HomeMy WebLinkAbout20110155 Ver 1_401 Application_20110211C A S S O C I A T E S February 14, 2011 20110155 ~ _ ~~" Mr. Tyler Crumbley Regulatory Specialist Asheville Regulatory Field Office US Army Corps of Engineers -Wilmington District 151 Patton Avenue, Room 208 Asheville, North Carolina 28801 Dear Mr. Crumbley: ~~~p~~ FE;=s ~ ~ ~~~~ RE: Pre-Construction Notification Form Fletcher Town Hall Henderson County, North Carolina Please find enclosed one (1) complete Pre-Construction Notification (PCN) submittal package for your review for the above referenced project. The complete submittal package includes the following information: 1. One (1) completed PCN form. 2. One (1) copy of the overall site plan. 3. One (1) copy of the project narrative. 4. One (1) copy of the exhibits for the proposed project area and impacts. 5. One (1) copy of the calculations for the proposed stream relocation. 6. One (1) copy of the original site for the proposed town hall. 7. One (1) copy of the approved jurisdictional determination for the site. The proposed site plan includes a temporary loss of flow along the existing streams being offset by the permanent relocation of the streams; therefore the Town of Fletcher is requesting a Nationwide permit without mitigation requirements. If during the review, mitigation is deemed necessary, an EEP approval to pay into the In Lieu Fee program has been issued for the project and can be submitted upon request. This project has been approved and funded by the USDA program. The project will need to be approved April 1, 2010 or the funding could be removed by the USDA. I trust this submittal will meet all applicable standards and regulations and look forward to your timely approval of this project. Engineering P l a n n i n g . F i n a n c e McGill Associates, P.A. P. O. Box 2259, Asheville, NC 28802 55 Broad Street, Ashei~ille, NC 28801 828-252-0575 Fax: 828-252-2518 Mr. Tyler Crumbley February 14, 2011 Page 2 of 2 If upon review you should have any questions or need additional information, please do not hesitate to contact me. Sincerely, McGILL ASSOCIATES, P.A. REBECCA J. JOHNSON, PE Senior Project Engineer Enclosures cc: Ms. Cyndi Karoly, NCDWQ 401/Wetlands Unit (w/ enclosures) Mr. Dave McHenry, NCWRC Mountain Region Coordinator (w/ enclosures) Mr. Bryan Tompkins, USFWS (w/enclosures) Mr. Mark Biberdorf, Town of Fletcher (w/ enclosures) P:\2011\11.00401-Fletcher Town Hall Site Desib \Letters\tcl0feb11 -corppermr it.docx 241 10 155 O~O-~~~yW AT~~9~G o~~ Office Use Only: Corps action ID no. DWQ project no. Form Version 1.3 Dec 10 2008 Pre-Construction Notification PC Form A. A licant Information 1. Processing 1 a. Type(s) of approval sought from the Corps: ®Section 404 Permit ^ Section 10 Permit 1 b. Specify Nationwide Permit (NWP) number: 39 or General Permit (GP) number: 1 c. Has the NWP or GP number been verified by the Corps? ®Yes ^ No 1 d. Type(s) of approval sought from the DWQ (check all that apply): ® 401 Water Quality Certification -Regular ^ Non-404 Jurisdictional Genera ^ 401 Water Quality Certification -Express ^ Riparian Buffer Authorization l Permit 1 e. Is this notification solely for the record because written approval is not required? For the record only for DWQ 401 Certification: ^ Yes ®No For the record only for Corps Permit: ^Yes ®No 1f. Is payment into a mitigation bank or in-lieu fee program proposed for mitigation of impacts? If so, attach the acceptance letter from mitigation bank or in-lieu fee program. ^Yes ®No 1g. Is the project located in any of NC's twenty coastal counties. If yes, answer 1h below. ^Yes ®No 1 h. Is the project located within a NC DCM Area of Environmental Concern (AEC)? ^Yes ®No 2. Project Information ~• 2a. Name of project: Heart of Fletcher -Town Hall 2b. County: Henderson {r"""~"~,-- -w_.,_-. 2c. Nearest municipality /town: Fletcher F~,~ 2d. Subdivision name: N/A 2e. NCDOT only, T.I.P. or state project no: weU$ndc,$~a~~Q(/,q~ ata 3. Owner Information 3a. Name(s) on Recorded Deed: Adele Petigru Moore Town of Fletcher 3b. Deed Book and Page No. 1436/129 928/239 3c. Responsible Party (for LLC if applicable): 3d. Street address: 59 B King Street 4005 Hendersonville Road 3e. City, state, zip: Charleston, SC 29401 Fletcher, NC 28732 3f. Telephone no.: N/A (828)687-3985 3g. Fax no.: N/A (828)687-7133 3h. Email address: m.biberdorf@fletchernc.org Page 1 of 11 PCN Form -Version 1.3 December 10, 2008 Version 4. Applicant Information (if different from owner) 4a. Applicant is: ^ Agent ®Other, specify: Town of Fletcher has the option to buy adjacent parcel. 4b. Name: Mark Miberdorf c/o Town of Fletcher 4c. Business name (if applicable): 4d. Street address: 4005 Hendersonville Road 4e. City, state, zip: Fletcher, North Carolina 28732 4f. Telephone no.: (828)687-3985 4g. Fax no.: (828)687-7133 4h. Email address: m.biberdorf@fletchernc.org 5. AgentlConsultantlnformation (if applicable) 5a. Name: Rebecca J. Johnson 5b. Business name (if applicable): McGill Associates, P.A. 5c. Street address: 55 Broad Street 5d. City, state, zip: Asheville, North Carolina 28801 5e. Telephone no.: (828)252-0575 5f. Fax no.: (828)252-2518 5g. Email address: Becky.johnson@mcgillengineers.com Page 2 of 11 PCN Form -Version 1.3 December 10, 2008 Version B. Project Information and Prior Project History 1. Property Identification 1a. Property identification no. (tax P-N or parcel ID): 702074 and 9936077 Latitude: 35.430267 Longitude: - 1b. Site coordinates (in decimal degrees): 82.498827 (DD.DDDDDD) (-DD.DDDDDD) 1c. Property size: 98.03 and 27.96 acres 2. Surface Waters 2a. Name of nearest body of water (stream, river, etc.) to UT of Cane Creek proposed project: 2b. Water Quality Classification of nearest receiving water: C 2c. River basin: French Broad 3. Project Description 3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this application: The site is currently used for agricultural purposes. Adjacent properties are used for the Town of Fletcher Public Works and Police Department, town park and other agriculutural purposes. 3b. List the total estimated acreage of all existing wetlands on the property: 0.33 acre wetland polygon, 0.73 acre wetland ditch 3c. List the total estimated linear feet of all existing streams (intermittent and perennial) on the property: 4,154 LF 3d. Explain the purpose of the proposed project: The construction of a new Town Hall with related parking. 3e. Describe the overall project in detail, including the type of equipment to be used: The project will be typical site and building construction activities requiring the use of dozer, track hoe, dump truck and roller. No specialized equipment is anticipated for the construction of this project. 4. Jurisdictional Determinations 4a. Have jurisdictional wetland or stream determinations by the Corps or State been requested or obtained for this property / ®Yes ^ No ^ Unknown project (including all prior phases) in the past? Comments: 4b. If the Corps made the jurisdictional determination, what type ^ Preliminary ®Final of determination was made? 4c. If yes, who delineated the jurisdictional areas? Agency/Consultant Company: USACE and Clearwater Name (if known): Tasha McCormick, Amanda Jones and Environmental Consultants Tyler Crumbley, USACE and Rebekah Newton, Clearwater Other: 4d. If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation. June 11, 2010 site visit and June 28, 2010 issue date 5. Project History 5a. Have permits or certifications been requested or obtained for ^Yes ®No ^ Unknown this project (including all prior phases) in the past? 5b. If yes, explain in detail according to "help file" instructions. Page 3 of 11 PCN Form -Version 1.3 December 10, 2008 Version 6. Future Project Plans 6a. Is this a phased project? ^ Yes ®No 6b. If yes, explain. Page 4 of 11 PCN Form -Version 1.3 December 10, 2008 Version C. Proposed Impacts Inventory 1. Impacts Summary 1 a. Which sections were completed below for your project (check all that apply): ^ Wetlands ®Streams -tributaries ^ Buffers ^ Open Waters ^ Pond Construction 2. Wetland Impacts If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted. 2a. 2b. 2c. 2d. 2e. 2f. Wetland impact Type of jurisdiction number - Type of impact Type of wetland Forested (Corps - 404, 10 Area of impact Permanent (P) or (if known) DWQ -non-404, other) (acres) Tem ora T W1 ^ P ^ T ^ Yes ^Corps ^ No ^DWQ W2 ^ P ^ T ^ Yes ^Corps ^ No ^DWQ W3 ^ P ^ T ^ Yes ^Corps ^ No ^DWQ W4 ^ P ^ T ^ Yes ^Corps ^ No ^DWQ W5 ^ P ^ T ^ Yes ^Corps ^ No ^DWQ W6 ^ P ^ T ^ Yes ^Corps ^ No ^DWQ 2g. Total wetland impacts 2h. Comments: 3. Stream Impacts If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this question for all stream sites impacted. 3a. 3b. 3c. 3d. 3e. 3f. 3g. Stream impact Type of impact Stream name Perennial Type of jurisdiction Average Impact number - (PER) or (Corps - 404, 10 stream length Permanent (P) or intermittent DWQ -non-404, width (linear Temporary (T) (INT)? other) (feet) feet) S1 ^ P ®T Loss of flow due to grading UT to Cane Creek ®PER ^INT ®Corps ^DWQ 335 Relocation of S2 ®P ^ T stream and UT to Cane Creek ®PER ®Corps 145 restoration of ^INT ^DWQ existing flow paths S3 ^ P ^ T ^PER ^Corps ^ INT ^DWQ S4 ^ P ^ T ^PER ^Corps ^ INT ^DWQ S5 ^ P ^ T ^PER ^Corps ^ INT ^DWQ S6 ^ P ^ T ^PER ^Corps ^ INT ^DWQ 3h. Total stream and tributary impacts 490 3i. Comments: The temporary impacts to the existing streams will be offset by the permanent french drains and onsite mitigation with the stream relocation. Page 5 of 11 PCN Form -Version 1.3 December 10, 2008 Version 4. Open Water Impacts If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of the U.S. then individually list all open water impacts below. 4a. 4b. 4c. 4d. 4e. Open water Name of waterbody impact number - (if applicable) Type of impact Waterbody type Area of impact (acres) Permanent (P) or Tem ora T 01 ^P^T 02 ^P^T 03 ^P^T 04 ^P^T 4f. Total open water impacts 4g. Comments: 5. Pond or Lake Construction If and or lake construction ro osed, then com lete the chart below. 5a. 5b. 5c. 5d. 5e. Wetland Impacts (acres) Stream Impacts (feet) Upland Pond ID Proposed use or purpose (acres) number of pond Flooded Filled Excavated Flooded Filled Excavated Flooded P1 P2 Sf. Total 5g. Comments: 5h. Is a dam high hazard permit required? ^ Yes ^ No If yes, permit ID no: 5i. Expected pond surface area (acres): 5j. Size of pond watershed (acres): 5k. Method of construction: 6. Buffer Impacts (for DWQ) If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts below. If an impacts require mitigation, then ou MUST fill out Section D of this form. 6a. Project is in which protected basin? 6b. 6c. 6d. Buffer impact number - Reason Permanent (P) or for Temporary (T) impact B1 ^P^T B2 ^P^T B3 ^P^T 6i. Comments: ^ Neuse ^Tar-Pamlico ^ Other: ^ Catawba ^ Randleman 6e. 6f. 6g. Buffer Stream name mitigation re uired? ^ Yes ^ No ^ Yes ^ No ^ Yes ^ No 6h. Total buffer impacts Zone 1 impact Zone 2 impact (square feet) (square feet) Page 6 of 11 PCN Form -Version 1.3 December 10, 2008 Version D. Impact Justification and Mitigation 1. Avoidance and Minimization 1a. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project. The building site has been moved from the initial plan to avoid and minimize the impacts to the adjacent streams. The new proposed site plan incorporates retaining walls to confine the grading and minimize the impact. The USACE has been consulted throughout the design process and prior to submittal of this application. 1 b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques. The stream relocation construction will be performed prior to any site construction to remove the flow from the site to minimize the overall impact. Proper erosion control measures will be installed to minimize the impact to the perenial stream and to avoid any unanticipated impacts during construction. 2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State 2a. Does the project require Compensatory Mitigation for impacts to Waters of the U.S. or Waters of the State? ^ Yes ®No 2b. If yes. mitigation is required by (check all that apply): ^DWQ ^ Corps 2c. If yes, which mitigation option will be used for this project? ^ Mitigation bank ^ Payment to in-lieu fee program ^ Permittee Responsible Mitigation 3. Complete if Using a Mitigation Bank 3a. Name of Mitigation Bank: 3b. Credits Purchased (attach receipt and letter) Type Quantity 3c. Comments: 4. Complete if Making a Payment to In-lieu Fee Program 4a. Approval letter from in-lieu fee program is attached. ^ Yes 4b. Stream mitigation requested: linear feet 4c. If using stream mitigation, stream temperature: ^ warm ^ cool ^cold 4d. Buffer mitigation requested (DWQ only): square feet 4e. Riparian wetland mitigation requested: acres 4f. Non-riparian wetland mitigation requested: acres 4g. Coastal (tidal) wetland mitigation requested: acres 4h. Comments: 5. Complete if Using a Permittee Responsible Mitigation Plan 5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan. Page 7 of 11 PCN Form -Version 1.3 December 10, 2008 Version 6. Buffer Mitigation (State Regulated Riparian Buffer Rules) -required by DWQ 6a. Will the project result in an impact within a protected riparian buffer that requires buffer mitigation? ^ Yes ^ No 6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the amount of mitigation required. Zone 6c. Reason for impact 6d. Total impact (square feet) Multiplier 6e. Required mitigation (square feet) Zone 1 3 (2 for Catawba) ~! Zone 2 1.5 6f. Total buffer mitigation required: 6g. If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank, permittee responsible riparian buffer restoration, payment into an approved in-lieu fee fund). II 6h. Comments: Page 8 of 11 PCN Form -Version 1.3 December 10, 2008 Version E. Stormwater Management and Diffuse Flow Plan (required by DWQ) 1. Diffuse Flow Plan 1 a. Does the project include or is it adjacent to protected riparian buffers identified ^Yes ®No within one of the NC Riparian Buffer Protection Rules? 1 b. If yes, then is a diffuse flow plan included? If no, explain why. ^ Yes ^ No Comments: 2. Stormwater Mana ement Plan 2a. What is the overall percent imperviousness of this project? 53.2 2b. Does this project require a Stormwater Management Plan? ®Yes ^ No 2c. If this project DOES NOT require a Stormwater Management Plan, explain why: 2d. If this project DOES require a Stormwater Management Plan, then provide a brief, na rrative description of the plan: The proposed site will include a mechanical treatment system and detention pipes on the north side of the property as well as a wet pond on the south side to provide adequate storage and treatment for the site to meet the standards set forth by Henderson County, a Phase II community. ® Certified Local Government 2e. Who will be responsible for the review of the Stormwater Management Plan? ^DWQ Stormwater Program ^ DWQ 401 Unit 3. Certified Local Government Stormwater Review 3a. In which local government's jurisdiction is this project? Henderson County ® Phase II 3b. Which of the following locally-implemented stormwater management programs ^ NSW ^ USMP apply (check all that apply): ^ Water Supply Watershed ^ Other: 3c. Has the approved Stormwater Management Plan with proof of approval been ^Yes ®No attached? 4. DWQ Stormwater Pro ram Review ^ Coastal counties ^ HQW 4a. Which of the following state-implemented stormwater management programs apply ^ ORW (check all that apply): ^ Session Law 2006-246 ^ Other: 4b. Has the approved Stormwater Management Plan with proof of approval been attached? ^Yes ^ No 5. DWQ 401 Unit Stormwater Review 5a. Does the Stormwater Management Plan meet the appropriate requirements? ^Yes ^ No 5b. Have all of the 401 Unit submittal requirements been met? ^Yes ^ No Page 9 of 11 PCN Form -Version 1.3 December 10, 2008 Version F. Supplementary Information 1. Environmental Documentation (DWQ Requirement) 1 a. Does the project invo-ve an expenditure of public (federal/state/local) funds or the ®Yes ^ No use of public (federal/state) land? 1 b. If you answered "yes" to the above, does the project require preparation of an environmental document pursuant to the requirements of the National or State ^Yes ®No (North Carolina) Environmental Policy Act (NEPA/SEPA)? 1 c. If you answered "yes" to the above, has the document review been finalized by the State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval ^Yes ^ No letter.) Comments: N/A 2. Violations (DWQ Requirement) 2a. Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland Standards, ^Yes ®No or Riparian Buffer Rules (15A NCAC 2B .0200)? 2b. Is this an after-the-fact permit application? ^Yes ®No 2c. If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s): 3. Cumulative Impacts (DWQ Requirement) 3a. Will this project (based on past and reasonably anticipated future impacts) result in ^Yes ®No additional development, which could impact nearby downstream water quality? 3b. If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent DWQ policy. If you answered "no," provide a short narrative description. 4. Sewage Disposal (DWQ Requirement) 4a. Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. The proposed facility will discharge any wastewater through a gravity sewer line that will be connected to an existing sewer system. Page 10 of 11 PCN Form -Version 1.3 December 10, 2008 Version 5. Endangered Species and Designated Critical Habitat (Corps Requirement} 5a. Wiil this project occur in or near an area with federally protected species or ^ Yes ®No habitat? 5b. Have you checked with the USFWS concerning Endangered Species Act [] Yes ®No impac#s? ^ Raleigh 5c. If yes, indicate the USFWS Field Office you have contacted. ^ Asheville 5d. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical Habitat? http:/lwww.fws.govlnc-esles/countyfr.html 6. Essential Ffsh Habitat (Corps Requirement} 6a. Will this project occur in or near an area designated as essential fish habitat? ^ Yes ®No 6b. What data sources did you use to determine whether your site would impact Essential Fish Habi#at? http:llwww.ncfisheries.net/habitatlchppmap.html 7. Historic or Prehistoric Culturai Resources (Corps Requirement} 7a. Wiil this project occur in or near an area that the state, federal or #ribal governments have designated as having historic or cultural preservation [] Yes ®No status (e.g., National Historic Trust designation or properties significant in North Caroiina history and archaeology)? 7b. What data sources did you use to determine whether your site would impact historic or archeological resources? ht#p:l/wvrw.hpo.ncdcr.govlnrlist.htm and study performed by Scott Schumate of Blue Ridge Archeological Consultants 8. Fiood Zone Designation (Corps Requirement} 8a. Will this project occur in a FEMA-designated 100-year floodplain? ^ Yes ®No 8b. If yes, explain how project meets FEMA requirements: 8c. What source(s) did you use to make the floodplain determination? http:/lwww.ncfloodmaps.com/ Mark Biberdorf, Town Manager G~ %~ 0 2- l ~ -- w(( Applicant/Agent's Printed Name Applicant/Agent's Sign re Date (Agent's signature is valid only if an author¢ation letter from the applicant is rovided. Page 11 of 11 PCN Form -Version 1.3 December 10, 2008 Version PROJECT NARRATIVE The Town of Fletcher proposes to develop the property adjacent to their current Parks and Recreation Department to establish the community center, the Heart of Fletcher. The property is currently an agricultural site that contains 1.06 acres of wetlands and 4,1541inear feet of streams as delineated by the Unites States Army Corp of Engineers (USAGE) along with C1earWater Environmental Consultants. The original master plan for the site was to develop most of the property to incorporate the Town's administrative offices as well as provide an area for commercial development. The original site plan was developed using an aesthetic approach without much consideration to the environmental impacts to the site. A copy of the original site plan is attached for reference. The impacts to the wetlands and streams would have required an Individual Permit. from the USAGE. The Town has revisited the original concept of the site and has revised the plan based on economic factors as well as overall approach. The currently proposed project consists of a single Town Hall building that will house the Town's administrative offices and Police department, producing minimal impacts to adjacent streams and wetlands. The revised site plan has moved the location of the proposed building site as well as incorporated retaining walls to limit the amount of disturbance on the project. The proposed site will also have minor temporary impacts to the adjacent streams with a permanent relocation of the stream behind the proposed site, reducing the overall impact to the site. We have calculated the drainage area of the proposed relocated stream section. Based on this drainage area, we prepared a conceptual design of the relocated stream cross-section. We are in the process of completing the stream design process including survey, site assessment, identification and measurement of reference reach, performing River Morph analysis of relocated stream section and preparing final design documents by refining our conceptual design. Based on serious time constraint that affect the viability of this project, we are submitting this application with conceptual design included with the understanding that a complete detailed design will be submitted within the next few weeks to completely explain the details and basis of the relocated stream. We are prepared to perform all necessary reporting, bidding construction monitoring and close-out documentation as required by USAGE, DWQ and all other commenting agencies. 6SW-Jp9SN3Ji"1 WNI~ SLSUZSZ IpLRI'Hd IIIppZ JN '99lIAHHSV a~aais HVOae ss " `"~~,,,,,,,,,,p~~~ f '' `dNll02~d~ H12jON `J.1.Nf10~ NOS2~~aN~H Id•JNI2I3flNIJNd d~NVNI3•JNINNV s ~ .r. ~ r ~ Q s s ~ ~~,,' ,o5a ?_ ' a = _^^_// ~ 3 H V 1~ ~ ~ ~ 0 N MOl 3wvN3~l3 -'M31n3i~ '1SN00 ` J~Hdd~IJOd01 ' 1181 Hx~ ~ \~~ w /~ ~ Q .~a ~M31n3L1 N JIS30 N~ :~.e aav~ NOIld00~~~1 Wd~2~1S J 2 "'- 2 o ~ ffa:xa o3N~ls3a (n ~-~-~ , ,~ .~ •. -, o ; ,, ~~H~1~~~ ~O l~ib'~H ' , , ~ppO1ppO~"~ LLOZ 933~31d0 ' ' • ON 90f LOb00 60 ~ z 0 a U 009 OOb OOZ 0 004 OOZ w 0 z 0 OOZ = ,~ L ~~`d~S ~ ,L ,~ ~ ~./~ _ ~ / / / I I I 1 `~. ~` . `. `~ \ ~ ` ~ ~ `~ \ 1 ~ -~ ~~ t ( / I 1 iii III 1 I ' ~ I / • ~• t ~ ~ ~ ~~ ,` .~ ,:%i =_~ \\ ,: / ~ /~ ~~` ~\\ `~ `~ \ \ \ ~\\~ ~\ ~ ~_-` J.NdaNfl08 ~- 1 ~ I 1 I I ; ~ ' \ '~ ` ~~ ~ I I I ~ \~ ,,,~ ,, -- i ~ ~ `~~~ ~` ~~~> ~ \ ` \ `~ dfIO~IJ BIOS ~IJOIO~IaJ.H \~ \ I { ~ ~- `~ ~~ •..,--, ~ 1 ter- ~. t ~ , 1 ~ + \ \ ' ' , , r /l2~dONf108 ` ~ MO~d I~NN dH0 N~dO ~~ L556 `, ,~~ \~ ``` ` / , ` l J--^ MOId a~1d2~1N~~N0~ MO~IdHS ~~ Z6 ~~, 11 \ "~. i ~\ ~, i i ~-- ~ ~ , MO~d 1d~HS d~ 661. `, ~~ i t i ` ~\ i i l - ~ ~~ ` 111 1 Hldd MO~d ~- --- .`` ----- ~~ 1 n \~~ 1 \ ,` ` ~`. i 1. ~ ~ ~ ~.. _~;~\ / ~__ ~~ ,, -~ ;~ --.. ~~__ _ 1` _ \ .. ~ I ` -~ ~ ~ ~ --___ \ I -- , ~~~ ) ~ -- , ~ ~ ` J ~--- ---------- , \ \ ,/ ~\ , /' r 1 \ , 111'1 ' I / r/___--- -_._~ `~`\ 03110 WV ZL:LL LLOZRNZ 6mp•uolleoolaa weailS dOH\uo0eooiaa wea~Ig~s6ulme~O~IInIO~u61saO~LOb00'601600Z1~0 i'/ cK O3Li0 WV SL L1 LLOZ/LL/Z 6mp~uoileoo~aa wea~~S dOHluopeso~aa wea~1S1s6uime~O1~iniOlu6isaO1LOb00'601600ZGb 6SNl9g3SN3Jil W81a scsu-zsz lezei~na IIIBBZ JN 'H'191n3H5V awvas avaav ss HNIl02~`d0 H1NON '.l1Nf100 NOS2~~aN~H NOIlO~S-SSO~10 ~ ~ ICI b' IvI I d ' ~J N I ICI ICI d "I d • rJ 1~I I 2I ~ 3 AI I sJ N ~ _ 2``~un1 runq''',d S~ Z d 1~ ~ S S d `~05~ m~", :3WtJN 3113 ~ ~~ ~13H~13~~ ~0 NMOl ~M3~A3a~1SN00 ~ d~ ~s0,~ w '- ~ ~M31~3a NJ~S30 - 1181HX~ W s. ~a =~r HO ~A9 OOVO ~~""'y~'o v~~•'~~ ~I~H~l~~~ ~O 1~1d~H rra Aea3N~is3a NOIl`d00~~2~ Wt/~2J1S (A ~.-~-~ ~ ~~~~~~~uunnap~~~ LLOZ'83d ~31'd0 LOb00'60 ~'ON BOf O ~ z ~ ^ .-. O C~ (~ ~ ~ a Z (h o ~ ~ ~ U p I- w W \\ ~ \ \ I ,\ ~ ~ 11 I 1 / ' / N W p p w \ \ \\\ ; I / 1 II / p~?cn ~ \ I ~ 1 I / Q~ ~~z ~\ \ I 1/I I ~ , 1 1 o~w 1 sl \ .~1 I I~ °~~ \\ ~ \ ~ 1 \\ Z ~ ` ~ ' 1 II' Q ° ~ I ~\ \\ ~\ i 1 J~ I IJ 11 iii ~~= \ \5~ \ / 1 ~- / 1 1 1111 ~~a I ° m I / 1 ~ ~ \~~ ~,~ \\ ~ \\ \ \\ p ~ I/ ~ i i iii ~ ° o I ~ ~ 1 ' \ 1 \ O - I / 1 1111 ~~Q - ~= w I I I 1 Illl wpb I ~ w \~5 ~\ I I I \\ U-'I I I Illl QUO I iw-~rn Z 1 ~ I I 1 IIII ~~z Q(~N ~ \\ 1 I I \\ ~ J I I IIII 1 who ~ ~ \ I \ \ W I I 1 IIII I' Qom ~~ ~ \ ~ I \ 1}~ I W I 1 IIII Il ~ W ~ ~\ \ i \ \o _ I Q I 1 IIII Ill X00 ~ \ 1 \ k7 I W I I 1111 Ill ~~~ \ I I I /~-~ IZ I I 1111 Illj wW~ \I I ~ I ~ I I.L _ ~ ~ ~ I /Ill 1111 ~ Q Q o I I I 10 1 Illl II ~mz I ~ I, I Q ! fn ~ I I 11 111 Illl \ 1 1 I w 1~_ I I 1 1111 11111 I I I I ~ ~ 1 _ 1 I 1 1 Ill IIII l cn ~\ I I I I ~ M \~ 1 I 11111 III l l .~ \ I I I l o w 1-~~1 I 1 1111 1111111 z~ I I I ~ w~-~a I - 1 11111 O \ I I ~Qw IX 1 111 11I1~ F= \ I I I az~~ I~ I I I IIII Ill lj U \ I 11 I ~z 1 po~W IO- ~ I I 1 1111 I~ll~ lI w l I I i I° I aaxc~ IQ -1 j 1 1111 ~~1I~1 ~ I I I Q w ~ 0 1 I 1111 I 11 i ~ ~ lo~ ~~~~ I 11 ~ / IIII ~~Ij~l!' o O I I 1 I awl o~aQ I ~, I l 1111 ~II~1 tY \ 1 1 ~ 1 I~ ~- T ~I i 1~ 1 ~ i ~i i~iii i ~ ~ \ I I / ~¢ I I 1 ,I, / IIl III 1 ~ Q \\ II i ~ I I ~ 11 / ~ ~ i `/1 j j l~ i f c~n I I I ~ ' \~l,/ II ~ ~ pUw ~ ~ `_ ~ ~ N / ~ _ 1 ~ ~~ \~\\\\~ \\ ~~ /~ \ '-'~- I - \ 1 ~/ vow \~~~ _ \ \ 1 1 1 •/ o N J o \ \~\ \\ ~\ \ ~~~ ~ ~ \ \1 ~ ~\ III ~ / Q w ~ ~ \ \ ~~ ~\~~\~ \ \~A\~,/ \ \\ fir[^~\ II~1 ~ l /' (~' N pz p .- ~ \\\ \ \\ ~~ ~ `,~,, ~ \ \'1~ j \ 1 111111 I / /~ ¢ ~ \ \ \ ~ I1 1 I ~ \\\ ~~.::~.. \ 1 ~1 1 Ill I C J / o Q \ \ \\ ~ ~ ~ ~1 I 1 I I , , ~ ~~ ~ ~ \~ lei. \ \ ~ ~,, \ - ~ I I 1 ll C ~ ~ o cn ~ ~ ~\ \ \ \ ~ r ~ / 1 ` F-- ~ \\ \ Q ~ ~ \ ~ \\\\\ \ ~ \ \ L o \ \ \ ~g \ 1 \ ~ \ ~ \kz~ ~ .~~~_.\. ~-` lam. ~S~ ~ \ ~ \ ~ > ~ ~ \\\/ ~ I J32i0 Wd 6b~b LLOZ/OUZ 6nnpvoi~eoo~aa weans 30H1uopeoo~aa wea~~g~s6uinne~O~pniO~ufiisa0\LOb00'601600Z10 "t Stream Narrative Page 1 of 1 Town of Flethcer During recent observations, the base flow of the existing stream was estimated to be approximately 0.56 cubic feet per second. This was done by measuring the normal depth of the water and analyzing it against the average slope and estimated roughness coefficient of 0.30. The average normal depth was estimated to be four inches. The shape of the channel is an irregularly shaped trapezoid. The cross section of the proposed stream can be analyzed in three stages. 1. Asymmetrical trapezoid was chosen as the cross section to allow for ease of construction. The normal depth for the base flow will be similar to the existing depth at 0.29 feet. 2. The main channel is designed to accommodate the two year storm. This is the maximum amount of runoff the stream can accommodate before spilling into the floodplain. The main channel will convey 63.24 cubic feet per second. This number is the runoff generated from the two year storm as well as the base flow. 3. In accordance with the Town of Fletcher ordinances, the floodplain is designed to accommodate the one hundred year storm. The flood plain will accommodate 143.89 cubic feet per second, in addition to the runoff conveyed in the main channel. ~1~C~rlll ASSOCIATES P:\2009\09.00401\Misc\Corp Permit\Stream Narrative.docx Worksheet for Base Flow project Description Friction Method Manning Formula Solve For Normal Depth Input Data Roughness Coefficient 0.030 Channel Slope 0.01300 ft/ft Left Side Slope 2.00 ft/ft (H:V) Right Side Slope 2.00 ft/ft (H:V) Bottom Width 0.50 ft Discharge 0.56 ft'/s Results Normal Depth 0.29 ft Flow Area 0.32 ftZ Wetted Perimeter 1.81 ft Top Width 1.67 ft Critical Depth 0.25 ft Critical Slope 0.02648 ft/ft Velocity 1.77 ft/s Velocity Head 0.05 ft Specific Energy 0.34 ft Froude Number 0.72 Flow Type Subcritical GVF'Input Data Downstream Depth 0.00 ft Length 0.00 ft Number Of Steps D GVF Output Data Upstream Depth 0.00 ft Profile Description Profile Headloss 0.00 ft Downstream Velocity Infinity ft/s Upstream Velocity Infinity ft/s Normal Depth 0.29 ft Critical Depth 0.25 ft Channel Slope 0.01300 ft/ft Critical Slope 0.02648 ft/ft Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [08.01.071.00] 2/1012011 4:17:14 PM 27 Siemons Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 Page 1 of 1 Worksheet for 2-Year Storm (Bank Full Estimate) Project Description Friction Method Manning Formula Solve For Normal Depth Input Data Roughness Coefficient 0.030 Channel Slope 0.01300 ft/ft Left Side Slope 2.00 ft/ft (H:V) Right Side Slope 2.00 ft/ft (H:V) Bottom Width 0.50 ft Discharge 63.24 ft'/s .Results Normal Depth 2.21 ft Flow Area 10.86 ftz Wetted Perimeter 10.38 ft Top Width 9.33 ft Critical Depth 2.16 ft Critical Slope 0.01445 ft/ft Velocity 5.82 ft/s Velocity Head 0.53 ft Specific Energy 2.74 ft Froude Number 0.95 Flow Type Subcritical GVF Input Data Downstream Depth 0.00 ft Length 0.00 ft Number Of Steps 0 GVF Output Data Upstream Depth 0.00 ft Profile Description Profile Headloss 0.00 ft Downstream Velocity Infinity ft/s Upstream Velocity Infinity ft/s Normal Depth 2.21 ft Critical Depth 2.16 ft Channel Slope 0.01300 ft/ft Critical Slope 0.01445 ft/ft Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [08.01.071.00] 2/1012011 4:17:07 PM 27 Siemons Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 Page 1 of 1 Worksheet for 100-Year Storm .Project Description Friction Method Manning Formula Solve For Normal Depth -Input Data Roughness Coefficient 0.030 Channel Slope 0.01300 ft!ft Left Side Slope 10.00 ft/ft (H:V) Right Side Slope 10.00 ft/ft (H:V) Bottom Width 9.34 ft Discharge 143.89 ft'/s Results Normal Depth 1.30 ft Flow Area 29.09 ftz Wetted Perimeter 35.50 ft Top Width 35.37 ft Critical Depth 1.28 ft Critical Slope 0.01414 ft/ft Velocity 4.95 ft/s Velocity Head 0.38 ft Specific Energy 1.68 ft Froude Number 0.96 Flow Type Subcritical GVF Input Data Downstream Depth 0.00 ft Length 0.00 ft Number Of Steps 0 GVF Output Data Upstream Depth 0.00 ft Profile Description Profile Headloss 0.00 ft Downstream Velocity Infinity ft/s Upstream Velocity Infinity ft/s Normal Depth 1.30 ft Critical Depth 1.28 ft Channel Slope 0.01300 ft/ft Critical Slope 0.01414 ft/ft Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [08.01.071.00] 2/1012011 4:17:00 PM 27 Siemons Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 Page 1 of 1 Area ID Land Use Hydrologic Soil Group Curve Number (CN) Area (acres) 1-A Commercial B 92 4.94 1-B Residential (Average Lot Size 1/2 Acre) B 70 23.36 1-C Commercial B 92 0.54 1-D Commercial B 92 0.59 2-A Commercial C 94 2.68 2-B Residential (Average Lot Size 1/2 Acre) C 80 7.12 Total Area: 39.23 Weighted CN: 77 Reference: Urban Hydrology for Small Watersheds TR-55 Drainage Area 1 Subcat Reach on Link Stream Analysis Prepared by {enter your company name here} Printed 2/8/2011 HydroCAD® 8.50 s/n 004263 ©2007 HydroCAD Software Solutions LLC Page 2 Area Listing (all nodes) Area CN Description (acres) (subcatchment-numbers) 39.230 77 Composite (1S) 39.230 TOTAL AREA Stream Analysis Prepared by {enter your company name here} Printed 2/8/2011 HydroCADO 8.50 s/n 004263 ©2007 HydroCAD Software Solutions LLC Page 3 Soil Listing (all nodes) Area (acres) Soil Goup Subcatchment Numbers 0.000 HSG A 0.000 HSG B 0.000 HSG C 0.000 HSG D 39.230 Other 1 S 39.230 TOTAL AREA Stream Analysis Type ll 24-hr 2-Year Rainfall=3.51 " Prepared by {enter your company name here} Printed 2/8/2011 HydroCAD® 8.50 s/n 004263 ©2007 HydroCAD Software Solutions LLC Page 4 Time span=5.00-20.00 hrs, dt=0.05 hrs, 301 points Runoff by SCS TR-20 method, UH=SCS Reach routing by Stor-Ind+Trans method -Pond routing by Stor-Ind method Subcatchment1S: Drainage Area 1 RunoffArea=39.230 ac 0.00% Impervious Runoff Depth>1.30" Flow Length=1,848' Tc=19.2 min CN=77 Runoff=62.68 cfs 4.265 of Total Runoff Area = 39.230 ac Runoff Volume = 4.265 of Average Runoff Depth =1.30" 100.00% Pervious = 39.230 ac 0.00% Impervious = 0.000 ac Stream Analysis Type ll 24-hr 2-Year Rainfall=3.51" Prepared by {enter your company name here} Printed 2/8/2011 HydroCAD~ 8.50 s/n 004263 ©2007 HydroCAD Software Solutions LLC Page 5 Summary for Subcatchment 1S: Drainage Area 1 Runoff = 62.68 cfs @ 12.13 hrs, Volume= 4.265 af, Depth> 1.30" Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs Type II 24-hr 2-Year Rainfall=3.51" Area (ac) CN Description 39.230 77 Composite 39.230 Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 10.5 199 0.0600 0.32 Sheet Flow, Shallow Concentrated Grass: Short n= 0.150 P2= 3.51" 0.3 92 0.0900 6.09 Shallow Concentrated Flow, Shallow Concentrated Paved Kv= 20.3 fps 8.4 1,557 0.0340 3.07 6.14 Channel Flow, Channel Flow Area= 2.0 sf Perim= 8.5' r= 0.24' n= 0.034 19.2 1,848 Total Subcatchment 1 S: Drainage Area 1 Hydrograph 70 ~~ ~ - - - ... _ ^ Runoff ss ~ ~ 62.68 cfs I ~ ' - ---- - - - - T- -e II-24=fir s° ~ -- --- - Yp 2=1~ear - 55 ~ ~ ~ ~ Rainfall=3.51" --- ---------i-------....- ----- ---i---_..----r---------------~-----,---- 50 ~ ~ ____~__ Runoff Area_39._2~0 ac_ _ 45 ~ ' runoff V-olume=4; ~_. _- --- .~_ _ _ _ . --_~_- ;- ;265..af... 40 ~ ----~- __ _ ~-- - _ _ --- ~ -- '~------_Runoff De ~~-- -- -- --- pth>1-.30- 3 35 ~ ~~ ~ ~ ~ 0 Ffow Length=11 ~848F _ LL 30 ~ 25 ~t Tc=19;.2 min 20 ~ ~I ~ - - _. _~ ~ ~ , . ~ CN=77 _ ~ I 1 I 15 I 10 ~ i I - - - ._~... ._ ... ... .. _. ._ ... ... .... ... ... ... ... ... ... .. .. ... ... ... ... _. ... ... .. ... .t ._ - - -_ C-. ... ... ... ... ... ... _. ._ ... _- _. ... _i._ ... _. ... .. ._ ... ... ... 5 ; 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Time (hours) Stream Analysis Type 1124-hr 100-Year Rainfall=7.32" Prepared by {enter your company name here} Printed 2/8/2011 HydroCAD® 8.50 s/n 004263 ©2007 HydroCAD Software Solutions LLC Page 6 Time span=5.00-20.00 hrs, dt=0.05 hrs, 301 points Runoff by SCS TR-20 method, UH=SCS Reach routing by Stor-Ind+Trans method -Pond routing by Stor-Ind method Subcatchment1S: DrainageArea 1 RunoffArea=39.230 ac 0.00% Impervious Runoff Depth>4.31" Flow Length=1,848' Tc=19.2 min CN=77 Runoff=206.01 cfs 14.102 of Total Runoff Area = 39.230 ac Runoff Volume =14.102 of Average Runoff Depth = 4.31" 100.00% Pervious = 39.230 ac 0.00% Impervious = 0.000 ac Stream Analysis Type 1124-hr 100-Year Rainfall=7.32" Prepared by {enter your company name here} Printed 2/8/2011 HydroCAD~ 8.50 s/n 004263 ©2007 HydroCAD Software Solutions LLC Page 7 Summary for Subcatchment 1 S: Drainage Area 1 Runoff = 206.01 cfs @ 12.11 hrs, Volume= 14.102 af, Depth> 4.31" Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs Type II 24-hr 100-Year Rainfall=7.32" Area (ac) CN Description 39.230 77 Composite 39.230 Pervious Area Tc Length Slope Velocity Capacity Description Amin) (feet) (ft/ft) (ft/sec) (cfs) 10.5 199 0.0600 0.32 Sheet Flow, Shallow Concentrated Grass: Short n= 0.150 P2= 3.51" 0.3 92 0.0900 6.09 Shallow Concentrated Flow, Shallow Concentrated Paved Kv= 20.3 fps 8.4 1,557 0.0340 3.07 6.14 Channel Flow, Channel Flow Area= 2.0 sf Perim= 8.5' r= 0.24' n= 0.034 19.2 1,848 Total Subcatchment 1S: Drainage Area 1 Hydrograph 210 w 13 12 c 11 ILL 10 _.. CfS ---- .---'---- ^Runoff - - - - - - - -T-ype..l I-24-h r-1.00-Xea K - _ __ _... _~, .._ _ _ Rai nf~[I ~:32'~ - _. _ _._.._....Runoff ;Area: 39~2:3Q_ac ___ Runoff Volumes--1~:102~ of --'---- -Runo_ffDepthy4:31"- - - - -- _ _ _ ..._ _ _ - -F~ow-Length=1;848` - _ . _..._ _ _ . __ __ _ _ __ Tc=19.~ rain- - __ .._. ~ __ _~ __ CN=77- 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Time (hours) •-,.. , j ~- -~--- - ,-"-~ --- s r - ~ ~ - ~ ,- ~~ I1 + ~ s t ' r \ ~ 11 ~ ~ , _' ~ , , ~ _ l _` c I ,,~ 1 `'--- 4 ' _ ~" ~ ~ ~~ ~ -~ ~?A ~ 1 '~ l `` 1 ~.~ * ~/..ice ~~~ ~\ F\J~~~ -• ~ ,\ 11 ~~ f ~ • ~ - ..j-~ `~~, f _ a.. ~71` `, 1 ~``j r f ~. \` t r ~ • ~'' r .,~ ~ +~ _~ ~ ~ !i t ._~~ ~ `, {~ ~ S' -- j ~ ~ ~ ~ : i ~ ^' r .. r 1 a J/~ '~ ,o f t~ '~ >' f H O C x Q ~~ :~ b !~ Heart of Fletcher Note: The illustrated +vetlaimd and stream locations are approximate. These areas have been flagged in the field; however, the} have not been sun~eyed. Although Clear\§'ater Environmental Consultants, Inc. is confident in our assessment. the L'S Anny Corps of Engineers (Corps) is the only agency that can make final decisions regardins jurisdictional wetland and +vaters of the US delineations. Therefore. all preliminary determinations are subject to change until ++~ritten verification is obtained. Clear\k'ater C-nvironmental Consulta~tts. Inc. strongly recommends that ++ritten verification be obtained from the Coryms prior to closing on the property, beginning any site work, or making airy legal reliance on this determination. # F~,-. ~~'~r ~, ` ~_: 5 J x f`t. ;' ! F xL ~' .~ ~ n ~:- F i' .,r ti . ~ Lam' r '~~~ x~ ~~, '~, , :~ .~ e ~' ~~ Legend Linear Wetland N Stream Total ' I ~ n Wetland Streams 4,154 linear feet Culvert Wetland Polygon 0.33 acre - - Wetland Ditch 0.73 acre 0 125 250 500 750 Delineation Bound 4,649 linear feet Feet Drawn by: RLN 04.01.10 C~earWater ~nvironmenta~ Consultants, ~nc- Henderson County, Stream and Wetland Delineation North Carolina 718 Oakland Stt-eet 04.01.10 Hendersonville, North Carolina 28791 828-698-9800 Heart of Fletcher ~~~~. yr Note: The illustrated wetland and stream locations are approximate. These areas have been flagged in the field; however, they have not been sun'eyed. ' Although Cleaz\\'ater Emirnnmental Consultants, Inc. is confident in our s -- assessment, the L:S Army Corps of Engineers (Corps) is the only agency that can make final decisions regardine jurisdictional H'etland and waters of ilte ~ , US delineations. Therefore. all prcliminan' determinations are subject to chati_e until ~~ritten verification is obtained. Clear\~'ater Environmental Consultants, htc. stronJy recommends that written verification be obtained from the Corps prior to closing on the property. beginning a»~' site work, or makine any legal reliance on this determination. 1 :. ~i,'tI Y T..-" Y.... y~ k ;•"'~ ~~ .r ~ ~~ ~,:: , .Yng } n L .i~ ~ '` ~~ ~ ~ U 5S. t~ ~~ 4a L •~~ t y y~ ~„ A y yy , ~f dl ,.,p } .~ 0 :;~ !% A•i ' ril('. h t S }` Legend Linear Wetland N Stream ~'~_ ~~ Wetland Culvert 0 125 250 500 750 Delineation Bound Feet Drawn by: RLN 06.16.10 Henderson County, ~~~~ ~~~r Stream and Wetland North Carolina Delineation Map 224 South Grove Street, Suite F X6,16.1 Hendersonville, North Carolina 28792 U.S. ARMY CORPS OF ENGINEERS WILMlI~tGTON DISTRICT Action Id. 2010-01007 County: Henderson U.S.G.S. Quad: Fruitland NOTIFICATION OF JURISDICTIONAL DETERMINATION Property Owner/Agent: Town of Fletcher Attention• Mark Biberdorf. Town Manager Address: 4005 Hendersonville Road Fletcher, NC 28732 SEC Rr~j~t ~ (o7-C~ Telephone No.: Data R~rcia~e+~ p~13~~11C) Property description: Size (acres} Greater than 5 acres Nearest Town Fletcher Nearest Waterway Unnamed Tributary to Cane Creek River Basin French Broad Coordinates 35.429556 ~N, -82.498158 W Location description The site is located on Parrish Municiaal Drive in Fletcher. Henderson County, NC. Indicate which of the Follovaans A~nly: A. Preliminary Determination _ Based on preliminary information, there may be waters on the above described property. We strongly suggest you have this property inspected to determine the extent of Department of the Army (DA) jurisdiction. To be considered final, a jurisdictional determination must be verified by the Corps. This preliminary determination is not an appealable action under the Regulatory Program Administrative Appeal Process (Reference 33 CFR Part 331). B. Approved Determination _ There are Navigable Waters of the United States within the above described property subject to the permit requirements of Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act. Unless there is a change in the law or our published regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification. X There are waters on the above described property subject to the permit requirements of Section 404 of the Clean Water Act (CWA)(33 USC § 1344). Unless there is a change in the law or our published regulations, this determination maybe relied upon for a period not to exceed five years from the date of this notification. _ We strongly suggest you have the waters on your property delineated. Due to the size of your property and/or our present workload, the Corps may not be able to accomplish this wetland delineation in a timely manner. For a more timely delineation, you may wish to obtain a consultant. To be considered final, any delineation must be verified by the Corps. X The waters on your property have been delineated and the delineation has been verified by the Corps. We strongly suggest you have this delineation surveyed. Upon completion, this survey should be reviewed and verified by the Corps. Once verified, this survey will provide an accurate depiction of all areas subject to CWA jurisdiction on your properly which, provided there is no change in the law or our published regulations, may be relied upon for a period not to exceed five years. _ The waters have been delineated and surveyed and are accurately depicted on the plat signed by the Corps Regulatory Official identified below on . Unless there is a change in the law or our published regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification. _ There are no waters of the U.S., to include wetlands, present on the above described property which are subject to the permit requirements of Section 404 of the Clean Water Act (33 USC 1344). Unless there is a change in the law or our published regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification. Action Id. 2010-01007 This delineation/determination has been conducted to identify the limits of COE's Clean Water Act jurisdiction for the particular site identified in this request. The delineation/determinationmoy not be valid for the wetland conservation provisions of the Food Security Act of 1985. If you or your tenant are USDA Program participants, or anticipate participation in USDA programs, you should request a certified wetland determination from the local office of the Natural Resources Conservation Service, prior to starting work. Placement of dredged or fill material within waters of the US and/or wetlands without a Department of the Army permit may constitute a violation of Section 301 of the Clean Water Act (33 USC § 1311). If you have any questions regarding this determination and/or the Corps regulatory program, please contact Tasha McCormick at 828-271-7980. C. Basis For Determination The site contains wetlands as determined by the USAGE 1987 Wetland Delineation Manual and contains stream channels located on the property that exhibit indicators of ordinary high water mazks. The stream channel on the property is an unnamed tributary to Cane Creek which flows into the French Broad River and ultimately flows to the Atlantic Ocean through the Gulf of Mexico. D. Remarks Site visit conducted on June 11 2010 with Amanda Jones and Tyler Crumbley USAGE and Rebekah Newton with C1earR'ater Environmental Consultants. E. Appeals Information (This information applies only to approved jurisdictional determinations as indicated in B. above) Attached to this verification is an approved jurisdictional determination. If you are not in agreement with that approved jurisdictional determination, you can make an administrative appeal under 33 CFR 33 I. Enclosed you will find a Notification of Appeal Process (NAP) fact sheet and request for appeal (RFA) form. If you request to appeal this determination you must submit a completed RFA form to the following address: District Engineer, Wilmington Regulatory Program Attn: Tasha McCormick, Project Manager 151 Patton Avenue, Room 208 Asheville, North Carolina 28801 In order for an RFA to be accepted by the Corps, the Corps must determine that it is complete; that it meets the criteria for appeal under 33 CFR part 331.5, and that it has been received by the Division Office within 60 days of the date of the NAP. Should you decide to submit an RFA form, it must be received at the above address by September 14, 2009. **It is not necessary to submit an RFA form to the Division Office if you do not object to the determination in this correspondence. Corps Regulatory Official: Issue Date: June 28.2010 Expiration Date: June 28.2015 The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so, please complete the Customer Satisfaction Survey located at our website at http•//regulatory usacesurvey.com/ to complete the survey online. CF: Clearwater Environmental Consultants, Inc., 224 South Grove Sweet, Suite F, Hendersonville, NC 28792 Attention: Rebekah Newton McGill Associates, PA, Consulting Engineers, 55 Broad Street, Asheville, NC 28801, Attention: Harry B. Buckner, PE 2 INV.:2988d)T N as SE TREES P/A FLETCHER FIRE S RESCUE GARY ESGAR ER PIN 9653-70-5223 PIN 9653 0-3552 DB 718 PG 59 = _ DB 1104 G 580 D8 727 PG 691 413 42 2 O DB 777 PG 843,847,659653,858, GAS METER $R0 " N i 0 GAS METER 0 30° RCP; CONNECTION UNABLE f m LIMITS OF GROUND BASED ATO BE DETERMINED e '/ ` RNY MON. FOUND TOPOGRAPHICAL SURVEY ° WM .... ea. FH (AUGUST 2010) _ _ ROW ► 18" CMP ®GO / o GB --.-_ CO DMH Binder of E. oB � 9 FANNING BRIDGE RO '�• ,,� �, MON. F ND 0/ DENSE TREES 0 SR 1358 - AD ` � � .)-�• II � _ � NCDOT RO� t SMH SM9`RCPs ++ate► 1 — / / / �•"`�,� ' SMH -=�'c'o RID PRO SED PUBLIC RIGHT-OF-WAY RBS WW MON. FOUND /-• x ' _ / i RUTLEDGE IRS BOUNDARY LINE !/ s � R(wMON. 0 EXISTING NCDOT INTENAN G -OF-WAY / i' —...,,,, s Remainder of FOUND �® �� / / :® APPEARS TO JRUN WITH THE MIDDLE OF Lot 1 R PIN 9652.79-4919 / sa FT. ®R°`N ® / OLD CANE CR K ROAD PER DD 1564 PG 15 MON. FOUND 5, Lot 2 °� ®` 0.028 Acres 3(4° IPF 1,2314RFq 6 ��p• RO ° Portion of R NORTH CAROLINA Portion of PIN 9652-79.4919 "• BF DEPT. OF TRANSPORTATION PIN 9652-70-2978 NCDOT NCDOT DS 1266 Pg 310 JUDY R. MCFALLS, ET AL •19 O / � , DS 1266 Pg 310 REBECCA M. PRESSLEY PINY R. MCFALL �► j ` / /`� WILLIAM R. MCFALLS DB 1218 PG 708 MARY M. LANNING PIN DS 102 PG 6958 PIN 9653-70-7262 BENJAMIN JOEL YOUNGBLOOD CHARLEEN DENISE YOUNGBLOOD "^--•�. DS 1205 111 712 / 41° 1" CAR AXLE FOUND ON LINE RBF° ! • 6OLD CANE CREEK ARO D WM _� • 7 � ! C ®® N E d) i ®_ V ° / v23 �0 ISTIN NCDOT MAWTENA E RIGHT-OF- EDPUBLIC RIG ° o POSED/ YAROPROP TF FL T P BLI IGHT-OF-W CONCEPTUAL LOCATION \ -4s // % �o C STREAM MITIGATION JJMJ•' �� �' �/ 5� / Ah / F: 211 aU er / (A ,.. o/ 2088.5 ower �l e ` • - ( APPX° LIMITS F 1 YEAR FLOOD PLAIN o— jI 0 1 1 I I I I 441111111111111� I I `S ° . ZONE L O AE e° yC mom ,x STREAM IS PROPOSED TOWN OF FLETCHER PUBLIC IGHT-O -WAY ti —�® 13ERIW DRY IN THIS 0 � sE c AREA EES CIO0 Ce 10 116 q ® WET AREA STREAM EBRIS PILE DENSE TREES , (� P ® - =Co 0 wFT� 40 0 20 40 80 120 s 83 DENSE TREES C - REFERENCES: = / ® - GRAPHIC SCAT F 1 INCH 40 FEET - COMPOSITE TOPOGRAPHICAL AERIAL SURVEY e� � - PREPARED BY MCABEE &ASSOCIATES, PA BEARING DRAWING #G-09-2586, DATED 8-1409. N TANKCABEE ® 0 - - ssoc�,TEsP.A. Know what® Y 0 ® ® ® DENSE TREES PROFESSIONAL LAND SURVEYING I... / - ®®® Eric S. McAbee, PLS . Fax 828) 828-7294 CII fire you dig. f J.BanyWe4el Telephone (828)828-129b ��nwn! Wallace 3. NIFABae, PL3 (Eme�1We) 3 n=bee hail Feivier Nodi, nse N,a, 28730 www, mcebeeeunrey.ccm . Firm Ucense Nun:bar. G894 g N.C. One -Call Center $ Dial 611 or 1-800-6324M NO. DATE BY REVISION DESCRIPTION 'v, Aftw� �v E-IiizI H �J � Ami N NoN_pp U /r--1 Z 0 �ryry til Q r^ o0 !r l W w z T�MS1 on tint O in iin ,•�`0P eoeo NOs''�, :�Qvo°°P� Vo ° ° 0 '% H Q Z V LL! X u LU 0 w J z LL LL z F_ Lim 0 O U Tz �l 0 'Q^ w 3:: W 0 Z W X V_ tY I I c p m a '3M O N m® W; 6 CO ui to M o z m z qq�V ZU zW 0Q0� W M P m 13 W Z III LL ®o ®v00 =� Z CL W F— t!) Z 0 CL SHEET J w a q j J / wv.99oe4 i/\ I I I I I I I / _ \ \ \ \ /n \ \ \ \ \ W ? amapR11. \ \ \ \ I 1 LER' /l N --20W11 ( FLETCHER FIRE & RESCUE / / //i j IGARY Es 11 11111 I 1 / / / //// // I 1 I \IIIf(III 1 PIN 8853-70-5223 I ��ll 1 tPIN 9653 0.35621 \ DB 718 PG 59 �J/ I\\�OB 1104 G680 DB 727 PG 691hSLIDE 42 �% \ \ DB 777 PO 843.847,850,653.656,CWV1\ \ AD / j 1' 'l 111111 / 1 / / 1 /j / / / / / \ \ \ \ \ \ �\ r \ \._ -.---PROPOSED 16'F-D.T.P7ATER �L)D1E' _ _ — - %i' / / /(� \ \ \ EXISTI WATER LINE UST REMAIIGI -SE E AT I:L TIMES Q fill 1/ / / / / / / / / / / / ® \ \ We\ \\\\ PROPOS 1lAI6B"IE F� E MUS�'�E C I�S CTED,,-TESTED, CHLORIA} , AND APPROVED .../\\" \�\\ Y E1Vt iN R'PRIOR TO NNECTIN�G EXISTING WATER SY$T M — _ - _ 00 �, GAS METER \ \ -- - \ / 1 111 I / 1 / I l ! Il / ! / / / / / / // / / \ \ 1 \�\ \ - / �- ,/\V\may — ---r , a \\\� - GAS METER III 11 I / l / / // l� } \ 1 \\y \` 1 / / "' — ►�. z \,/.�--// Z+ 30" RCP' CONNECTION UNABLE \ / 1 J ® I 11 MH 29 a r / / — /-- —' — \ 1I 1 ^ / 1 111 / / / l ! \ \ //>j >(� m M /� BASED /� n TO BE DETERMINED RNV MON. FOUND \ 1 / I 1 I I , I / / // } ! , // /1 �\�\\ \t( j I IVI ITS ®IF/ V R 0 U_I'D BASE 4J � WM \ ' 1111 /1 l 11 111 / / ! ! /\ \(�\�\\� ` \ / T -.,� ..�.�. FH 11 li\/ /11111 / I / / r/ /� I\ _ / / J I I �\\\\\\��\ \ / / OPOG.RAPHiCAL SupvEY" _ — W 1 1 r 1 / / 1 / / / // / ' I \\\\`�11N&(AUGUST , 010Rte,..I 1 �\j \� . > — --` � -- — `• / - / -- �" -' `- H 18" CMP ® DMH I 1 1 i ! , l 1111 .,�' --�' _ / � / � \ -�` �--/ // / / 11 1''/�%��fl/l}\ /// �/ i cinder of '—`Nup r 115MIF \ / / — — — ►—+ vs VII E. FANNIN B ®�" MON. F UND/ j II l l 1 / J / _ / / / / f %/1f //ll//f — / / / / / / `� ¢q V7 / / / / RIDGE ROAD �-- , / / , , ( / / °.� � - �� � , / iai� � Iii � / / _ �, / o ca v _ / — _ Z SR 1358 - NCDOT � � ®RO�I'+� ~ �-- 1� 1 II I 1 1 / � — / / L / /� / ' / / / / 1 " � � 0 / SM •`" �SMH / / 1. / / �•_"^•+.....-..... 9 RCP �"'^"";'�.,,,- / / .-- .- SMH --- co 1 1 \\ / / / / / / h0'/� / ya — — / \ / PRO S UBLIC�I�HT-OF-W,AY' / / — / �► i�Of — - ' / ►►►►�I111,1 2087. / / / N / / �� /- ROW,�Re,$ R/W MON. FOUND �• 1 , \ / ® / / / / / b� / I I J J �`� P e°o° %,/O / ,--'_ \ \ a ' ��✓//F� / / RBS R[WMON. ( \ \ 1 / EXISTING NCDOT IN NAN G -OF-WAY // i / I I Illi 1 ° .. ! i / // l ' liil Jirl , / RUTLEDG / IRS BOONDARY LINE _ _ ° Lot 1 *+R s Remainder of FOUND �.� I } 1 / / I° / PIN 9652.79.4919 ` 1 I / / / // � y/ i / 11 2086/ //�1 APPEARS TO tRUN/WITH TH fE VIIDDLE OF 0.132 Acres R — - _ N MON. FOUND 5,762 $Q. FT. / - � // / // /o/ // ( OLD CANE CR K ROAD ('PER D64 PG 153- ° .. ° O 0.028 Acres //'0�°° 000e o°°o��`\a�• 314" IPF 1,231 SQ. FT. RBS d/(/ oP�O,Qn- / Portion of `Y*s BF Re / ' — / / / / / / I v NORTH CAROLINA Portion of PIN 9652-79-4919 ,► / DEPT. OF TRANSPORTATION / / /1 i % PIN 9652-78-2978 NCDOT / / / / I NCDOT DS 1266 Pg 310 / DB 1266 P 310 JUDY R. M9-5947 , ET AL / I 0 PIN 9652-78.''i847 1. / / / / / _0' -- / t \ REBECCA M. PRESSLEY DB 1218 PG 708// J / / I \ WILLIAM R. MCFALLS ✓ / \ \ MARY M. LANNING +ate 0 / / ' , / % `� / I I I I / / / / /� / % / , ' / / \ PIN 9652 79-1958 ,+• 1 \ \ DB 1102 PG 61 \ \ \ \ \ PIN 985370 7262 2 ` BENJAMIN JOEL YOUNGBLOOD e / / / / I 1 / / / / / / / // /- \ CHARLEENDENISEYOUNGBLOOD \ I DB 1208 PQ 712 / / / ° / /� zo l/ / / / // ////li�l \ 1 CAR AXLE FOUND ON LINE \ ! � " RBF / -v SLD CANE CREE_--- _ _ WM_„_ / / / J / / / / / 20� j� / / /� / // //// _ — — / / N / / CZOAD / .-- _..-. / :•:, . � p 20 PQRQJL / (F;je (\ "C'-- — `�� `9 oma 8 ;s u�a / -/ J2 3.5 / / / / 1�0 1l _ _ _ i/ _ --1 _ _ _ _ ---- — — ----- --�__ )_ J J) �® { Moa 269D. / / / NNETH YQUNGBLa ODOD ` \ O 1 / / r / 1 / / 1 CK / / / f /8. f / RIM EL:2080.8 1 LLJ MH 29263 apprax ( I / INV. OUT EL.: 2073.0 / h I Pw9ss2a93n7 - \/ / / ' ' /C` / /tio / / / // / i \ / / / / Z 1 (I DB 428 POO _ ! / \ / /// �°�'•� � ,, �.-' � /// / ,// / /// \ \.------' �/ / / � LL. 1 99_LL // // ISTINQ NC60i AINT'EN RIGHTldF �/ I I \ ° / / / / / `b� ® " \ \ \ / / — / i / Z ® // PROPOSED PUBLI RIG Y / \ / /LjL PROPOSED 8" D.I.P. WATER LINE / // ROPOSED TOWN OF VLET PUB / I HT -OF -WA \yam `- / y �i1 •o / s-8 as / �— INSTALL BLOW -OFF AT END OF LINE // 2100. \ \ CONCEPTUAL LOCATION ' 0 �-- — — — STBF.,�M MITIGAIIQP+1 Q / �1p 2 (y� , / / 1 \/ / / PROPOSED 6 D.I.P. SEWER SERVICE LINE @ 1 MIN. SLOPE ��. RELOCATION OF ELECTRICAL SERVICE T9 ILR R SING kT / /1 6 / , //,/ / /j/ /�/ / / 1 - o, INSTALL CLEANOUTS MAXy100' SP/ 01- BY 1 — — BY POWER COMPANY // / / / / .a. - v.75.8 �`�"O" � � �-- � ELECTRICAL SERVICE TO GATES TO R IN IN P ON A ALL S / �� t �r/ ,�.,�, yy�� f . U.1 -_/ Inv. 74.8 am// / / /� �° , / — /. S ' --- �+ �+�� S 0— Ifni. 73.9 ' / / ' ` �J �7 - \ / ! 02 _ _ _ _ CO _ ir inY.72.9 t , , / / / � . OyVPr/ // �� Iowa inv f20� / / �� S $ "_--,�_ S -__.-_....._- _ _ / / ' •- .- W 11 D C'> APP LIMITS F� YEAR 6 / / '/ ° Inv. 71.9 / [y: /ate , I Nw MH 29282 approx, l /owl — — — _ — s h _ — — w Nam RIM EL :2077.3 "WW�� / \ t ^ � %// / 1 / / ` ' � l � / / // ��� / Tio �. � ' . - — �,�• — _..- —' � � ---- — .� � -u�v. ZONE AE A PROPOSED TOWN OF FLETCHER PUBLIC IGHT-01-W Y / / / / ( — / i / _ \ fST4EAM IS , , ` — — - , , — — — ' — — - — _ _ , T_ a l ti l r J — sERM �? IN THIS / �� — — c N } a w — 0-9 H C LL z in z 08 W __ ®_= __$RM=I _ m W o Zoo 147 WET-�AREA / 91. I / / / \ \ \ — TREAM �•"' woe.. _,� e = = q N \ - — ^'_ `— = — I 1.0 \ \, - 1 _ _ — — — — — — _ ,,.��r `; -- _ ,PROPOSED 6' CHAIN LINK FENCE / v 8.5 v/20 5 _ Q LU PLAN )CO 0\ 40 o zo 4o so iao / // / /1/ ii/ /� \\\ 1 \ I / \ ? -g tope 82. I / 1111//11 00 Z / / /\\\ \ t I I / \ l / / / l / / \ I \ \ , / / / I f 11 \ \ REFERENCES: / / / \ 2.9 // // - COMPOSITE G GRAPHIC SCALE 1 INCH - 40 FEET / / ® \ r1 j 1 / ) / / / \ TOP- BEE & SS AERIAL SURVEY "rely \ � \ ,..- HO \` \ � I / / � _ — -- � ! // / 1 � � � PBEP-AREB Bit 10fCABEE &ASSOCIATES, PA \ \ nNo \ I 1 / — — — 081 ! // / / // / / // 1 BEARING DRAWING #dr08-2588, `n � \ I J .._. / / / / / / / / , DATED 8-1408. TcABEE 4 Know what® Q a socrATEsU P.A. \ �•/ / PROFESBIDNAL-LAND SURVEYING Cal ! before you i � (�� I liar �l //// / / , / / / / 1/1 / / I I 1 f , ' / / 1 / J. 6eNY We&, PLS Telephone (828)628-1295 I/ Eric S. McAbee, PLS Fax (M)ON-1294 I/ \ ' """ _ ` 1 — \ .... . Wallace S Mc/U>ae, PLS lephone t 3 MrAbea Trail Fauv aw Nab' Carolim, 28730 ® • — I / 1/ \\ , \ \ ` } } ( I ( _ v 2074 / / / / l / )1 I l \ \ -� \\ /// / J / / 111 I "'�/ //// / 1• ' \ \ 1 ( / / / / www. mcebeeauivey=fn Firm Ucanae Number. G4804 N.C. One -Call Center ��i / / f / / / — ! �! r��� �,,/ /� \ \ i I I I ► j / N _ _ / , f l / / \ SHEET •1-8001.632494 Dial 811 or / NO. DATE BY REVISION DESCRIPTION