HomeMy WebLinkAbout040030_30 Day POA_20210104PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 4-30 County: Anson Facility Name: Fox Ridge AWA Certified Operator Name: Eric Ferrell Operator Number: 17634 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Lagoon Name/113: FIR NIFin FIR Sow Spillway(Y or N): N Y Level(inches): 14 19 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste to be pumped and hauled is reflected in section 111 tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation "if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: 3/8/2010 I hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the hest of my knowledge and ability, the information is accurate and correct, Murphy Brown, LLC Facility Owner/Manager (print) Facility OwnerlManager (signature) Phone: 910-293--3434 Date: 1/412021 II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 Y HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: Fox Ridge Nur/Fin line m = 2. Structure ID: Fox Ridge Sow line m = 1203.9 3. Structure ID: line m = 4. Structure ID: line m = 5. Structure ID: line m = 6. Structure ID: line m = n.lines 1+2+3+4+5+6= 1203.9 III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAM PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 o. tract # p. field # q. crop r. acres s. remaining IRR- 2 PAN balance (lb/acre) t. TOTAL PAN BALANCE FOR FIELD (Ibs.) column r x s FR Tract H01 Fescue Hay 4.82 162.59 783.7 FR Tract H02 Fescue Hay 3.58 163.40 585.0 FR Tract H05 Fescue Hay 6.19 162.77 1007.5 'State current crop ending application date or next crop application beginning date for availablf receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 2376.2 IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line In from section Il) = 1203.9 PoA (30 Day) 2121/00 x. Crop's remaining PAN balance (line v from section III) = 2376.2 y. Overall PAN balance (w - x) _ -1172 Line y must show as a deficit. If line y does not show as a deficit, list course of action here incl haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalcul� on new information. If new fields are to be included as an option for lowering lagoon level, add PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to facility, provide information regarding the herd population and lagoon freeboard levels at the re PoA (30 Day) 2121100 PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): I Fox Ridge Sow 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker 19.0 b. designed 25 yr./24 hr. storm & structural freeboard 19.8 c. line b - line a (inches in red zone) = 0.8 d. top of dike surface area according to design (area at below structural freeboard elevation) 246445 e. line c/12 x line d x 7.48 gallons/W 122894 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 1 180 g. volume of waste produced according to structural design 1 380670 h. current herd # 3600 certified herd #1 3600 actual waste produced = current herd # x line g = 380670 certified herd # i. volume of wash water according to structural design 0 j. excess rainfall over evaporation according to design 143760 k. (lines h + i + j) x 7.48 x 30 days/line f= 653789 4. Total PAN to be land applied during draw down period 1. current waste analysis dated 1 12/16/2 1 1.55 m. ((lines e + k)/1000) x line I = 1203.9 REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2121/00