HomeMy WebLinkAbout20201728 Ver 1_PreFiling Acknowledgement Email_20201207Strickland, Bev
From: laserfiche@ncdenr.gov
Sent: Monday, December 7, 2020 3:57 PM
To: jonathan.herman@mcgillassociates.com
Cc: Goss, Stephanie
Subject: Pre -Filing Meeting Request Acknowledgement - Pine Level Sewer Force Main
Replacement - 20201728 Ver 1
Attachments: DWR Pre -Filing Meeting Request Form.pdf
The North Carolina Division of Water Resources has received the Pre -Filing Meeting Request Form for Pine Level Sewer Force Main
Replacement that you submitted on 11/11/2020. The ID number for that project is 20201728, Version 1.
Reviewer Contact Information:
Reviewer: Stephanie Goss
Email: stephanie.goss@ncdenr.gov
Reviewing Office: Raleigh Regional Office - (919) 791-4200
You will either be contacted by staff to set up a meeting or notified by email that the 30 calendar day clock has been reached and you
are allowed to submit your application.
This email was automatically generated by Laserfiche workflow. Please do not respond to this email address, as responses are not
monitored.
ID#* 20201728 Version* 1
Regional Office* Raleigh Regional Office - (919) 791-4200
Reviewer List* Stephanie Goss
Pre -Filing Meeting Request submitted 11/11/2020
Contact Name * Jonathan Herman
Contact Email Address* jonathan.herman@mcgillassociates.com
Project Name* Pine Level Sewer Force Main Replacement
Project Owner* Johnston County Government
Project County* Johnston
Owner Address: Street Address
P.O. Box 1049
Address Line 2
aty
State / Province / Region
Smithfield
North Carolina
Fbstal / Zip Code
Country
27577
United States
Is this a transportation project?* r Yes r No
Type(s) of approval sought from the DWR:
W 401 Water Quality Certification - F- 401 Water Quality Certification -
Regular Express
r- Individual Permit r- Modification
r- Shoreline Stabilization
Does this project have an existing project ID#?*
r Yes r No
Do you know the name of the staff member you would like to request a meeting with?
Please give a brief project description below. *
The Johnston County — Pine Level Sewer Force Main Replacement project
proposes approximately 20,300 linear feet of new force main sewer line
from the existing Pine Level pump station on North Peedin Ave, following an
existing gravity sewer line, and ultimately discharging into an existing
manhole adjacent to Outlet Center Dr. This will increase the capacity of the
sanitary sewer collection system for Pine Level allowing for the town to
grow further in the future as they are nearing their Flow capacity. The
project is located within the municipal and extra -territorial limits of the Town
of Pine Level and Johnston County with some minor cut through of
properties within the Town of Selma Most of the lines will be installed
adjacent to existing roads with some being installed cross country following
the existing gravity sewer. Most locations where there are existing streams
and wetlands there are proposed bore with encasement pipes and
horizontal directional drill to avoid those conflicts. In two incidences open
cut with stream bypass is proposed due to the constraints of the existing
conditions. The installation of the force main is expected to disturb a total
of 13.32 acres of soil, primarily in the excavation and stockpiling of dirt
associated with the installation of the proposed force main.
Please give a couple of dates you are available for a meeting.
11 /19/2020
11 /20/2020
Please attach the documentation you would like to have the meeting about.
2020-10-21 - Pine Level FM Final Drawing Set
40.43MB
- ISSUED FOR PERMITS.pdf
pdf only
By digitally signing below, I certify that I have read and understood that per the Federal Clean Water Act Section
401 Certification Rule the following statements:
• This form completes the requirement of the Pre -Filing Meeting Request in the Clean Water Act Section 401 Certification
Rule.
• I understand by signing this form that I cannot submit my application until 30 calendar days after this pre -filing
meeting request.
• I also understand that DWR is not required to respond or grant the meeting request.
Your project's thirty -day clock started upon receipt of this application. You will receive notification regarding meeting location
and time if a meeting is necessary. You will receive notification when the thirty -day clock has expired, and you can submit an
application.
Signature
C11 1111Y411PkIl � tpwc?w
Submittal Date 11/11/2020