Loading...
HomeMy WebLinkAbout090088_30 Day POA_20210104PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 9-88 County: Bladen Facility Name: Farm #15, 16, and 23 Certified Operator Name: Johnny Cain Jr. Operator Number: 987304 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon Name/ID Spillway(Y or N): Level(inches): Lagoon Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Farm 15 Farm 16 Farm 23 N 29 19 19 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Flans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP_ Operation will be partially or fully depopulated. Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: as conditions permit I hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Murphy Brown LLC Phone: 910-293-3434 Facility Owner/Manager (print) C I -I L C Date: Facility Owner/Manager (signature) 1 /412021 II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: Farm 15 line m = lb PAN 2. Structure ID: Farm 16 line m = 417.7 lb PAN 3. Structure ID: Farm 23 line m = 460.3 lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6, Structure ID: line m = lb PAN n.lines 1+2+3+4+5+6= 878.1lbPAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD. o. tract # p. field # q. crop r. acres s. remaining IRR- 2 PAN balance (lb/acre) t. TOTAL PAN BALANCE FOR FIELD (lbs.) column r x s u. application window' 20 Overseed 31.41 39.37 1236.6 Sept -April 21 Overseed 8.26 41.24 340.6 Sept -April 22 Overseed 8.49 41.24 350.1 Sept -April 23 Overseed 10.98 39.36 432.2 Sept -April 24 Overseed 11.30 39.36 444.8 Sept -April 25 Overseed 11.26 39.36 443.2 Sept -April 26 Overseed 11.26 39.36 443.2 Sept -April 27 Overseed 11.13 39.36 438.1 Sept -April 'State current crop ending application date or next crop application beginning date for available receiving crops during 30 day draw down period. x. Crop's remaining PAN balance (line v from section III) = 4128.8 lb. PAN y. Overall PAN balance (w - x) _ -3251 lb. PAN Line y must show as a deficit. 1f line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information_ If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Irrigation onto existing spray fields will continue as weather and field conditions permit. Additional land is ava for pumping if needed. PoA (30 Day) 2/21100 PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/identifier (ID): I Farm 16 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker b. designed 25 yr.124 hr. storm & structural freeboard c. line b - line a (inches in red zone) = d, top of dike surface area according to design (area at below structural freeboard elevation) e. line c112 x line d x 7.48 gallonslft3 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design g. volume of waste produced according to structural design h. current herd # 5600 certified herd # 5600 actual waste produced = current herd ## x line g = ertified herd # volume of wash water according to structural design excess rainfall over evaporatio . according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 1 12/17/2020 m_ ((lines e + k)11000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) 19.0 inches 192 inches 02 inches 34935 Ift2 5226 gallons 180 days 168000 ft3 168000 fta ® ft3 20379 ft3 234846 gallons 1.74 Ibs11000 gal. 417.7 lbs. PAN PoA (50159402"0 PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): F Farm 23 2. Current liquid volume in 25 yr.124 hr. storm storage & structural freeboard a. current liquid level according to marker 19.0 inches b. designed 25 yr.124 hr. storm & structural freeboard 19.$ inches c. line b - line a (inches in red zone) = 0.8 inches d. top of dike surface area according to design (area at below structural freeboard elevation) 168100 ft2 e. line c112 x line d x 7.48 gallonslft3 83826 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design I 180 days g. volume of waste produced according to structural design I 211483 ft3 h. current herd # 2000 certified herd #1 2000 actual waste produced = current herd # x line g = certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 1 12/17/2020 m. ((lines e + k)11000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) 211483 ft3 Offs 98058 ft3 385894 gallons 0.98 Ibs11000 gal_ 460.3 lbs. PAN PoA (30 Day) 2/21/00