I ?oo3'1
Chatham SR 2316 1
Herndon, Mason
Sent: Thursday, February 10, 2011 2:51 PM
To: King, Art C
Cc: Smith, Ronnie D SAW [Ronnie.D.Smith@usace.army.mil]; Carrillo, Sonia
Art, I have reviewed your application for Zeb Brook Rd (SR 2316) in Chatham and did a site visit yesterday. I
have a couple of questions and/or clarifications that need to be addressed, before I can issue the 410:
Site 1-The permit drawing does not show the existing pipe so I cannot determine for sure if you are proposing
to adjust the skew of the proposed pipe to align with stream channel at the R/W limits. Currently the stream
enters the roadside ditch and flows down the road ^25 ft before entering the existing pipe. So are you
proposing to install the new pipe in line with the channel intercept at the R/W on both the inlet and outlet
ends? Based on the drawing and proposed length of new pipe, it appears that you are. Just want to make sure
Site 2 -The permit drawing appears to show rip rap bank stabilization beyond the inlet and outlet ends of the
proposed pipe. However, you only requested authorization for 28 ft of impacts for the additional length of
proposed pipe (60 ft proposed minus 32 ft of existing). You need to either eliminate the rip rap from the permit
drawing or modify page 4 of your PCN and include a separate line of impacts for bank stabilization at Site 2. If
you can, make the appropriate changes on either the drawing or PCN, scan it and e-mail it to me as soon as
possible.
If you have any questions or want to discuss any of these items, please do hesitate to give me a call.
Thanks!
Mason
Mason Herndon
Environmental Senior Specialist
NCDENR, Division of Water Quality
Surface Water Protection
mason.herndon(o)ncdenr.gov
Phone: (910) 308-4021
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties.
https:Hmail.nc.gov/owa/?ae=ltem&t- W2TJHI4%2bm... 2/25/2011
RE: Pitt 64 Revisions
RE: Pitt 64 Revisions
Ward, Garcy
Sent: Wednesday, February 09, 2011 10:53 AM
To: Sutton, Michael W; Garcy Ward (garcy.ward@ncmail.net); Carrillo, Sonia
Cc: Johnson, Jay B; Steffens, Thomas A SAW [Thomas.A.Steffens@usace.army.mil]
Page 1 of 1 .
Mike,
Thanks for the revisions. Did you find out about the on-site detour? The NRTR
submitted with the application indicates there will be one. This would create
additional impacts that need to be accounted for. Thanks. - Garcy
E-mail correspondence to and form this address may be subject to the North Carolina
Public Records Law and may be disclosed to third parties.
-----Original Message-----
From: Sutton, Michael W [mailto:msutton@ncdot.gov]
Sent: Friday, February 04, 2011 4:19 PM
To: Garcy Ward (garcy.ward@ncmail.net); Carrillo, Sonia
Cc: Johnson, Jay B
Subject: Pitt 64 Revisions
Good Afternoon Ms. Sonia and Mr. Garcy.... Attached are revisions for Pitt 64; please
replace the old 404 wetland sheet with this revision, as well as page numbers 5 and
7 of the PCN... Thank You...Have a Great Week-End ..... mike
Email correspondence to and from this sender is subject to the N.C. Public Records
Law and may be disclosed to third parties.
https:Hmail.nc. gov/owa/?ae=Item&t=I PM.Note&id=RgAAAADMSzLcd9 W 2TJHI4%2bm..: 2/25/2011