HomeMy WebLinkAbout20100790 Ver 1_Time Ext Request_20101021DEPARTMENT OF PUBLIC UTILITIES
POST OFFICE BOX 2263
SMITHFIELD, N.C. 27577
(919) 989-5075 D
OCr2 w
October 18, 2010 412A4 0s 1tA! a ?O?p
Mr. Ian McMillan ?sRe
NCDENR 401 Oversight/Express Review Unit
1650 Mail Service Center
Raleigh, NC 27699-1650
Re: E. Clayton Industrial Area Water Transmission Improvements
Request for More Information
DWQ Project #10-0790
Dear Mr. McMillan:
In regards to your letter dated September 28, 2010 for the above referenced project,
Johnston County requests a 45 day extension to provide the additional information. The
owner of one of the parcels that would have been impacted by the proposed route has.
asked the county to reconsider the alignment of the water transmission line. We are
currently redesigning a portion of the proposed project in an attempt to satisfy the request
of the property owner. As a result of the new proposed alignment, buffer, stream, and
wetland impacts may change.
Thank you for considering the request for a 45 day extension.
Sincerely,
Jamie Guerrero, PE
Stormwater Administrator
Cc: USACE Raleigh Regulatory Field Office