Loading...
HomeMy WebLinkAbout20051216 Ver 2_More Info Received_20100517JMcGM A S S O C I A T E S May 12, 2010 Mr. Ian McMillan 401 Permitting Unit 1650 Mail Service Center Raleigh, North Carolina 27699-1650 40W- I ck? kP=@ff0WP= 9 MAY 17 2010 %w-vionRQUAUTY NIETi M AW STORWATU SRII O RE: 401 Water Quality Certification East Yancey Water and Sewer District Sewer System Improvements Yancey County, North Carolina Dear Mr. McMillian: This letter is a response to a request for additional information on the above referenced project, received on April 12, 2010 from Roger Edwards, Regional Supervisor in the North Carolina Department of Environment and Natural Resources Asheville Regional Office (DENR-ARO). Yancey County has requested that we respond to the Department's letter. The request for additional information comes from the suggestion from the North Carolina Wildlife Resources Commission to utilize horizontal directional drilling (HDD) techniques for the creek crossings in the East Yancey project. McGill Associates constantly evaluates the use of this technology for all projects involving stream crossings. We would like to take this opportunity to explain the reasons this technique is not appropriate for these sites with the current state of the HDD industry and equipment. While Horizontal Directional Drilling has been utilized by other industries such as telecommunications and gas for some time, it has a shorter history with other types of utilities. McGill Associates has utilized HDD for the installation of water lines and force mains under creeks and rivers for some time, when the topography and other conditions are appropriate. It certainly can have a lessened impact from a land and waterway disturbance standpoint with the added benefit of streamlining the permitting process. It has become our standard installation method for projects in which the pipe is under pressure and grades are not critical, such as water and sewer force mains. Without question, where appropriate and reasonable, horizontal directional drilling can lessen the impact to stream bottoms and banks. But there are other impacts associated with HDD that can be detrimental to streams. A crossing with HDD requires excavation of both a launch pit and receiving pit. Depending on depth and terrain, both these pits can be large and deep, requiring the stockpiling of excavated material adjacent to the stream. While proper erosion control measures can minimize any issues, a large storm event with a mound of soil material next to the stream has the potential to create a larger sedimentation problem than a properly installed conventional creek crossing. A conventional creek crossing has an impact E n g i n e e r i n g P l a n n i n g F i n a n c e McGill AAsociale.S'. P.A. - P.O. Box 2259. Asheville. NC 28802 - 55 Broad Slreel. Asheville, NC 28801 S28-252-0575 - Fax: 828-252-2518 Mr. Ian McMillan May 12, 2010 Page 2 only on the width of the work area necessary for the pipe installation. In addition, the actual work time involved in working adjacent or in the creek can be significantly less for conventional installation techniques. Due to the flow characteristics of both Little Crabtree Creek and Ayles Creek, any minor sedimentation problems will quickly be dissipated. Unfortunately, current HDD equipment is limited in the ability to maintain a uniform alignment and grade. Even the most expensive drilling equipment has difficulty keeping the pipe alignment of the pilot bit straight with minimum deflections, especially in less than ideal conditions. And even with a relatively straight pilot bore, the reaming and pullback operation is easily deflected off course, creating dips and valleys in the final pipe alignment. These issues are well known within the field and have been noted on many projects. Obviously, pipe deflections are not a problem with pipes under pressure, but with gravity sewer line this leads to solids deposition pipe blockages, and eventually, sewer overflows. Since the sewer lines in question are adjacent to water bodies, this is a public health concern and a maintenance issue for those responsible for the sewer system. Because of the difficulties mentioned, attempts to install gravity sewer by HDD are generally limited to areas where soil conditions are known and better suited for drilling and maintaining alignments and grades and also where gravity sewer line grades are 2 percent or greater, allowing for some fluctuation of the pipe and still maintaining flow. Rocky conditions and areas where there is the presence of both soft and hard materials in the bore are the most likely to create problems. Case studies in the past by trenchless technology societies and utilities have shown that gravity sewer line installations under poor conditions are likely to not be successful. Our soil conditions on the East Yancey project are typical of many mountain locations, which are either solid rock, `cobbles' (small to medium loose rocks) or a mixture of both. Also, due to grade issues, most all of our creek crossings are less than 1 percent grade. Both of these factors make an attempt to install gravity sewer by directional drilling likely to fail and a poor construction approach. HDD sewer line installation in this type of environment will likely result in failed attempts which would then have to be installed as a conventional installation. The resultant delays for permitting, all while the Contractor is on the project and stopped from working, is impractical from a contract administration standpoint. Another difficulty with HDD pipe installation where grade is so critical is the cover requirements. On past projects, when using HDD for water or sewer force main installation, both U.S. Fish and Wildlife Service and North Carolina Wildlife Resources Commission have requested that the utility line be installed up to 30 feet below the creek or river bed due to concerns about `frac outs', which is drilling fluid escaping through rock crevices into the Mr. Ian McMillan May 12, 2010 Page 3 water flow. While we have considered the risks minimal and the depth requirements excessive at times, McGill Associates has attempted to maintain significantly more depth for HDD projects than with conventional installation techniques. This is obviously an issue for gravity sewer line and in the case of the East Yancey project, extra depth requirements cannot be obtained and maintain gravity sewer flow for the rest of the project. Other alternatives that were considered for the project but were rejected for various reasons include the following: • Siphons are used for creek and river crossings but require a high, sustained flow to maintain the siphon. Flows for the East Yancey project are going to be small at first and no large-scale growth or increase in flow is expected in the future to allow the use of siphons. • Traditional bore and jack installation of encasement pipe such as used under highways will not work under creek crossings for the same reasons as HDD - rocky conditions preventing a successful installation. There is also the additional factor to boring under a water body risking creating a route for the stream flow to divert into the bore hole, risking the safety of the contractors and damaging the creek bottom. • Micro tunneling or rock bores are an extremely expensive technique, usually reserved for pipe installation in congested urban settings. In addition, all the safety concerns and threats to the stream bed that apply to traditional bore and jack techniques, also apply to this method. • Aerial crossings have been used in the past, allowing most of the construction to be done outside the waterway. However, grade issues, the higher risk of aerial pipes during flooding and the increased maintenance of the crossings required to keep them free of debris eliminate their use for most of this project. • Pump stations may be used to eliminate water crossings. However, 15 pump stations are unrealistic from a public health risk, cost, and maintenance standpoint. After multiple internal meetings on this subject, which included project engineers, field personnel, and the input of Forrest Westall in our office for guidance on regulatory issues, McGill Associates believes that permitting the gravity sewer line crossings as sub-aqueous crossings, installed by conventional construction methods and current best management practices for erosion and sedimentation control is the best alternative at this time. We continually monitor new technology in the construction industry and look forward to the time techniques are developed that will allow us to avoid working in the water for crossings. That will both reduce the impact on the habitats and simplify the approval process greatly. Mr. Ian McMillan May 12, 2010 Page 4 We hope this answers any questions about why horizontal directional drilling is not a viable alternative for this project. If there are any further questions on the project, please contact our office at any time. Sincerely, McGILL, TES, P.A. Technician cc: Nathan Bennett, Yancey County Manager Roger Edwards, Regional Supervisor, Asheville Region, DWQ Chuck Crawford, Surface Water Protection Section, Asheville Region Dave Baker, US Army Corps of Engineers Bryan Tompkins, US Fish and Wildlife Service Dave McHenry, NC Wildlife Resources Commission Harry Buckner, PE, McGill Associates, P.A. Randy Hintz, PE, McGill Associates, P.A. Forrest Westall, PE, McGill Associates, P.A. 01743/collection system/letters/iml2may10_401 Cert.doc