June 29, 2010
CERTIFIED MAIL: RETURN RECEIPT REQUESTED
Mr. Kirk J. Bradley
Lee-Moore Oil Company
P.O. Drawer 9
Sanford, NC 27331
Subject Property: Westpoint At 751
Ut to New Hope Creek [030605, 16-41-1-(11.5), WSIV, NSW]
REQUEST FOR MORE INFORMATION
Dear Mr. Bradley:
DWQ Project # 10-0494
Durham County
On June 22, 2010, the Division of Water Quality (DWQ) received your application dated June 22, 2010, to fill
or otherwise impact 0.05 acres of Non-404, Jurisdictional and Isolated Wetland and 20 linear feet of perennial
stream (temporary impact), to develop the site. The DWQ has determined that your application was incomplete
and/or provided inaccurate information as discussed below. The DWQ will require additional information in
order to process your application to impact protected wetlands and/or streams on the subject property.
Therefore, unless we receive five copies of the additional information requested below, we will place this
project on hold as incomplete until we receive this additional information. If we do not receive the requested
information, your project will be formally returned as incomplete. Please provide the following information so
that we may continue to review your project.
Additional Information Requested:
1. Please provide verification from the USACE that they are permitting this project under a Nationwide
Permit 12, and not a Nationwide Permit 39.
2. Please indicate proposed lot layout as an overlay on the site plan and re-submit your site plans on full
plan sheets at a scale of no smaller than 1 "=50' with topographic contours shown.
3. Please provide building envelopes for all lots with wetlands, streams or buffers on the site plans.
4. Please locate all isolated or non-isolated wetlands, streams, and other waters of the State as overlays on
the site plan.
5. Please provide the overall percent imperviousness of the project, and an inventory of impervious for the
project. The inventory should include all proposed,building footprints, roads, driveways, sidewalks,
gravel-surfaced areas, amenity areas, etc.
401 Oversight/Express Review Permitting Unit
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
Location: 2321 Crabtree Blvd., Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-17861 FAX: 919-733-6893
Internet: http:l/portal.ncdenr.org/web/wgtws
An Equal Opportunity 1 Affirmative Action Employer
NorthCarohna
Al 1' lly
Lee-Moore Oil Company
Page 2 of 2
June 29, 2010
6. Please note that the stormwater management information submitted with your application must be
approved by the City of Durham, and when approved, you are required to submit:
• A valid approval letter from the City of Durham and a copy of the approved SMP, including plan
details, operation and maintenance agreement(s), design calculations and any other supporting
information, OR
• A set of stormwater plan details, operation and maintenance agreement(s), and design calculations
stamped as "Approved" by the local government.
7. Please enumerate the Jordan Buffer impacts on both the impact map and the PCN form. Although
DWQ is not administering the Jordan Rules to private entities within the City of Durham, it is requested
that impacts to the buffers are enumerated on all projects requiring a 401 or Non-404 Jurisdictional
General Permit (IWP100000).
Please submit this information within 30 calendar days of the date of this letter. If we do not receive this
requested information within 30 calendar days of the date of this letter, your project will be withdrawn and you
will need to reapply with a new application and a new fee.
This letter only addresses the application review and does not authorize any impacts to wetlands, waters or
protected buffers. Please be aware that any impacts requested within your application are not authorized (at this
time) by the DWQ. Please call Mr. Ian McMillan or Ms. Amy Chapman at 919-733-1786 if you have any
questions regarding or would like to set up a meeting to discuss this matter.
2,y, A,69:
Ian McMillan, Acting Supervisor
401 Oversight/Express Review Permitting Unit
IJM
cc: USACE Raleigh Regulatory Field Office
Lauren Witherspoon, DWQ Raleigh Regional Office
File Copy
Nicole Thomson, S&EC, P.A., 11010 Raven Ridge Road, Raleigh, NC 27614
Filename: 100494WestpointAt751(Durham)On_Hold
¦ Complete items 1, 2, and 3. Also complete
item 4 if Restricted Delivery is desired.
¦ Print your name and address on the reverse
so that we can return the card to you.
¦ Attach this cans to the back of the mailpiece,
or on the front if space permits.
1. Article Addressed to:
MR KIRK J BRADLEY 6/29/10
LEE-MOORE OIL COMPANY
PO DRAWER 9
SANFORD NC 27331
DWQ 10-0494 DURHAM COUNTY
A. Signatu ?
13 X Lk Agent
0 Addressee
B!)?g^ ceive by (Printed Name) C. Date of Delivery
D. Is delivery address different from 4em42__,0 Yes
If YES, enter delivery address Wow, _ E? tdo
JUN 3 0 ?N
3. Service Type I-, /
ACertified Mail 0 Express. Mail X1.1
0 Registered 0 Return ReceipTfor Merchandise
0 Insured Mail 0 C.O.D.
4. Restricted Delivery? (Extra Fee)
2. Article Number
(rhmsfer from service label) ?009 2820 0004 413? 1493
? Yes
UNITED STATES' POSTAL SERVICE ..:.r-
' ' ._ I' stag:&•I
• Sender: Please print your name, address, and ZIP+4 fi this box
NC DENR DIVISION OF WATER QUALITY
401 OVERSIGHT/EXPRESS UNIT
2321 CRABTREE BOULEVARD, SUITE, 250
RALEIGI I, NC 27604
_¢-? Lll.11??it?ll??tl?l??t,J??ht,J,1Jl?l??lI?J?I?fi???r?ltzl