HomeMy WebLinkAbout20201692 Ver 1_PreFiling Email 30-Day Clock Reached Email_20201206Strickland, Bev
From: laserfiche@ncdenr.gov
Sent: Sunday, December 6, 2020 12:00 AM
To: mkirby200@comcast.net
Cc: Mairs, Robb L
Subject: Pre -Filing Time Clock has been reached for Oyster Harbour Boat Ramp Replacement
Permit Application - 20201692 Ver 1
Attachments: DWR Pre -Filing Meeting Request Form.pdf
The North Carolina Division of Water Resources has received the Pre -Filing Meeting Request Form for Oyster Harbour
Boat Ramp Replacement Permit Application that you submitted on 11/5/2020. The ID number for that project is
20201692, Version 1.
Your Pre -Filing Meeting Request has now reached the 30 calendar days' requirement and your application can now be
accepted.
When you submit your application please upload a copy of the attached document in this email.
This email was automatically generated by Laserfiche workflow. Please do not respond to this email address, as
responses are not monitored.
ID#* 20201692 Version* 1
Regional Office* Wilmington Regional Office - (910) 796-7215
Reviewer List* Robb Mairs
Pre -Filing Meeting Request submitted 11/5/2020
..................................................................................................................................................................................................................................................................................................................................................
Contact Name * Mike Kirby, P.E.
Contact Email Address* mkirby200@comcast.net
Project Name* Oyster Harbour Boat Ramp Replacement Permit Application
Project Owner* Oyster Harbour Homeowners Association, Inc.
Project County* Brunswick
Owner Address: Street Address
2191 Oyster Harbour Parkway
Address Line 2
aty State / Frovince / Region
Supply NC
Rbstal / Zip Code Country
28462 United States
Is this a transportation project?* r Yes r No
Type(s) of approval sought from the DWR:
r- 401 Water Quality Certification - F 401 Water Quality Certification -
Regular Express
W Individual Permit r- Modification
r- Shoreline Stabilization
Does this project have an existing project ID#?*
r Yes r No
Do you know the name of the staff member you would like to request a meeting with?
Robb Mairs
Please give a brief project description below.
The property owner, Oyster Harbour Homeowner's Association, Inc.
(OHHOA) intends to replace the existing private- community elevated boat
ramp. The existing elevated boat ramp has deteriorated over the years to
the point that replacement is needed in the near future in order to ensure
that community residents can safely launch boats for access to navigable
waters for fishing and other recreational purposes.
i ne existing eievatea boat ramp consists or two portions. i ne rirst portion
is constructed of timber support piling, timber pile caps, timber stringers,
and timber decking. It begins at the bulkhead that runs along the edge of
the upland and extends approximately 114 feet in length out towards the
Atlantic Intracoastal Waterway (AIWW). The second portion is constructed
of a cast -in -place concrete slab that is supported on timber piling. The
existing elevated concrete boat ramp begins at the end of the timber boat
ramp (Sta. 1+14) and extends approximately 107 feet; ending at Sta. 2+21.
The entire elevated boat ramp, timber and concrete, is approximately 16-
feet. in width. A 6" x 8" timber curb guard runs along both sides of the
existing boat ramp for the full length. Also, timber guard rails run along both
sides of the elevated boat ramp for approximately the first 143 feet.
In order to construct the new replacement elevated boat ramp, the existing
dilapidated elevated boat ramp will be demolished and disposed offsite.
The new replacement elevated boat ramp will be constructed, in place, to
the same dimensions (length and width), top elevations, and slopes as the
existing structure. The top elevation at the beginning of the new elevated
boat ramp will be at +12.3 feet Mean Low Water (MLW) and the top
elevation at the lower end of the new elevated boat ramp is -5.5 feet MLW;
existing and proposed. The first 114 lineal feet of the new replacement
elevated boat ramp will be constructed with treated timber; same as the
existing timber elevated boat ramp. The new replacement concrete
elevated boat ramp (approximately 107 feet in length) will be constructed of
reinforced concrete slabs supported on reinforced concrete pile caps and
prestressed concrete piles. A temporary steel sheet piling cofferdam will be
installed around the perimeter of the area where the concrete portion of
the elevated boat ramp is located. This will allow water to be pumped out to
provide dry working access to this below -water area during construction.
Additionally, approximately 215 cubic yards of mud will need to be
temporarily excavated from an area of approximately 2,120 square feet
from within the cofferdam. This is necessary so that the lower portion of the
new concrete elevated boat ramp structure can be constructed at the
specified elevations to ensure proper functionality and access during all
tide cycles and water levels. The excavated material will be temporarily
stored on the floating work barge during construction and then will be
replaced back in its original locations after construction of the new concrete
elevated boat ramp is complete. The temporary cofferdam structure will be
removed when construction is complete. Existing adjacent fixed access
decks, gangway ramps, and portions of the floating dock will need to be
temporarily removed to allow access to the work area during construction.
These structures will be replaced back in their original locations once all
boat ramp construction is completed. All demolition and new construction
work will be conducted from the water using one or two floating barges and
other small work floats.
As noted above, the proposed new replacement elevated boat ramp
structure will be constructed in the same location as the existing structure.
The existing elevated boat ramp structure is located within the range of
approximately 2-feet to 14-feet from the eastern riparian property line and
within the range of approximately 69-feet to 80-feet from the western
riparian property line. A riparian property owner waiver will be requested
from the neighbor located on the eastern side of the elevated boat ramp
property to give permission for the new replacement elevated boat ramp
being constructed inside of the 15-feet riparian offset line.
END
Please give a couple of dates you are available for a meeting.
11 /20/2020
12/4/2020
Please attach the documentation you would like to have the meeting about.
Oyster Harbour Boat Ramp P1 - P6.pdf 2.52MB
pdf only
By digitally signing below, I certify that I have read and understood that per the Federal Clean Water Act Section
401 Certification Rule the following statements:
• This form completes the requirement of the Pre -Filing Meeting Request in the Clean Water Act Section 401 Certification
Rule.
• I understand by signing this form that I cannot submit my application until 30 calendar days after this pre -filing
meeting request.
• I also understand that DWR is not required to respond or grant the meeting request.
Your project's thirty -day clock started upon receipt of this application. You will receive notification regarding meeting location
and time if a meeting is necessary. You will receive notification when the thirty -day clock has expired, and you can submit an
application.
Signature
Ake Zaf
Submittal Date 11/5/2020