Hey Kevin,
Below is a summary of my notes from our site visits (on a very windy day) with Ivan and Brandon along with a
few attached pictures.
Section B
Site 1A culvert inlet area. Reinstall ground cover on hill slope where equipment disturbed existing
vegetation. Remove the traffic cone from the stream channel and the pile of 57-stone from riparian
area. High and low flow barrels appeared to be functioning well.
Site 2 pipe outlet. Area appears to be stable.
Sites 9, 17 and 18 pipe outlets and rip rap appeared to be stable. Some 57-stone needed to be
removed from bank near outlet at Site 18.
NPDES records were in order. As a reminder, a DOT staff inspector for the project needs to sign the
forms along with the contractor performing the inspections. And, remind inspectors to enter the date
when repairs to erosion control measures were completed. If inspectors cannot make repairs within
the 24-hour or 5-day requirements, a note needs to be made providing reasons why (e.g., area was not
accessible due to current flooding or unsafe conditions, etc.)
Section A
Outlets at Sites 24, 23 and 17 appeared to be functioning with no instability noted.
Outlet at Site 16. Riprap placed for bank stabilization was washed out into Gap Creek following a storm
event. We discussed repair options and agreed on repositioning the rip-rap along the ditch outlet,
tying it into existing stream banks matching existing natural downstream aggradational bar elevation
(picture attached).
Site 14 outlet. Rip rap along bank was stable.
Site 11 culvert outlet. High and low flow barrels were functioning and stable.
Site 5 outlet was functioning.
Site 4 rip rap was stable and energy dissipator was stable and functioning.
Our discussion with Ivan concerning his questions relative to stormwater management plans (SMPs)
was to clarify that any revisions to a SMP associated with a written 401 permit should be channeled
through you so that you can notify DWR.
Let me know if I missed anything or misinterpreted our conversations and how DOT decides to make repairs
relative to Site 16 on the A Section. Thanks.
1
Dave W.
Division of Water Resources
401 & Buffer Transportation Permitting
NC Department of Envirionmental Quality
336-776-9703 office
336-403-5655 mobile
Dave.Wanucha@ncdenr.gov
NC DEQ Winston Salem Regional Office
450 West Hanes Mill Road, Suite 300
Winston Salem, NC 27106
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
2