HomeMy WebLinkAboutSWA000085_Summerhaven West Phase1 and 2 Construction Sequence_20201221Summerhaven West Phase1 and 2 Construction Sequence:
1. Obtain Post Construction Stormwater Permit for Summerhaven West Phase 1.
2. Obtain Grading and Erosion Control Permit for Summerhaven West Phase 1.
3. Construct Summerhaven West Phase 1 Lots and Roads.
4. After Phase 1 is completed. Apply for the final permit and send Asābuilt plans for review.
5. Once final permit is obtained, apply for the Post Construction Stormwater Permit for Phase 2.