Loading...
HomeMy WebLinkAbout820101_Plan of Action (POA)_20200620 PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 6/20/2020 1. Structure Name/Identifier(ID): Rose Swine Farm#1 (82-101) 2. Current liquid volume in 25 yr./24 hr. storm storage&structural freeboard a. current liquid level according to marker 12.0 inches b. designed 25 yr./24 hr. storm &structural freeboard 19.0 inches c. line b-line a(inches in red zone)= 7.0 inches d. top of dike surface area according to design 66850 ft2 e. line c/12 x line d x 7.48 gallons/ft3 291689 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 81754 ft3 h. current herd# 2480 . certified herd# 2480 actual waste produced = current herd# x line g = 81754'ft3 certified herd# i. volume of wash water according to structural design 0 ft3 j. excess rainfall over evaporation according to design 38996 ft3 k. (lines h +i+j)x 7.48 x 30 days/line f= 150535 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 12/18/2019 2.46 lbs/1000 gal. m. ((lines e+k)/1000)x line I = 1087.9 lbs. PAN REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) Structure 1 Rose Swine Farm (PoA30day) 6-20-2020 Page 1 of 1 PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 6/20/2020 1. Structure Name/Identifier(ID): Rose Swine Farm#2 (82-101) 2. Current liquid volume in 25 yr./24 hr. storm storage&structural freeboard a. current liquid level according to marker 13.0 inches b. designed 25 yr./24 hr. storm &structural freeboard r 19.0 inches c. line b-line a (inches in red zone)= 6.0 inches d. top of dike surface area according to design 88356 ft2 e. line c/12 x line d x 7.48 gallons/ft3 330451 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 121321.9 ft3 h. current herd# 3680 certified herd# 3680 actual waste produced = current herd# x line g = 121322 ft3 certified herd# i. volume of wash water according to structural design 0 ft3 j. excess rainfall over evaporation according to design 53812.5 ft3 k. (lines h+i+j)x 7.48 x 30 days/line f= 218334 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 12/18/2019 2.85 lbs/1000 gal. m. ((lines e+k)/1000)x line I= 1564.0 lbs. PAN REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) Structure 2 Rose Swine Farm (PoA30day)6-20-2020 - Page 1 of 1 II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24 HR.STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: Rose Swine Farm#1 (82-101) line m = 1087.9 lb PAN 2. Structure ID: Rose Swine Farm#2(82-101) line m = 1564.0 lb PAN 3. Structure ID: line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structure ID: line m = n. = 1 +2 +3+4+5+6 2651.9 III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD. o.tract# p.field# q. crop r. acres s.remaining IRR-t.TOTAL PAN u.application window' 2 PAN balance . BALANCE FOR (lb/acre) FIELD(lbs.) column r x s 11308 F1 Bermuda Hay, 13.96 160.00 2233.6 3/1 -3/31 11308 F2 Bermuda Hay 7.99 111.00 886.9 3/1 -3/31 11325 F1 Bermuda Hay 0.80 150.00 120.0 3/1 -3/31____ 11325 F2 Bermuda Hay 5.06 150.00 759.0 3/1 -3/31 11325 F3 , Bermuda Hay 2.91 150.00 436.5 3/1 -3/31 1263 F1 Bermuda Hay 12.47 135.00 1683.5 3/1 -3/31 3722 F2 Bermuda Hay 2.33 100.00 233.0 3/1 -3/31 3722 F1 Bermuda Hay 1.39 100.00 139.0 3/1 -3/31 3722 F2 Bermuda Hay 3.76 135.00 507.6 3/1 -3/31 'State current crop ending application date or next crop application beginning date for available receiving crops during 30 day draw down period. v.Total PAN available for all fields (sum of column t)= 6999.0 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II)= 2651.9 lb. PAN x. Crop's remaining PAN balance(line v from section III)= 6999.0 lb. PAN y. Overall PAN balance(w-x)= -4347 lb. PAN SUMMARY Rose Swine Farm (PoA30day)6-20-2020 Page 1 of 2 Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump& haul and herd reduction options, recalculate new PAN based on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. NARRATIVE: 1 • SUMMARY Rose Swine Farm (PoA30day)6-20-2020 Page 2 of 2