December 8, 2020
LETTER OF APPROVAL
DR Horton, Inc.
ATTN: Jessica Meyer, NPDES Technical Compliance Administrator
2000 Aerial Center Parkway, Suite l 10A
Morrisville, NC 27560
RE: Project Name: Lafayette Meadows Subdivision
Acres Approved: 3.66
Project ID: HARNE-2020-038
County: Harnett
City: Hectors Creek Township
Address: Baptist Grove Road
River Basin: Cape Fear
Stream Classification: HQW
Submitted by: DR Horton, Inc. 1 The Curry Engineering Group, PLLC
Date Received by LQS: December 8, 2020
Plan Type: REVISED - Residential
Dear Ms. Meyer:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be acceptable and hereby
issue this Letter of Approval. The enclosed Certificate of Approval must be posted at the job site. This plan shall expire
three (3) years following the date of approval, if no land. disturbing activity has been undertaken, as required by Title 15A
NCAC 4B.0.129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent (NOI)
form requesting a Certificate of Coverage (COC) under the NCG010000 Construction Stormwater General Permit. This
form MUST be submitted and COC issued prior to the commencement of any land disturbing activity on the above -named
project. The NOI form may be accessed at de .nc. govNCGO1. Please direct questions about the NOI form to Annette
Lucas at Annette, lucas nedenr. ov or Paul Clark at :Paul..clark ncdenr. ov. After you submit a complete and correct NOI
Form, a COC will be emailed to you within three business days. A $100 fee will be charged annually until a Notice of
Termination is issued. This fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh. If the
owner/operator of this project changes in the future, the new responsible party is required to apply for his/her own
COC.
North Carolina Department of Environmental Quality I lXvialon of Energy, mineral and Land Resources
zf:��A.E . . . Fayetteville Regional office 1 225 Green Street, Suite 7141 Fayetteville, North Carolina 282L01
nwP ' vt_ . —" 910,433.3300
Letter of Approval
DR Horton, Inc.
December 8, 2020
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on file at the job
site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO 1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
This letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to ensure compliance with the
approved plan.
Title 15A NCAC 4B .0118(a) requires that a copy of the approved erosion control plan be on file at the job site.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to ensure
compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of existing natural
resources and adjoining properties. If, following the commencement of this project, it is determined that the erosion and
sedimentation control plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North
Carolina General Statute 113A-51 through 66), this office may require revisions to the plan and implementation of the
revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality laws,
regulations, and rules. In addition, local city or county ordinances or rules may also apply to this land -disturbing activity.
This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial Responsibility
Form, which you provided. You are requested to file an amended form if there is any change in the information included on
the form. This permit allows for a land -disturbance, as called for on the application plan; not to exceed the approved acres.
Exceeding the acreage will be a violation of this permit and would require a revised plan and additional application fee. In
addition, it would be helpful if you notify this office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
irnothy L. 4unty, PE
Regional Engineer
DEMLR
Enclosures: Certificate of Approval
NPDES NCGO1 Fact Sheet
cc: The Curry Engineering Group, PLLC (via email)
Landon Chandler, Harnett County (via email)
Fayetteville Regional Office — DEMLR file