HomeMy WebLinkAbout20071384 Ver 1_Time Ext Request_20100914FW: Bath Branch - Request for Permit Extension Page I of 1
FW: Bath Branch - Request for Permit Extension
Homewood, Sue
Sent: Tuesday, September 14, 2010 12:29 PM
To: Dennison, Laurie; Strickland, Bev
Attachments: Request for Permit Extensi-l.doc (29 KB)
For file 07-1384
Sue Homewood
NC DENR Winston-Salem Regional Office
Division of Water Quality
585 Waughtown Street
Winston-Salem, NC 27107
Voice: (336) 771-4964
FAX: (336) 771-4630
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and
may be disclosed to third parties.
From: clearcreeks@zoominternet.net [mailto:clearcreeks@zoominternet.net]
Sent: Tuesday, September 07, 2010 4:17 PM
To: John.t.thomas.jr@saw02.usace.army.mi
Cc: Sue.homewood@ncmail.net; keithhl@cityofws.org; canderson@pilotviewrcd.org; cdnolan@wfubmc.edu
Subject: Bath Branch - Request for Permit Extension
John,
Per our phone conversation I'm attaching the request for extension. I'll follow up with a hard copy by
US postage.
Rocky
https://mail.nc.gov/owa/?ae=Item&t=IPM.Note&id=RgAAAAAAOgPoLNIPQZ06vHVR... 9/15/2010
September 7, 2010
Mr. John Thomas
U.S. Army Corps of Engineers
Raleigh Regulatory Field Office
3331 Heritage Trade Drive
Suite 105
Wake Forest, North Carolina 27587
Re: Bath Branch Stream Valley Restoration Project
Action ID: SAW 2007 02448 234 Forsyth
Dear Mr. Thomas:
As you know, the Bath Branch project involves a number of project components
including stream channel and valley restoration, three regional stormwater management
facilities, and repair/relocation of associated utilities. Most of our state and federal
permits were approved in late 2007. However, the North Carolina Department of
Environment and Natural Resources (NCDENR), Division of Land Resources, Dam
Safety Section withheld approval for the proposed Central District SWM Pond due to
concerns raised by the North Carolina Department of Transportation (NCDOT).
In particular, NCDOT was concerned about the embankment for the proposed Central
District SWM Pond encroaching on their rights-of-way along Route 52 and U.S.
Business Route 40. We have spent the last couple of years diligently working on a
redesign for the Central District SWM Pond that will address NCDOT's concerns while
still meeting the original objectives for the project as outlined by the Piedmont Triad
Research Park and the City of Winston-Salem.
The redesign is now complete and we anticipate final approval shortly. It is our intention
to submit the revised plans to you for your review and files. However, due to the
significant delay, we are concerned that our original Nationwide and WQ permits will
expire prior to the actual start of construction. There will be no additional impacts to
Waters of the U.S associated with the plan revisions. Therefore, we are here in
requesting an extension of our permits.
Page 2
Mr. John Thomas
September 7, 2010
If you have any questions or require additional information, you may contact me at my
office. We appreciate the assistance you have provided on this project.