June 25, 2020
LETTER OF APPROVAL WITH MODIFICATIONS
Cumberland County Hospital System dba Cape Fear Valley Health System
Michael Nagowski, CEO
163 8 Owen Drive
Fayetteville, NC 28304
RE: Project Name: Cape Fear Valley Health System Academic Center
Acres Approved: 3.06
Project ID: CUMBE-2020-182
County: Cumberland, City: Fayetteville
Address: Melrose Road
River Basin: Cape Fear
Stream Classification: Other
Submitted by: Jeffery Nobles
Date Received by LQS: May 19, 2020
Plan Type: Institutional
Dear Mr. Nagowski:
This office has reviewed the subject erosion and sedimentation control plan. We find the
plan to be acceptable and herebyissue this Letter of Approval. The enclosed Certificate of
Approval must be posted at the job site. This plan shall expire three (3) years following the.
date of approval, if no land disturbing activity has been undertaken, as is required by Title
15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCGO 10000 Construction Stormwater General Permit. This form MUST be submitted and
COC issued prior to the commencement'of any land disturbing activity on the above -named
project. The NOT form may be'accessed at de .nc. ovINCGOL.Please direct questions about
the NOT form to Annette Lucas at Annette.lucas@ncdenr.gov or Paul Clark at
Paul.clark@ncdenr.gov_ After you submit a complete and correct NOT Form, a COC will be
emailed to you within three business days. Initially, DEMLR will not charge a fee for
coverage under the NCG01 permit. However, on or after June 1, 2019, a $100 fee will be
charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh.
North Carolina Department of Environmental' Quality V Division of Energy. Mineral and Lend Resources
E Fayetteville Regional Office 1225 Green Street. Suite 7141 Fayetteville. North Carolina 28301
o.wmn m ��ui o�nnncv ate, /""� 910.433.3300
Title 15A NCAC 4B .0118(a) and the NCG01 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. I I3A-61.1(a) of our right of periodic -
inspection to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate to
meet the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina
General Statute 113A-51 through 66), this office may require revisions to the plan and
implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances
or rules may also apply to this land -disturbing activity. This approval does not supersede
any other permit or approval.
Please note that this approval is based in part on the accuracy of the information
provided in the Financial Responsibility Form, which you provided. You are requested to
file an amended form if there is any change in the information included on the form. This
permit allows for a land -disturbance, as called for on the application plan, not to
exceed the approved acres. Exceeding the acreage will be a violation of this permit and
would require a revised plan and additional application fee. Any addition in impervious
surface, over that already noted on the approved plan, would also require a revised plan
to verify the appropriateness of the erosion control measures and the stormwater retention
measures. (GS 113A-54.1(b)). In addition, it would be helpful if you notify this office of
the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Chris Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Jeffrey Nobles, P. E., Larry King & Associates, P. A. --- electronic copy
Michael Bailey, City of Fayetteville Permit Office — electronic copy
I' Fayetteville Regional Office.
Project Name: Bojangles' Restaurant
Date: June 25, 2020
Project ID: CUNME-2020-182
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
1. Label the construction entrances and include their installation in the Construction Sequence.
2. On Sheets C-05 and C-06 remove the note about installing groundcover within 21 calendar days
because the construction stormwater requirements are more stringent, requiring groundcover in 7
or 14 days.
3. Include a note on the erosion control plan about the self -inspection requirements.