HomeMy WebLinkAboutNCC205860_ESC Approval Submitted_20201222ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
BRJAN WRENN
DIrector
NORTH CAROLINA
Environmental Quality
November 20, 2020
LETTER OF APPROVAL
Duke Energy
Joseph Barbee, Project Manager
4720 Piedmont Row Drive
Charlotte, NC 28210
RE: Project Name: Line 75 MAOP Replacement
Acres Approved: 4.1
Project ID: ANSON-2021-003.
County: Anson, City: Wadesboro
Address: Yadkin-PeeDee
River Basin: Cape Fear
Stream Classification: Other
Submitted by: Matthew Daniels
Date Received by LQS: November 3, 2020
Plan Type: Utility
Dear Mr. Barbee:
This office has reviewed the subject erosion and sedimentation control plan. We find the
plan to be acceptable and herebyissue this Letter of Approval. The enclosed Certificate of
Approval must be posted at the job site. This plan shall expire three (3) years following the
date of approval, if no land disturbing activity has been undertaken, as is required by Title
15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCG010000 Construction Stormwater General Permit. This form MUST be submitted and
COC issued prior to the commencement of any land disturbing activity on the above -named
project. The NOI form may be accessed at deg.nc.gov/NCGO1. Please direct questions about
the NOI form to Annette Lucas at Annette. lucasgncdenr.-go v or Paul Clark at
Paul. clarkgncdenr.gov. After you submit a complete and correct NOI Form, a COC will be
emailed to you within three business days. Initially, DEMLR will not charge a fee for
coverage under the NCGO1 permit. However, on or after June 1, 2019, a $100 fee will be
charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh.
,�Dff North Carolina Department of Environmental Quality 1 Division of Energy. Mineral and Land Resources
Q> Fayetteville Regional Office 1 225 Green Sheet. Suite 7141 Fayetteville. North Carolina 28301
MCAr.-I CM'R.iNA
aewnmem a Fnv rvmrenw a�nh 910.433.3300
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO 1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. I I3A-61.1(a) of our right of periodic
inspection to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate to
meet the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina
General Statute I I3A-51 through 66), this office may require revisions to the plan and
implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances
or rules may also apply to this land -disturbing activity. This approval does not supersede
any other permit or approval.
Please note that this approval is based in part on the accuracy of the information
provided in the Financial Responsibility Form, which you provided. You are requested to
file an amended form if there is any change in the information included on the form. This
permit allows for a land -disturbance, as called for on the application plan, not to
exceed the approved acres. Exceeding the acreage will be a violation of this permit and
would require a revised plan and additional application fee. Any addition in impervious
surface, over that already noted on the approved plan, would also require a revised plan
to verify the appropriateness of the erosion control measures and the stormwater retention
measures. (GS 11 3A-54. 1 (b)). In addition, it would be helpful if you notify this office of
the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Chris Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Matthew Daniels, Kleinfelder
Marvin Deese, Anson County Inspections Office — electronic copy
Fayetteville Regional Office