HomeMy WebLinkAbout20170537 Ver 1_Year 2 Monitoring Report_20201005Strickland, Bev
From: Dailey, Samantha J CIV USARMY CESAW (USA) <Samantha.J.Dailey@usace.army.mil>
Sent: Monday, October 5, 2020 8:57 AM
To: Tugwell, Todd J CIV USARMY CESAW (US); Kim Browning; Haywood, Casey M CIV
(USA); Davis, Erin B; Wilson, Travis W.; Bowers, Todd
Subject: [External] SAW-2015-01799 / EBX-Neuse I, LLC / Neu -Con UMBI / Hannah Bridge Year
2 Monitoring Report
Follow Up Flag: Follow up
Flag Status: Completed
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as
an attachment to report.spam@nc.gov<mailto:report.spam@nc.gov>
Good morning,
The below referenced Year 2 Monitoring Report review has been requested by EBX-Neuse I, LLC. Per Section
332.8(o)(9) of the 2008 Mitigation Rule, this review follows the streamlined review process, which requires an
IRT review period of 15 calendar days from this email notification. Please provide any comments by 5 PM on
the 15-day comment deadline shown below. When providing comments please indicate if your concerns are
great enough that you intend to request a site visit prior to the Year 2 credit release. Comments provided after
the 15-day comment deadline (shown below) may not be considered.
At the conclusion of this comment period, a copy of all comments will be provided to EBX-Neuse I, LLC and the
NCIRT along with District Engineer's intent to approve or disapprove this Year 2 Monitoring Report credit
release. Please note, the IRT visited the site, post -construction, on May 28, 2019.
Sponsor: EBX-Neuse I, LLC
Name:
Neu -Con UMBI / Hannah Bridge
USACE ID:
SAW-2015-01799
River Basin:
Neuse
HUC:
03020201
County:
Johnston
CREDIT RELEASE:
10-percent of the total stream and wetland restoration and enhancement credits: 446.6 stream mitigation
units, and 1.0 wetland mitigation units
15-Day Comment Start Date: October 5, 2020 15-Day Comment Deadline: October 20, 2020 45-Day Credit
Release Approval Deadline: November 19, 2020
*NOTE: If a site visit is request by the IRT, comments are due 15 days after the site visit is complete. At this
time an IRT site visit is not scheduled for this site.
Link to Hannah Bridge Year 2 Monitoring Report can be found on RIBITs, under the Monitoring Reports, Year 2
Monitoring Report:
https://urldefense.com/v3/_https://ribits.ops.usace.army.mil/ords/f?p=107:278:2982261030990::NO:RP,27
8:P278_BANK _ID:4413_;!!HYmSToo!O8Ht07RkRee887S1RtLgfUE6ZJO2GuQY1XjWR0OG9gqKN1WSFWF_r6oT
MeuXrEZJCvo$
Please select the arrow beside Year 2 Monitoring Report to view and/or download the documents.
Best Regards,
Sam
Samantha Dailey
Regulatory Project Manager
U.S. Army Corps of Engineers
Regulatory Division
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
(919) 554-4884, Ext. 22
Samantha.j.dailey@usace.army.mil