HomeMy WebLinkAbout20201062 Ver 1_Mitigation Bank Information_2020121712/16/2020
Robert W. Bugg
Wildlands Holdings III, LLC
Conditions for Transfer of Compensatory Mitigation Credit:
• Once this document has been signed by the Mitigation Sponsor and the USACE is in receipt of the signed form, the
Permittee is no longer responsible for providing the mitigation identified in this form, though the Permittee remains
responsible for any other mitigation requirements stated in the permit conditions.
• Construction within jurisdictional areas authorized by the permit identified on page one of this form can begin only after
the USACE is in receipt of a copy of this document signed by the Sponsor, confirming that the Sponsor has accepted
responsibility for providing the mitigation requirements listed herein. For authorized impacts conducted by the North
Carolina Department of Transportation (NCDOT), construction within jurisdictional areas may proceed upon permit
issuance; however, a copy of this form signed by the Sponsor must be provided to the USACE within 30 days of permit
issuance. NCDOT remains fully responsible for the mitigation until the USACE has received this form, confirming that the
Sponsor has accepted responsibility for providing the mitigation requirements listed herein.
• Signed copies of this document must be retained by the Permittee, Mitigation Sponsor, and in the USACE administrative
records for both the permit and the Bank/ILF Instrument. It is the Permittee's responsibility to ensure that the USACE
Project Manager (address below) is provided with a signed copy of this form.
• If changes are proposed to the type, amount, or location of mitigation after this form has been signed and returned to
the USACE, the Sponsor must obtain case -by -case approval from the USACE Project Manager and/or North Carolina
Interagency Review Team (NCIRT). If approved, higher mitigation ratios may be applied, as per current District guidance
and a new version of this form must be completed and included in the USACE administrative records for both the permit
and the Bank/ILF Instrument.
Comments/Additional Conditions: A letter from Wildlands Holdings III, LLC, confirming they are willing and able to accept
the applicant's compensatory mitigation responsibility, dated 8/14/2020 was included with the preconstruction
notification.
This form is not valid unless signed below by the USACE Project Manager and by the Mitigation Sponsor on Page 1. Once
signed, the Sponsor should provide copies of this form along with an updated bank ledger to:1) the Permittee, 2) the USACE
Project Manager at the address below, and 3) the Wilmington District Mitigation Office, Attn: Todd Tugwell, 11405 Falls
of Neuse Road, Wake Forest, NC27587 (email: todd. tugwell@usace. army. mil). Questions regarding this form or any of the
permit conditions may be directed to the USACE Project Manager below.
USACE Project Manager: Christopher Hopper
USACE Field Office: Raleigh Regulatory Office
US Army Corps of Engineers
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Email: christopher.d.hopper@usace.army.mil
Digitally signed by
HOPPER.CHRISTOP HOPPER.CHRISTOPHER.D.1194
375979
HER.D.1 194375979 Date: 2020.12.0413:49:53
-05'00'
USACE Project Manager Signature
10/21/2020
Date of Signature
Current Wilmington District mitigation guidance, including information on mitigation ratios, functional assessments, and
mitigation bank location and availability, and credit classifications (including stream temperature and wetland groupings) is
available at http://ribits.usace.army.miI