HomeMy WebLinkAbout20151229 Ver 1_Monitoring Report_20210108ANNUAL STREAM MONITORING REPORT
HAECO FACILITY IMPROVEMENTS PROJECT
IS-8A LOCATION
GREENSBORO, NORTH CAROLINA
PREPARED FOR:
PIEDMONT TRIAD INTERNATIONAL AIRPORT
1000-A TED JOHNSON PARKWAY
GREENSBORO, NORTH CAROLINA 27409
PREPARED BY:
PILOT ENVIRONMENTAL, INC.
PO BOX 128
KERNERSVILLE, NORTH CAROLINA 27285
JANUARY 5, 2021
PILOT PROJECT 2207.2
PO Box 128, Kernersville, NC 27285
www.pilotenviro.com
January 5, 2021
Ms. Kimberly Turney
North Carolina Department of Environmental Quality
Division of Energy, Mineral and Land Resources —Land Quality Section
450 W. Hanes Mill Road, Suite 200
Winston-Salem, North Carolina 27105
Reference:HAECO Facility Improvements Project
3rd Annual Stream Monitoring Report
Piedmont Triad International Airport
Greensboro, North Carolina
Pilot Project 2207.2
Dear Ms. Turney:
Pilot Environmental, Inc. (Pilot), on behalf of Piedmont Triad Airport Authority (PTAA),has
completed the post-construction annual stream monitoring report for the unnamed tributary to
Horsepen Creek located downstream of the HAECO project.The monitoring was completed in
accordance with the Monitoring Plan prepared by WK Dickson dated August 30, 2016 and the Letter
of Approval with Modifications,prepared by the North Carolina Division of Energy, Mineral and Land
Resources –Land Quality Section,dated August 31, 2016.The findings from the monitoring events
are enclosed.
If you have questions concerning this report or need additional information, please contact us at
(336)310-4527.
Sincerely,
David S. Brame, PWS B. J. Lineback, CIEC, LEED AP
Senior Project Manager Vice President
cc:Mr. Chuck Kirchner, NCDEQ-DEMLR
Ms. Sue Homewood, NCDEQ-DWR
Mr.Alex Rosser, PTAA
Mr. Richard Darling, Michael Baker International
Annual Stream Monitoring Report
Pilot Project 2207.2
January 5, 2021
3
Background
In accordance with the 401 Water Quality Certification and the HAECO National Pollutant
Discharge Elimination System (NPDES)Construction Stormwater General Permit NCG0100000 for
the onsite development of the HAECO Facility Improvements Project, visual and analytical
monitoring is required for the unnamed tributary to Horsepen Creek located downstream of the
project.The specific requirements as outlined by the 401 Water Quality Certification and the
HAECO NPDES Construction Stormwater General Permit NCG0100000 and subsequent
Monitoring Plan are summarized below.If monitoring results indicate that the tributary is
unstable, then the Piedmont Triad Airport Authority (PTAA)shall conduct an analysis of the cause
and propose a resolution to the North Carolina Department of Environmental Quality (NCDEQ)
Division.
401 Water Quality Certification Conditions
Conditions 5, 6,and 7 of the 401 Water Quality Certification (included below)shall be followed
for up to seven years following construction to satisfy monitoring requirements.However, if after
three years of monitoring or two documented bankfull events (whichever occurs first)the site
demonstrates that there are no significant stream stability concerns, then the monitoring of the
site will be terminated.
5. In-stream analytical monitoring shall be performed at stream site ISBA as specified in
the most recent version of NCS00050B issued to the PTAA by the Division of Energy,
Mineral and Land Resources (DEMLR) and correspondence between the PTAA and DEMLR
on March 10, 2016. If monitoring results at ISBA indicate exceedances of Turbidity
benchmark values as identified in NCS00050B,the Division WSRO shall be notified in
writing.
6. Visual monitoring of the unnamed tributary shall be conducted at location ISBA. Pictures
shall be taken of the upstream and downstream bank conditions during each monitoring
event. If visual monitoring indicates that banks of the tributary are exhibiting erosion, the
Division WSRO shall be notified in writing.
7. If monitoring conducted pursuant to Condition #5 or #6 above indicate that the
unnamed tributary is unstable or that the banks of the tributary are unstable, then the
Permittee shall conduct a detailed analysis of the cause and propose a resolution to the
Division WSRO. Upon approval by the Division WSRO, the Permittee shall implement the
resolution accordingly.
Annual Stream Monitoring Report
Pilot Project 2207.2
January 5, 2021
4
HAECO NPDES Construction Stormwater General Permit NCG0100000
A stream monitoring and maintenance plan is required for the section of stream located below
the existing 114” CMP leading to Horsepen Creek.The plan requires all monitoring parameters
and frequencies to be followed.Two permanent cross sections have been established and are
monitored quarterly.In addition, bank pins have been installed in several locations along the
outer bends of meanders.Baseline stream monitoring was conducted prior to diverting water
into the new culvert systems, located upstream of Structure #1.In accordance with the permit,
a repair/stabilization plan shall be submitted for approval if repairs become necessary to
adequately stabilize the stream.Based on the results of the stream monitoring, a
repair/stabilization plan has not been submitted and is not proposed at this time.
Monitoring Observations
Pilot completed the third year of stream monitoring in accordance with the Monitoring Plan
prepared by WK Dickson for the unnamed tributary to Horsepen Creek located downstream of
the HAECO Facility Improvements Project at the Piedmont Triad International Airport in
Greensboro, North Carolina.The approximate location of the stream and monitoring location is
depicted on the attached USGS Topographic Map (Drawing 1).During the 2020 monitoring
period, Pilot conducted quarterly visual monitoring of the stream,bank pins, and crest gauge and
surveyed two fixed cross sections along the stream.The annual results of our findings and
supporting data, including monitoring cross section profiles, monitoring observation
spreadsheet, and photographs,are attached.
Visual Monitoring
Visual monitoring of the project channel was conducted quarterly. Visual assessments of stream
stability included a complete stream walk and channel inspection. Digital images were taken at
fixed representative locations to note any problem areas or areas of concern. Based on the visual
monitoring conducted,we did not observe notable channel aggradation and degradation or bank
erosion.It should be noted that visual evidence of erosion is apparent along the stream banks.
However, similar conditions were evident p rior to completion of the upgradient HAECO project.
The erosion does not appear to be exacerbating.Visually turbid conditions were observed during
the third quarter monitoring event. Pilot evaluated the adjacent Horsepen Creek and other
nearby streams located upgradient of the project drainage area for comparison. These streams
were observed to be equally turbid and therefore conditions are likely attr ibutable to heavy
rainfall that occurred prior to monitoring.Digital images compiled during the four quarterly
monitoring events are included as attachments.
Annual Stream Monitoring Report
Pilot Project 2207.2
January 5, 2021
5
Cross Sections
Two permanent cross sections were installed along the project channel as indicated in the
Monitoring Plan. The cross sections are surveyed during the annual monitoring events. Based on
the results of the cross section surveys,we did not identify significant changes that could indicate
a change in bank stability for Cross Section 1 or Cross Section 2.The results of the annual survey
events are depicted on Drawing 2.
Bank Pin Arrays
Bank pin arrays are used as a supplemental method to monitor erosion on selected meander
bends and other locations where there is not a cross section. Bank pin arrays were installed along
the outer bends of the meanders. Bank pins were installed just above the water surface and every
1.5 to two feet above the lowest pin. Bank pin exposure was recorded at each monitoring event,
and the exposed pins were driven flush with the bank.Based on the quarterly monitoring of the
bank pin arrays, significant changes that could indicate a change in bank stability were not
identified. The results of the quarterly survey events are included as an attachment.
Crest Gauge
The crest gauge was checked during each monitoring event. The stage recorded by the crest
gauge was measured and logged. If any debris lines or watermarks were observed, photos were
taken to document the features. There were no readings recorded by the crest gauge nor
watermarks or debris wrack lines observed during the quarterly monitoring events.
Annual Stream Monitoring Report
Pilot Project 2207.2
January 5, 2021
6
Conclusions and Opinions
Based on our findings during the quarterly monitoring events conducted for the unnamed
tributary to Horsepen Creek,we did not identify significant changes to the stream as measured
by the applicable parameters that could indicate a change in stream stability. It is our opinion
that responsive action to changes in bank stability is not warranted at this time .Three years of
monitoring have been conducted in accordance with the 401 Water Quality Certification ,the
HAECO NPDES Construction Stormwater General Permit NCG0100000 ,and subsequent
Monitoring Plan.Considering that three years of monitoring have demonstrated there are no
significant stream stability concerns,we recommend the monitoring of the site be terminated .If
the NCDEQ deems continuation of the stream monitoring necessary, we request notification
from your office prior to the first quarterly monitoring event of the fourth year of stream
monitoring.
Attachments:Drawing 1 –USGS Topographic Map
Drawing 2 –Wetland Map (including Monitoring Cross Section Profiles)
Monitoring Observation Spreadsheet
Photographs
SITE
USGS Topographic Map
HAECO Facility Improvements Project
Post Construction Stream Monitoring
Piedmont Triad International Airport
Greensboro, Guilford County, NC
Pilot Project 2207.2
Drawing 1
USGS Topographic Map
Guilford, NC Quadrangle
Scale: 1” = 2,000’
LEGEND
Site Boundary
Wetland Map
HAECO Facility Improvements Project
Post Construction Stream Monitoring
Piedmont Triad International Airport
Greensboro, Guilford County, NC
Pilot Project 2207.2
Drawing 2
Aerial Imagery from ESRI
and Pilot Field Notes
Scale: 1” = 50’
Date: 1.4.21
4
5
1
2 3
Legend
!>Crest Guage
!(Bank_Pins
Culvert/Apron
Cross Section 1
Cross Section 2
Stream
Crest Gauge
Bank Pins
Culvert/Apron
Cross Section 1
Cross Section 2
Stream
815
820
825
0.00 5.00 10.00 15.00 20.00 25.00 30.00Elevation (Ft)Station (Ft)
Cross-Section 2 Profile
Post Construction
Year 1 Post Construction (2018)
Year 2 Post Construction (2019)
Year 3 Post Construction (2020)
815
820
825
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00Elevation (Ft)Station (Ft)
Cross-Section 1 Profile
Post Construction
Year 1 Post Construction (2018)
Year 2 Post Construction (2019)
Year 3 Post Construction (2020)
HAECO Facility Improvements Project
Stream Monitoring Data History - Post Construction
See Monitoring Plan 8/31/2016 for monitoring requirements
Date Pin 1 Pin 2 Pin 3 Pin 4 Pin 5
Q1 1.24.18 0 1 0 0 0 No observed issues No observed issues No reading
Q2 4.27.18 0 1.5 1 0 1.5 No observed issues No observed issues No reading
Q3 7.12.18 0 1 0 1.5 0 No observed issues No observed issues No reading
Q4 11.26.18 0 2 2 2 0 No observed issues No observed issues No reading
Q1 2.7.19 0 0 0 0 0 No observed issues No observed issues No reading
Q2 4.23.19 0 0.5 0 0 0 No observed issues No observed issues No reading
Q3 7.31.19 0 0 1 3 0 No observed issues No observed issues No reading
Q4 11.19.19 0 0 0.5 3 0 No observed issues No observed issues No reading
Q1 2.14.20 0 0 0 0 0 No observed issues No observed issues No reading
Q2 5.1.20 0 0 0 0.25 0 No observed issues No observed issues No reading
Q3 7.20.20 0 0 0 0.25 0 No observed issues No observed issues No reading
Q4 12.17.20 0.25 0.5 0 2 5 No observed issues No observed issues No reading
Bank Pins Array, Observed erosion reported in inches Visual Monitoring
Notable observations
Cross Sections
Notable Observations
Crest Gauge
Recorded Stage Measurement
Photo 1 –Cross section 1, right bank facing left bank
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 2 –Cross section 1, left bank facing right bank
Photo 3 –Cross section 1, view facing downstream
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 4 –Cross section 1, view facing upstream
Photo 5 –Cross section 2, right bank facing left bank
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 6 –Cross section 2, left bank facing right bank
Photo 7 –Cross section 2, view facing downstream
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 8 –Cross section 2, view facing upstream
Photo 9 –View facing downstream from culvert apron
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 10 –Bank pin 1
Photo 11 –Bank pin 2
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 12 –Bank pin 3
Photo 13 –Bank pin 4
Q2
Q2
Q3
Q3
Q4
Q4
Q1
Q1
Photo 14 –Bank pin 5