mr. Brown: Attached is Cherokee Nation's response to the proposed undertaking. Please let me know if there are any questions or concerns. Wado, Elizabeth Toombs, Tribal Historic Preservation Officer Cherokee Nation Tribal Historic Preservation Office PO Box 948 Tahlequah, OK 74465-0948 918.453.5389 Office of the Chief CWY.6 D$P Chuck Hoskin Jr. CHEROKEE NATION® PNrkipal Chief Bryan Warner P.O. Box 948 • Tahlequah, OK 74463-0948 Deputy Principal Chief 918-453-5(XX)• www.chemkcc.org August 4, 2020 David Brown United States Army Corps of Engineers Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, NC 28801-5006 Re: SAW-2015-00788, Proposed Dredging of Lake Adger Mr. David Brown: The Cherokee Nation (Nation) is in receipt of your correspondence about SAW-2015-00788, and appreciates the opportunity to provide comment upon this project. Please allow this letter to serve as the Nation's interest in acting as a consulting party to this proposed project. The Nation maintains databases and records of cultural, historic, and pre -historic resources in this area. Our Historic Preservation Office reviewed this project, cross referenced the project's legal description against our information, and found no instances where this project intersects or adjoins such resources. Thus, the Nation does not foresee this project imparting impacts to Cherokee cultural resources at this time. However, the Nation requests that the United States Army Corps of Engineers (USACE) halt all project activities immediately and re -contact our Offices for further consultation if items of cultural significance are discovered during the course of this project. Additionally, the Nation requests that USACE conduct appropriate inquiries with other pertinent Tribal and Historic Preservation Offices regarding historic and prehistoric resources not included in the Nation's databases or records. If you require additional information or have any questions, please contact me at your convenience. Thank you for your time and attention to this matter. Wado, Elizabeth Toombs, Tribal Historic Preservation Officer Cherokee Nation Tribal Historic Preservation Office elizabeth-tombs@cherokee.org 918.453.5389 Brown, David W CIV USARMY CESAW (USA) From: Leslie, Andrea J <andrea.leslie@ncwildlife.org> Sent: Thursday, August 13, 2020 2:56 PM To: Brown, David W CIV USARMY CESAW (USA) Cc: Homewood, Sue; Moore, Andrew W; Byron Hamstead (byron_hamstead@fws.gov); Robert Cork; Ferguson, Jeff C; Loftis, C. Scott Subject: [Non-DoD Source] Lake Adger Dredging project - NCWRC comments Attachments: LAdgerDredging_Polk_WRCComments.pdf Hi David, Attached are NCWRC's comments on the Lake Adger dredging project. Andrea Leslie Mountain Habitat Conservation Coordinator NC Wildlife Resources Commission 645 Fish Hatchery Rd., Building B Marion, NC 28752 828-803-6054 (office) 828-400-4223(cell) Blockedwww.ncwildlife.org Get NC Wildlife Update delivered to your inbox from the N.C. Wildlife Resources Commission. Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties. ® North Carolina Wildlife Resources Commission Cameron Ingram, Executive Director August 13, 2020 Mr. David Brown U.S. Army Corps of Engineers, Regulatory Branch 151 Patton Avenue, Room 208 Asheville, North Carolina 28801-5006 SUBJECT: Lake Adger Navigation Channel Maintenance Dredging Lake Adger Wetlands, Polk County SAW-2015-00788 Dear Mr. Brown: Biologists with the North Carolina Wildlife Resources Commission (NCWRC) reviewed the individual 404 permit application modification for the Lake Adger Navigation Channel Maintenance Dredging project, which would temporarily impact 3 acres and permanently impact 1.1 acres of wetland, as well as temporarily impact up to 14 acres and permanently impact 3 acres of open water, in Lake Adger in Polk County. NCWRC is the applicant for the permit, and staff are familiar with the site and have attended multiple site visits. Our comments on this application are offered for your consideration under provisions of the Clean Water Act of 1977 (33 U.S.C. 466 et. seq.) and Fish and Wildlife Coordination Act (48 Stat. 401, as amended: 16 U.S.C. 661-667d). Project activities should not impact wild trout reproduction, and a moratorium is not needed. The permit is associated with the dredging of a navigation channel from the boat dock to the lake. 6,800 yd3 of sediment would be hydraulically dredged in 2020-2021 from the navigation channel, 3,800 yd3 of which are required to make the channel navigable. An additional 3,000 yd3 of sediment will be dredged at the navigation channel location, and this additional amount is meant to compensate for sediment lost to the Big Hungry River during the removal of the lower Big Hungry River dam in 2015. The dredged sediment would be piped 1,500 ft to be placed in shallow in -lake placement areas Al and A2. The sediment would be allowed to drain in place and contoured to create new or enhance existing wetlands, as well as create upland habitat. The areas would be planted with native herbaceous and woody vegetation, using an adjacent wetland/upland complex as a reference for the plant list. Mailing Address: Habitat Conservation • 1721 Mail Service Center • Raleigh, NC 27699-1721 Telephone: (919) 707-0220 • Fax: (919) 707-0028 Lake Adger Dredging Page 2 August 13, 2020 L Adger & wetlands, Polk Co Total disturbance for the project would be 22.3 acres, including 4.5 acres for the navigation channel and 3.9 acres for sediment placement. The individual permit describes four areas for sediment placement (A1, A2, B1, and C1, totaling 3.9 acres) that would allow for sediment placement for the 6,800 yd3 and for future dredging activities. 1.1 acres of this sediment placement area is jurisdictional wetland. The sediment placement areas would be surrounded by two rows of biodegradable and/or temporary containment materials (e.g., hay bales) as well as a silt curtain beyond these rows; these measures are meant to hold sediment in place (especially the first row of material) and control turbidity. Turbidity would be monitored upstream and downstream of the activities, with turbidity sampled once each day at the upstream reference and twice each day downstream for the first week, with the goal of not increasing turbidity by more than 50 NTU from the upstream location. If the turbidity goal is met during the first week, monitoring frequency would be cut back to once per day. The application states that a review and possible change in activity will be taken only if turbidity is 100 NTU or more above the upstream reference. It is unknown if any action would be taken if turbidity increases 50-100 NTU from the reference. We offer the following comments and recommendations on this project: • The turbidity monitoring and contingency plan should be revised with the input of NC Division of Water Resources (NCDWR). • The vegetation monitoring plan should be developed with the input of NCDWR, US Army Corps of Engineers, and NCWRC. • We recommend adding Needle Spikerush and Silky Willow to the wetland plant list and Persimmon and Black Gum to the upland plant list. • Herbivory control fencing should consist of fabric that will not trap animals. NCWRC biologists can provide recommendations at to the type of fencing that is appropriate. • Although the text notes that 3.9 acres of area will be used for sediment placement, Sheet C5 notes that 1.1 acres of wetland and 3.0 acres of open water will be impacted by fill, which totals 4.1 acres. These differences should be rectified. Thank you for the opportunity to review and comment on this project. Please contact me at (828) 400-4223 if you have any questions about these comments. Sincerely, /Andrea Leslie Mountain Region Coordinator, Habitat Conservation Program ec: Robert Cork, Anchor QEA Kaylie Yankura & Sue Homewood, NC Division of Water Resources Byron Hamstead, US Fish and Wildlife Service Jeff Ferguson & Scott Loftis, NCWRC Brown, David W CIV USARMY CESAW (USA) From: laura.e.baird@everyactioncustom.com on behalf of Laura Baird <laura.e.baird@everyactioncustom.com> Sent: Friday, August 21, 2020 9:57 AM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & More Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, Laura Baird 92 Mill Shoals Rd Mill Spring, NC 28756-4767 laura.e.baird@gmail.com Me n.t kc:k— MAL�vr' T 6 co \N, I-q v-e INI,1 1 >Qe : 56vJ! a015-O u nd �_ 1kkf_,..s�.w, Sr % ee- yy r #':'FU'F2VE�RWj/ USA L�t,Vf '0( a of a '6- %o l - 500 � : fill 1111i111I)A j'Ij111'.f')JI:&II1';1!'11jbIlIli llnliil r Monika Mayr 78 Cove Lane Mill Spring, NC 28756 Tr !77 � r s Mr. David Brown AUK 1 a USACE Wilmington District Asheville Regulatory Field Office BY:. .. 151 Patton Ave, Room 208 Asheville, NC 28801-5006 Re: Public Comment Concerning Lake Adger Marina Dredging Project, ID # SAW-2015-00788 Dear Mr. Brown: Thank you for the opportunity to comment on this important project that improves public access to Lake Adger. I appreciate the effort to gather and consider comments of interested parties, especially those that live on Lake Adger like I do. I agree with many of the comments presented by MountainTrue and am including them below with my additional comments. Stakeholder Consultation - NCWRC should convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive project details and provide pertinent feedback and input including project timing, potential impacts to water quality and lake habitat, lake level fluctuations, and other concerns of public interest. Sediment Management — I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area and reducing the impact trigger from 100 NTU's to 75 NTU's. Additionally, if the trigger is activated, project specifications should clearly call for ceasing all operations until corrective actions are enacted and the turbidity levels return to 50 NTU's or below. Corrective operations must be initiated and not simply reviewed or monitored more frequently. Wetland Construction - I support methods to contain and dewater material used to construct wetlands that do not introduce living non-native material or non -biodegradable material. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the least environmentally damaging technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how impacts can be mitigated. Wetland Planting - Water Willow must be removed from the wetland planting list. It is a nuisance plant that cannot be planted in a way that prevents its migration. Only material native to Lake Adger or the nearby area should be used in this project. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels and do not lower lake levels when fish are spawning on their beds. Expanded Public Access Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public, especially Lake Adger residents, as plans are finalized. Again, thank you for the opportunity to comment on this important project. Sincerely, Monika Mayr Lake Adger Resident FA S ; `t VP•�iyvF�' FOREVER AJu 0 � ve r e y BY: � �Jqeor r 2SE,W6I E.:Fj }.; P-; 4YA C, yke. �u�.,�awz- �' 1fw� yz4,,00j-,,Li. �s o/L,,,� t-& c �. - 11-7 ,a, v�,Cz Brown. David W CIV USARMY CESAW (USA) From: Gray Jernigan <gray@mountaintrue.org> Sent: Thursday, August 6, 2020 3:18 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] SAW-2015-00788 - Lake Adger Dredging Public Comment Attachments: USACE Lake Adger Dredging Comments.pdf Mr. Brown, Please find the attached comments submitted on behalf of MountainTrue in regard to the permit application to dredge the public access channel at Lake Adger. We're glad to see this project moving forward, and thank you and your staff for all you do to serve the citizens of WNC. Sincerely, Gray Jernigan Southern Regional Director & Green Riverkeeper MountainTrue 121 Third Avenue West, Suite 1 Hendersonville, NC 28792 (828) 692-0385 ext.1004 Blockedwww.mountaintrue.orp Follow us on Facebook & Twitter Waterkeeper Alliance Member MountainTrue is committed to keeping our mountain region a beautiful place to live, work and play. Our members protect our forests, clean up our rivers, plan vibrant and livable communities, and advocate for a sound and sustainable future for all residents of WNC. BUILD A BETTER TOMORROW FOR WESTERN NORTH CAROLINA. BE MOUNTAINTRUE. JOIN TODAY: mountaintrue.org/loin ��� ►iT All mountaintrue. Protecting the Places We Share. August 6, 2020 Mr. David Brown USACE Wilmington District Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, North Carolina, 28801-5006 RE: SAW-2015-00788 - Lake Adger Dredging Public Comment Dear Mr. Brown, We are pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement and to use the dredge spoils to construct engineered wetlands on the existing sediment delta that has formed over the years since the Green River was dammed in 1925 creating the lake. We support this important project to protect public access to Lake Adger since the channel has become nearly impassible to boat traffic due to sedimentation. We have some suggestions to make this project as successful as possible and to protect water quality during and after the project: • Stakeholder Consultation - We request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project including timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. • Sediment Management - We appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. We suggest adding silt curtains around the dredging area, not just around the wetland construction area. • Wetland Construction - We support the most protective and strongest methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how impacts can be mitigated. 121 Third Avenue West, Suite 1, Hendersonville, NC 28792 • Wetland Planting - We would request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. • Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. • Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. • Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments and for the US Army Corps of Engineers oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, � � 0 0 Gray Jernigan Southern Regional Director & Green Riverkeeper Wallace, Nancy L CIV USARMY CESAW (US) From: Wallace, Nancy L CIV USARMY CESAW (US) Sent: Tuesday, August 4, 2020 1:58 PM To: 'ronpeters@skyrunner.net' Cc: Brown, David W CIV USARMY CESAW (USA) Subject: SAW-2015-00788 (Lake Adger) On August 3, 2020 we received your public notice comments for file number SAW-2015-00788 and forwarded it to David Brown for further processing. Sincerely, Nancy Wallace USACE Wilmington District Asheville Regulatory Field Office 151 Patton Avenue RM 208 Asheville, NC 28801 828-271-7980 Ext 4221 nancy.wallace@usace.army.mil July 27, 2020 ,< to Mr. David Brown United States Army Corps of Engineers (USAGE) Wilmington District Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, NC 28801-5006 Re: Corps Action ID Number: SAW-2015-00788 Dear Mr. Broom, We understand the North Carolina Wildlife Resources Commission (NCWRC) is seeking Department of the Army authorization for 7.5 acres of permanent impacts to open waters (dredging and conversion to wetlands); 9.5 acres of temporary impacts to open waters (access and erosion control); 1.1 acres of permanent impacts to wetlands (fill); and 3.0 acres of temporary impacts to wetlands (access and erosion control), associated with dredging of the recreational navigation channel between the Lake Adger public boat access area and the lake's main channel adjacent to the Lake Adger Main Marina in Mill Spring, Polk County, North Carolina. The Lake Adger Property Owners Association, Inc. Board of Directors (LAPOABOD) recommends that USACE issue an authorization for the proposed work pursuant applicable procedures of Section 404 of the Clean Water Act. The LAPOABOD also reserves the right to comment on more detailed design specifications pertinent to the proposed dredging once they are developed by NCWRC or their contractor(s). Specific to the information provided, the LAPOABOD does offer the following comments: 1. Silt curtains should be installed around any area where active hydraulic dredging is occurring to reduce the potential for downstream resuspension of sediment. According to the plan, turbidity monitoring is only occurring twice daily and if an exceedance above 100 NTUs occurs, the plan does not call for dredging to stop until further control measures are put in place. 2. Downstream turbidity testing should continue at an interval of twice daily for the entire length of the project; not just the first week as conditions can change due to weather related events. Ronald R. Peters, Presiderrt, Board of Directors, Lake Adger Property owners Association, Inc. 839 Parkway North Road • 1411 Spdng, NC 28756 • (828) 6254M • nef Labe .%4er 2'royerty owners Association, Inc. Pqp12 3. The NCWRC should detail the anticipated timeframe the Lake Adger Main Marina and the recreational navigation channel may be off limits to the public. 4. We request that NCWRC consult with the LAPOABOD prior to the selection of the final plantings contained on page 14 of the plan to make certain any native species selected do not become invasive. If you have any questions regarding our comments, please do not hesitate to contact us. Thank you for considering our input. On behalf of the Lake Adger Property Owners Association, Inc., Ronald R. Peters President, Board of Directors Lake Adger Property Owners Association, Inc. RRP:smp cc: Mrs. Brittany Foulds, CMCA, Community Association Manager, IPM Corporation, P.O. Box 580, Arden, NC 28704 Ronald R. Peters, President, Board of Dlrectore, Lake Adger property Omwre Assodatlon, Inc. 839 Parkvny North Road a keli Spring, NC M56 0 (828) 6254M 0 kwu nn -1w Wallace, Nancy L CIV USARMY CESAW (US) From: Wallace, Nancy L CIV USARMY CESAW (US) Sent: Tuesday, August 4, 2020 1:55 PM To: itlecourt@hotmail.com Subject: SAW-2015-00788 (Lake Adger) On August 3, 2020 we received your public notice comments for file number SAW-2015-00788 and forwarded it to David Brown for further processing. Sincerely, Nancy Wallace USACE Wilmington District Asheville Regulatory Field Office 151 Patton Avenue RM 208 Asheville, NC 28801 828-271-7980 Ext 4221 nancy.wallace@usace.army.mil July 29, 2020 U 3 Mr. David Brown BY: United States Army Corps of Engineers (USACE) Wilmington District ----.. Asheville Regulatory Field Office 151 Patton Avenue, Rm. 208 Asheville, NC 28801-5006 Dear Mr. Brown, This is in response to the Public Comment requests being sought for SAW-2015-00788, concerning the application for Lake Adger Dredging Plans as submitted by North Carolina Wildlife Resources Commission (NCWRC). While we support the dredging of Lake Adger, these are our comments and concerns regarding this plan: 1. Concerning Cells B1 and C1— Protection of Culvert Between These Cells a. Placement and breakdown of these cell materials could over time clog or close off the drainage culvert running under Silver Creek Road. b. Clogging of this drainage culvert could directly create flooding of Polk County Tax Parcels #1— P54-199, #2 — P54-356, #3 — P54-132, and #4 — P54-133 as identified on impacted Parcels presentation enclosed. c. Clogging of this drainage culvert could also result in flooding of Silver Creek Road at that point during heavy rain events that happen often. d. We request that this plan address this potential issue. 2. Concerning Cell Al — Approximate Area of Disturbance a. According to Plan C5, it appears that the upstream flow from the Green River will be negatively impeded from flowing into the Lake Adger. b. Water must not be -impeded from entering Lake Adger during this project which would negatively endanger wildlife and water quality. 3. Concerning Cell B1— Choking off Permanent Green River flow into Lake Adger a. There would appear to be some danger that Cell B1 will eventually close off the branch of flow nearest Silver Creek Road leaving only one feed into the lake. b. Concerns this reduction of flow will result in less turnover replacement of water in the lake resulting in stagnation, reduced lake levels, and degradation to the quality of the water. 4. Redirecting All Sediment Away from the Marina a. This plan appears to recommend redirecting all sediment to travel into the deeper middle channel of the lake. b. If allowed to occur, the sediment from upstream will then build up significantly in a new place. NCWRC is not under contract to have to dredge that portion of the lake. This would inevitably leave Polk County with the responsibility and expense of dredging. c. We request that Polk County Commissioners and citizens be made aware of this future impact before approval of application. S. Wetland Plantings a. We would request that Water Willow be removed from the wetland planting list. b. Polk County Commissioners are waiting on recommendation from Lake Adger POA citizens - On December 2, 2019, NCWRC requested Polk County Commissioners to allow planting of Water Willow into Lake Adger as a Test Site. The Commissioners deferred until Lake Adger Property Owners Board and its citizens can make a recommendation to the Commissioners. Due to COVID-19; efforts to inform citizens, investigate further, and make such recommendation to Commissioners has stalled. c. Willow Weed should not be introduced as part of this project. It is not native to Lake Adger. d. We request that this application not approve specific plant species. NCWRC should be required to consult stakeholders on final plantings. 6. Materials Used for Sediment Containment - Project Plan Description Page 4 a. On March 18, 2018, an original dredging plan was presented to Polk County Commissioners by NCWRC with approval by Polk County to proceed for permitting. b. On April 1,2019, NCWRC again appeared before the Polk County Commissioners to explain why the permitting submitted to the USACE one year earlier was not the correct permitting and new permitting application would have to be made. SAW-2015-00788 is the result. c. We request the original materials approved by the Commissioners for sediment containment be used as opposed to hay bales in the plan. Refer to Option 2 — in Water Replacement - Berm Construction Alternatives — Pg. 10 of March 18, 2018, NCWRC presentation enclosed. This would also somewhat address Concern #1 in this letter. 7. Public Meeting a. We request that a public meeting be held before application approval. b. Citizens were denied ability to ask questions of NCWRC following the March 18, 2019, presentation to Polk County Commissioners. c. Citizens were promised by then Commission Chair Melton an opportunity to question NCWRC once a new plan application was submitted. d. As USACE does not individually respond to concerns and comments sent to them as part of public comment, citizens were not previously allowed to ask questions, and a promise was made to the citizens that questions would be allowed once the plan was developed for USACE application submission; we believe a public meeting would benefit this project. Sincerely, djtt� 4(4fA4& I Irene and David LeCourt, 85 North Mountain Lane, Mill Spring, NC 28756 678-778-8065 — Mobile itlecourt@hotmaii.com mpacted Parcels �-R p IL -A4 .71 ,t . J .1, "', If Option 2 — In -water Placement • Wetland will be designed to • Ensure stability of placed material • Maintain hydraulic connection to the lake • Use cells for future channel maintenance dredging • Berm construction alternatives 1. Construct using rock 2. Construct using wood crib techniques 3. Construct using geotextile or HDPE liner 4. A combination of alternatives 1 through 3 • Design and construction considerations • Source of construction materials • On -shore staging during construction • Establishment of vegetation • Options for lake draw -down to aid construction NORTH CAROLINA RESOURCES COMMI551I1i. W Brown, David W CIV USARMY CESAW (USA) From: Jamie Davidson <jej56789@gmail.com> Sent: Monday, August 3, 2020 12:25 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Corps Action ID Number: SAW-2015-00788 - Lake Adger Dredging - COMMENTS ATTACHED Attachments: Davidson Comments Lake Adger Dredging -Mountain True.docx Attached are my comments regarding the Lake Adger Dredging Plan. Thank you, Jamie Davidson Mr. David Brown USACE Wilmington District Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, North Carolina, 28801-5006 RE: Corps Action ID Number: SAW-2015-00788 Mr. Brown: I am commenting on the proposed plan to dredge the Lake Adger Marina. I am a full time resident of Lake Adger, owning lake front property since 2002. As a volunteer with Mountain True's Clean Water Team for 10 years and a past chair of the Lake Adger Lake Advisory Committee, I am, and have been for a long time, an advocate for clean water in Lake Adger. I agree with Mountain True's comments listed below but would like to add a few personal comments. Due to the fact that many Lake Adger residents did not directly receive notification of this plan nor the public comment until it was brought to our attention weeks after the announcement, I would like to stress the point that the Lake Adger residents should be kept informed of this plan, especially prior to the start of actual work being performed. Communication with the Lake Adger POA is essential. The section of the plan that I am most concerned with is the planting of Justicia Americana (water willow). In my research I have learned that this is considered a nuisance plant in some lakes and it is not native to Polk County. I do not want to see water willow, nor any other plantings that are not native to Polk County, planted in the waters of Lake Adger. Sediment Management, wetland construction methods, and habitat considerations are also of importance as detailed by Mountain True. I would like to add that I would hope that during this process, NCWRC would considered adding more recreational access for the public in the project area such as boardwalks, fishing piers, etc.. This would provide more citizen access and opportunities for educational programs for citizens to learn about the importance of wetlands. I think the plan developed by NCWRC for dredging is much needed and I hope all citizen comments will be taken into consideration. Below are the Mountain True comments in which I am in full agreement: MountainTrue has advocated for and supports this important project to protect public access to Lake Adger, since the public access channel has become nearly impassible to boat traffic due to the accumulating sediment delta. However, we have some suggestions to make this project as successful as possible and to ensure that water quality is protected during and after the project. Stakeholder Consultation — We request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management — We appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. We suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction — We support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how impacts can be mitigated. Wetland Planting — We request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations — Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access Opportunities — NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication — NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Essommoommommummmmmmmommonamommmmmmummommmmmomommmmmussummummummmmmummmmommmomg Sincerely, Jamie Davidson Jej56789@gmail.com Brown, David W CIV USARMY CESAW (USA) From: Jamie Davidson <jej56789@gmail.com> Sent: Monday, August 3, 2020 11:31 AM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Follow up request Mr. Brown: Do you have a copy of the Lake Adger wetland survey that I requested in my email below. Or, do you know how I can obtain a copy of this survey? Thank you, Jamie On Mon, Jul 27, 2020 at 11:03 AM Jamie Davidson <iei56789@gmail.com> wrote: Mr. Brown: We met Nov 18, 2018, when Gray Jernigan and I came to your office for a meeting regarding Lake Adger dredging. I have read the Lake Adger dredging plan and will comment on that in a separate email. I would like to request a copy of the Lake Adger wetland survey that is mentioned on Sheet io of io on the Plan below the plant listings. I have tried contacting Clearwater Environmental Consultants with no success or response. Below is information that was taken from the Plan (Sheet io of 1o) in regards to the Wetland Survey: NOTE: VEGETATION SPECIES AND WETLAND SEED MIXES LISTED IN TABLES 1 AND 2 ARE GENERALLY BASED ON THE INFORMATION COLLECTED DURING THE REFERENCE WETLAND SURVEY COMPLETED BY CLEARWATER ENVIRONMENTAL CONSULTANTS, INC., ON AUGUST 21-22, 2018. • Thank you in advance, Jamie Davidson Note new email address: iei56789@�mail.com Please change in your Contacts list. Jamie Davidson Brown, David W CIV USARMY CESAW (USA) From: schuylerconard@everyactioncustom.com on behalf of Sky Conard <schuylerconard@everyactioncustom.com> Sent: Sunday, August 2, 2020 6:08 AM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Sky Conrad - PN Comments Lake Adger Dredging Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, Sky Conard 49 Indian Summer Ln Mill Spring, NC 28756-4790 schuylerconard@gmail.com Brown, David W CIV USARMY CESAW (USA) From: dlconard@everyactioncustom.com on behalf of David Conard <dlconard@everyactioncustom.com> Sent: Sunday, August 2, 2020 5:36 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & More Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. This project has been long delayed and action is needed to protect this resource which the public has utilized intensively during the Covid times. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, David Conard 49 Indian Summer Ln Mill Spring, NC 28756-4790 dlconard@yahoo.com Brown, David W CIV USARMY CESAW (USA) From: khummel@everyactioncustom.com on behalf of Kevin Hummel <khummel@everyactioncustom.com> Sent: Saturday, August 1, 2020 11:20 AM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Kevin Hummel PC Comments Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & More Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public: access to Lake Adger. Sincerely, Kevin Hummel SECTION D LAKE ADGER Pkwy Lot 27 Mill Spring, NC 28756 khummel@bellsouth.net Brown, David W CIV USARMY CESAW (USA) From: marks74@everyactioncustom.com on behalf of Mark Smith <marks74 @everyactioncustom.com> Sent: Wednesday, July 29, 2020 9:01 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Mark Smith PN Comments Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & More Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, Mark Smith 509 Silver Creek Rd Mill Spring, NC 28756-7626 marks74@windstream.net Brown, David W CIV USARMY CESAW (USA) From: lydia.wilson@everyactioncustom.com on behalf of Lydia Wilson <lydia.wilson@everyactioncustom.com> Sent: Wednesday, July 29, 2020 2:31 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Lydia Wilson PN Comments Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & More Dear Reg. Specialist David Brown, Hi! I use Lake Adger for relaxation and paddleboarding almost weekly. Thank you to the NC Wildlife Resources Commission (NCWRC) for submitting a permit application to dredge the public access channel at Lake Adger, even if is an obligation. The lake channels toward the Green River are getting hard to navigate due to the sediment. Would someone also look into the odd metal poles that stick up in the water on the river side? When levels are low, they seem dangerous. I support MountainTrue's below suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, Lydia Wilson 222 Winners Cir Tryon, NC 28782-3762 lydia.wilson@gmail.com Brown, David W CIV USARMY CESAW (USA) From: jambey7@everyactioncustom.com on behalf of James Beyer <jambey7 @everyactioncustom.com> Sent: Wednesday, July 29, 2020 2:06 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] James Beyer PN Comments Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & More Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, James Beyer Saluda, NC 28773 jambey7@yahoo.com Brown, David W CIV USARMY CESAW (USA) From: brucewhelchel@everyactioncustom.com on behalf of Bruce Whelchel <brucewhelchel@everyactioncustom.com> Sent: Wednesday, July 29, 2020 3:31 PM To: Brown, David W CIV USARMY CESAW (USA) Subject: [Non-DoD Source] Bruce Whelchel PN Comments Lake Adger Dredging Project: Request for Water Quality Protections, Better Public Access & Moreiiyiyiy Dear Reg. Specialist David Brown, I am pleased to see that NC Wildlife Resources Commission (NCWRC) has submitted a permit application to dredge the public access channel at Lake Adger as it is obligated to do under the lake management agreement, and to use the dredge spoils to construct engineered wetlands on the existing sediment delta. I support this important project to protect public access to Lake Adger, since the channel has become nearly impassible to boat traffic due to sedimentation. I have some suggestions to make this project as successful as possible and to protect water quality during and after the project: Stakeholder Consultation - I request that NCWRC convene a stakeholder group consisting of parties to the lake management agreement (Polk County, Lake Adger Property Owners Association, Northbrook Energy), MountainTrue's Green Riverkeeper, and other interested parties like members of the fishing and boating community to receive feedback and input on the details of the project. These project details would include timing, potential impacts to access and water quality, lake level fluctuations, and other concerns of public interest. Sediment Management - I appreciate the detailed turbidity monitoring protocols and support all efforts to control sediment impacts during and after the project. I suggest adding silt curtains around the dredging area, not just around the wetland construction area. Wetland Construction - I support the strongest and most protective methods to contain and dewater material used to construct wetlands. While hay bales may be cost effective to contain spoil material to form engineered wetlands, options like coir fiber biologs, geotubes, and others should be explored to ensure that the best available technology is incorporated into the project. NCWRC should specifically consider how high water events may impact constructed wetlands and how these impacts can be mitigated. Wetland Planting - I request that Water Willow be removed from the wetland planting list. NCWRC is currently studying whether Water Willow is appropriate for introduction to Lake Adger, as it does not currently grow there. Following the precautionary principle, this plant should not be introduced as part of this project. Rather, NCWRC should continue its study and consult stakeholders on the potential future introduction of Water Willow. Habitat Considerations - Be mindful of aquatic and wetland wildlife habitat, especially fish spawning beds that can be affected by fluctuations in lake levels. Expanded Public Access and Educational Opportunities - NCWRC should consider opportunities to expand and improve public access and education in the project area, such as boardwalks, docks, fishing piers, and educational signage explaining the history of the lake and the ecological significance of the Green River and surrounding area. Public Communication - NCWRC should clearly communicate project details and timelines with the public as plans are finalized. Thank you for your consideration of these comments, and for the US Army Corps of Engineers' oversight and guidance of this important project to protect public access to Lake Adger. Sincerely, Bruce Whelchel Columbus, NC 28722 brucewheichel@att.net Attachment F Lake Adger Navigation Channel Maintenance Dredging Project Turbidity Monitoring Plan Anchor QEA of North Carolina, PLLC ANCHOR 231 Haywood Street�z Asheville, North Carolina 28801 QEA �i 828.281.3350 TURBIDITY MONITORING PLAN January 12, 2021 Lake Adger Navigation Channel Maintenance Dredging Project Anchor QEA of North Carolina, PLLC, in Consultation with North Carolina Wildlife Resources Commission, and North Carolina Department of Environmental Quality Division of Water Resources A plan for maintenance dredging of the public boat ramp and marina navigation channel has been developed by engineering consultant Anchor QEA of North Carolina, PLLC in consultation with North Carolina Wildlife Resources Commission (NCWRC), and North Carolina Department of Environmental Quality (NCDEQ) Division of Water Resources (DWR). It is proposed to remove 6,800 cubic yards of soft sediment from the navigation channel and place the soft sediment within the Lake Adger footprint as beneficial use for habitat creation. Turbidity will be monitored by the contractor during project dredging and sediment placement activities. Turbidity will be monitored using hand-held or automated turbidity meters to record Nephelometric Turbidity Units (NTU) at a fixed upstream location (near the sediment placement area but upstream of the influence of project activities) and a fixed downstream location that allows for some in -lake mixing; approximate monitoring locations are shown on sheet C5 of the 90% Design Set (attached) submitted with the Response to USACE Comments and Provision of Additional Information'. During the first week of operations, data will be collected daily at the upstream background location, and twice daily (once 2 to 3 hours after daily operations have started, and again during the last 1 to 2 hours of daily operations) at the downstream monitoring location. If turbidity levels of >50 NTU are not measured at the downstream monitoring location during the first week, then monitoring will be reduced to once daily, taken during the last 1 to 2 hours of in -lake work for the remainder of the maintenance dredging project or until excessive turbidity is measured. Turbidity will be recorded and a turbidity log of all turbidity measurements will be sent to NCWRC and NC Division of Water Resources (NCWWR) at the end of each work week. The North Carolina turbidity standard is 25 NTU; attempts to keep turbidity at or below this level will be made. An operations protocol that describes corrective actions and reporting requirements for various turbidity scenarios is outlined in Table 1. Corrective actions include adjustments to operations and best management practices (BMPs), examples of which are as follows: • Performing dredging operations within a turbidity curtain system • Adjusting the rate of the work to reduce suspended sediment 1 Anchor QEA, 2021. Letter to: David Brown, USACE. Regarding: Response to USACE Comments and Provision of Additional Information. Lake Adger Navigation Channel Maintenance Dredging Project. January 15, 2021. • Optimizing the number of dredge bites that will achieve target dredge depth to increase sediment capture • Controlling the rate of dredging, including the rate of raising and lowering of the mechanical dredge through the water, particularly when the dredge is close to the bottom of the river • Not performing excessive and rapid movement of the dredge, such as dragging the dredge on the bottom or reopening the bucket after initial closure • Conducting pre -dredging removal of debris that could interfere with dredging • Removing debris from the riverbed in a slow and steady manner • Minimizing over -penetration of the dredge bucket to prevent overfilling • Completely closing (to the extent possible) the dredge bucket before it is lifted through the water column • Moving dredge continuously and in the most efficient path to the barge once the dredge breaks the water surface • Conducting vessel operations in a manner that minimizes potential resuspension due to vessel propeller wash (propwash) Table 1 Turbidity Monitoring and Corrective Action Protocols for Lake Adger Dredging and Sediment Placement Turbidity Levels Corrective Action Reporting Background Downstream <25 NTU <25 NTU None Weekly <25 NTU 26-50 NTU Evaluate, adjust BMPs to lower Weekly turbidity levels below 25 NTU. Evaluate, adjust BMPs. If turbidity Report to NCDWR within 24 hours <25 NTU >50 NTU doesn't drop to :550 NTU within of turbidity measurement 24 hours, stop work <25 NTU above Evaluate, adjust BMPs to lower >25 NTU background level turbidity levels to background levels Weekly or below Evaluate, adjust BMPs. If turbidity >25 NTU >25 NTU above doesn't drop to :525 NTU above Report to NCDWR within 24 hours background level background level within 24 hours, of turbidity measurement stop work Attachment Sheet C5 of 90% Design Set —Turbidity Monitoring Locations LEGEND: EXAMPLE COIR LOG OR HAYBALE LOCATION 8 EXAMPLE SILT CURTAIN OR SILT FENCE n LOCATION 14�� PROJECT STATIONING NAVIGATION CHANNEL DREDGE AREA OQO APPROXIMATE EXTENTS \ �..� O�<cQ' \ ' / • • ' • � - — • — • — DREDGE AREA APPROXIMATE EXTENTS APPROXIMATE LIMITS OF DISTURBANCE TURBIDITY MONITORING LOCATION CULVERT \\ \ �\ DOWNSTREAM TURBIDITY MONITORING \. LAKEADGER �'\ STATION: (FULL POOL ELEVATION 911.61') V N35.335345° I \ W82.2233970 NORTH LAKE ADGER 0 150 300 SCALE IN FEET � � F = PO _ �O O V r � O 0 Z UPSTREAM TURBIDITY MONITORING STATION: w N 35.330801 ° z o W82.235823° SOURCES: Q = a z m i 1. PHOTOGRAPH ©2019 AERIAL IMAGERY N RIVER (NC ONE MAP) Y i GREE _ r .... _ ;;. - _ ._. _ _ m 00 2. TOPOGRAPHIC SURVEY BY HAYESIJAMES o 27 2 DATED AUGUST 018. z o LL J Z V w - N w - w V LL to DRAFT -NOT FOR CONSTRUCTION REVISIONS NORTH DESIGNED BY: CORK,R. NORTH CAROLINA WILDLIFE RESOURCES COMMISSION C5 REV DATE BY AP DESCRIPTION LAKE ADGER NAVIGATION CHANNEL MAINTENANCE DREDGING ��®� CAROLINA ' Knowwhaesbelow. Call betas you dig. DRAWN BY : HOLMER, D. CHECKED BY: REEMTS, M. 7 - QEA(`�, ® �`� �v RESOURCES APPROVED BY : DINICOLA, W. COMMISSION SCALE: AS NOTED DATE: JANUARY2021 TURBIDITY MONITORING LOCATIONS HEET# 8 of 11