Compliance Inspection Report
Permit: SW8111212 Effective:04123112 Expiration: 04/23/20
Project: Ryker Trace Section I at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County: Onslow Actress: Ramsey Rd
Region: Wilmington
CitylStatelZip: Jacksonville NC 28540
Contact Person: Anthony W Sydes Title: President Phone: 910-455-6956
Directions to Project:
From US 17 north, left onto Western Blvd., turn right onto Carolina Forest Blvd, at int. with Ramsey Rd, proceed across Carolina
Plantation Blvd, left onto Merin Heights Rd, left on Radiant Drive project begins at powerlines.
Type of Project: State Stormwater - HD - Wetlands State Stormwater - HD - Detention Pond
Drain Areas: 1 - (Half Moon Creek) (03-05-02 ) ( C;NSW)
2 - (Half Moon Creek) (03-05-02 ) ( C;NSW)
On -Site Representative(s):
Related Permits:
Inspection Date: 09/11/2019 Entry Time: 03:00PM Exit Time: 04:30PM
Primary Inspector: Kelly Johnson
Secondary Inspector(s):
Kelly Johnson
Phone: 910-796-7331
Reason for Inspection: Follow-up Inspection Type: Compliance Evaluation
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant E Not Compliant
Question Areas:
0 State Stormwater
(See attachment summary)
page: 1
Permit: SW8111212 Owner- Project: Carolina Plantation Development Corporation
Inspection Date: 09l11/2019 Inspection Type Compliance Evaluation Reason for Visit: Follow-up
File Review Yes No NA NE
Is the permit active? ❑ ❑ ❑
Signed copy of the Engineer's certification is in the file? ❑ ❑ ❑ 0
Signed copy of the Operation & Maintenance Agreement is in the file?
Copy of the recorded deed restrictions is in the file?
Comment: See letter. File review to document that they didn't respond.
L■>■ZET
❑ ❑❑■
page: 2
Compliance Inspection Report
Permit: SW811Oro 15 Effective:10/16/12 Expiration: 08/09/21
Project: Bristol Heights and Bartlett Square at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County: Onslow Adress: Ramsey Rd
Region: Wilmington
CitylState/Zip: Jacksonville NC 28540
Contact Person: Anthany W Sydes Title: President Phone: 910-455-6956
Directions to Project:
From US 17 north, left onto Western Blvd., right onto Carolina Forest Blvd., left onto Merin Heights Rd., project begins at stream
crossing on Arabella Dr I alternate entrance is from Sonoma Rd., in Regal Hill.
Type of Project: State Stormwater- HD - Detention Pond
Drain Areas: 1 -
On -Site Representative(s):
Related Permits:
Inspection Date: 0411012019 Entry Time: 10:25AM
Primary Inspector: Holley A Snider
Secondary Inspector(s):
Kelly Johnson
Reason for Inspection: Other
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
E State Stormwater
(See attachment summary)
Exit Time: 02:40PM
Phone: 919-796-7315
Inspection Type: Transfer Renewal
page: 1
Permit SVV8110615 owner- Project: Carolina Plantation Development Corporation
Inspection Date: 04/10/2019 Inspection Type Transfer Renewal Reason for Visit: Other
File Review Yes No NA NE
Is the permit active? a ❑ ❑ ❑
Signed copy of the Engineer's certification is in the file? ❑ N ❑ ❑
Signed copy of the Operation & Maintenance Agreement is in the file? E ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file?
Comment: Bartlett Square certification needed.
Built Upon Area
Is the site BUA constructed as per the permit and approval plans?
Is the drainage area as per the permit and approved plans?
Is the BUA (as permitted) graded such that the runoff drains to the system?
Comment: Bristol Heiqhts Sect. I : the built upon area appears to be consistent with the approved plan.
Bartlett Square: the built upon area appears to be consistent with the approved plan.
SW Measures
Are the SW measures constructed as per the approved plans?
Are the inlets located per the approved plans?
Are the outlet structures located per the approved plans?
■❑❑❑
Yes No NA NE
■ ❑❑❑
0 ❑❑❑
Yes No NA NE
❑ E ❑ ❑
❑ ■❑❑
E ❑ ❑ ❑
Comment: Bristol Heiahts Sect I : three (3) additonal catch basins have been installed near Lot 406/510 not shown
on the approved plan. (digital files emailed by the Engineer on 4/15/2019 show the additional catch
basins and i es) Swales at the rear of the lots have not been installed or require slope maintenance.
Rip rap apron at the outlet structure of the pond was not visible.
Bartlett Square: stormwater structures are located per the approved plan.
Operation and Maintenance Yes No NA HE
Are the SW measures being maintained and operated as per the permit requirements? ❑ E ❑ ❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ ❑ ❑
DWQ upon request?
Comment: Bristol Heights Sect I: repair slopes of swales at the rear of the Lots. Reinstall rip rap apron at outlet
pipe and repair erosion at outlet pipe.
Bartlett Square: measures appear to be maintained.
Other Permit Conditions Yes No NA NE
Is the site compliant with other conditions of the permit? ❑ 110 E
Comment:
Other WQ Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑ ❑
Comment:
page: 2
perTntt SWO110615 Owner - Project Carolina Plantation Development Corporation
Inspection Date: 0411012019 Inspection Type Transfer Renewal Reason for Visit: Other
page: 3
Compliance Inspection Report
Permit: SW8120710 Effective:12103114 Expiration: 09/20/20
Project: Ryker Trace Section II at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County: Onslow Adress: Ramsey Rd
Region: Wilmington
City/State/Zip: Jacksonville NC 28540
Contact Person: Anthony W Sydes Title: President Phone: 910-455-6958
Directions to Project:
From US 17 north, go left onto Wstern Blvd., right onto Carolina Forest Blvd at intersection with Ramsey Rd., proceed across
Carolina Plantations Blvd left on Merin His Rd left on Radiance left on Cavalier site begins past Section 1.
Type of Project: State Stormwater - HD - Detention Pond
Drain Areas: 1 - (Half Moon Creek) (03-05-02) { C;NSW)
On -Site Representative(s):
Related Permits:
Inspection Date: 04/10/2019 Entry Time: 10:25AM Exit Time: 02:40PM
Primary Inspector: Holley A Snider
Secondary Inspector(s):
Kelly Johnson
Phone: 919-796-7315
Reason for Inspection: Other inspection Type: Transfer Renewal
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
State Stormwater
(See attachment summary)
page: 1
Permit SW8120710 Owner - Project: Carolina Plantation Development Corporation
Inspection Date: 0411012019 Inspection Type Transfer Renewal Reason for Visit Other
File Review Yes No NA NE
Is the permit active? ❑ ❑ ❑
Signed copy of the Engineer's certification is in the file? ❑ ❑ ❑
Signed copy of the Operation & Maintenance Agreement is in the file? 0 ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file? ❑ i ❑ ❑
Comment: Deed restrictions needed.
Built Upon Area Yes No NA NE
Is the site BUA constructed as per the permit and approval plans? ❑ ❑ ❑
Is the drainage area as per the permit and approved plans? Q ❑ ❑ ❑
Is the BUA (as permitted) graded such that the runoff drains to the system? M ❑ ❑ ❑
Comment: The built upon area appears to be consistent with the approved plan.
SW Measures Yes No NA N£
Are the SW measures constructed as per the approved plans? ❑ M ❑ ❑
Are the inlets located per the approved plans? ❑ M ❑ ❑
Are the outlet structures located per the approved plans? ❑ M ❑ ❑
Comment: The rip rap apron and traneziodal swale at the outlet of the stormwater pond is absent or requires
maintenance. The eastern inlet pipe is not visible and the slopes near the pipe location have failed.
Operation and Maintenance Yes No NA N£
Are the SW measures being maintained and operated as per the permit requirements? ❑ 0 ❑ ❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ M ❑ ❑
DWQ upon request?
Comment: The rip rap apron and trapeziodal swale at the outlet pipe of the stormwater pond require maintenance.
Repair slopes to provide an outlet for the eastern inlet tripe of the stormwater pond.
Other Permit Conditions Yes No NA HE
Is the site compliant with other conditions of the permit? ❑ ❑ ❑
Comment:
Other WQ Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑
Comment:
page: 2
Compliance Inspection Report
Permit: SW8100714 Effective- 02/05/15 Expiration: 12/31/21
Project: Great Neck Section II Regal Hill and Tinley Estates at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County: Onslow Adress: Ramsey Rd
Region: Wilmington
Contact Person: Anthony W Sydes
City/StatelZip: Jacksonville NC 28540
Title: President Phone: 910-455-6956
Directions to Project:
From US17 north, turn left onto Western Blvd, right onto Carolina Forest, proceed across Carolina Plantations Blvd., right onto
Sonoma Rd. Site begins at stream crossing.
Type of Project: State Stormwater - HD - Wetlands State Stormwater - HD - Detention Pond
Drain Areas: 1 - (Half Moon Creek) (03-05-02) { C;NSW)
2 - (Half Moon Creek) (03-05-02) { G;NSW)
3 - (Half Moon Creek) (03-05-02) { C;NSW)
On -Site Representative(s):
Related Permits:
SW8100510 Carolina Plantation Development Corporation - Great Neck Section I Crown Party
Inspection Date: 04110/2019 Entry Time: 10:25AM Exit Time: 02:40PM
Primary Inspector: Holley A Snider
Secondary Inspector(s):
Kelly Johnson
Reason for Inspection: Other
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
■ State Stormwater
(See attachment summary)
Phone: 919-796-7315
Inspection Type: Transfer Renewal
page: 1
Permit. SW8100714 Owner- Project: Carolina Plantation Development Corporation
Inspection Rate: 0411012019 Inspection Type Transfer Renewal Reason for Visit: Other
File Review
Is the permit active?
Signed copy of the Engineer's certification is in the file?
Signed copy of the Operation & Maintenance Agreement is in the file?
Copy of the recorded deed restrictions is in the file?
Comment: Heed restrictions needed.
Final certifications needed.
Built Upon Area
Is the site BUA constructed as per the permit and approval plans?
Is the drainage area as per the permit and approved plans?
Is the BUA (as permitted) graded such that the runoff drains to the system?
Comment: Great Neck Section II : The built upon area appears to be consistent with the anoroved plan.
Regal Hill The built upon area appears to be consistent with the approved plan.
Tinley Estates: The built upon area appears to be consistent with the approved plan.
SW Measures
Are the SW measures constructed as per the approved plans?
Are the inlets located per the approved plans?
Are the outlet structures located per the approved plans?
Comment: Great Neck Section II : additional catch basins and pipes have been installed not shown on the
Yes No NA NE
❑ ❑ ❑
❑ ■❑❑
Yes No NA NE
M ❑ ❑ ❑
s❑❑❑
■ ❑❑❑
Yes No NA NE
❑ ■❑❑
❑ ■❑❑
❑ ❑ ❑
approved 121an. (digital files emailed by the Engineer on 4/15/2019 show the additional catch basins and
pipes).
Regal Hill: the stormwater measures appear to be constructed in accordance with the approved plans.
Tinley Estates: the stormwater measures appear to be constructed in accordance with the aoroved
l�—
Operation and Maintenance Yes No NA NE
Are the SW measures being maintained and operated as per the permit requirements? ❑ 0 ❑ ❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ ❑ ❑
TWO upon request?
Comment: Great Neck Section II : a large hole has formed next to the manhole over near the stormwater wetlands.
The outlet structures of wet detention basin #1 and #2 lack riprap aprons and require repairs. The orifice
of the stormwater wetlands appear to be clogged and the wetland vegetation is absent in some areas.
Regal Hill : measures appear to be maintained.
Tinley Estates : measures appear to be maintained.
Other Permit Conditions
Is the site compliant with other conditions of the permit?
Comment:
Yes No NA NE
❑ ❑ ❑ M
page: 2
Permit: SW8100714 Owner - Project: Carolina Plantation Development Corparation
inspection Date: 04/10/2019 Inspection Type Transfer Renewal
Other WQ Issues
Is the site compliant with other water quality issues as noted during the inspection?
Comment:
Reason for Visit: Other
Yes No NA NE
❑ ❑❑■
page: 3
Compliance Inspection Report
Permit: SW8111212 Effective:04123/12 Expiration: 04/23/20
Project: Ryker Trace Section I at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County. Onslow Actress: Ramsey Rd
Region: Wilmington
CitylState/Zip: Jacksonville NC 28540
Contact Person: Anthony W Sydes Title: President Phone: 910-455-6956
Directions to Project:
From US 17 north, left onto Western Blvd., turn right onto Carolina Forest Blvd, at int. with Ramsey Rd, proceed across Carolina
Plantation Blvd, left onto Merin Heights Rd, left on Radiant Drive project begins at powedines.
Type of Project: State Stormwater - HD - Wetlands State Stormwater - HD - Detention Pond
Drain Areas: 1 - (Half Moon Creek) (03-05-02 ) (C;NSW)
2 - (Half Moon Creek) (03-05-02) (C;NSW)
On -Site Representative(s):
Related Permits:
Inspection Date: 04/10/2019 Entry Time: 10:25AM
Primary Inspector: Holley A Snider
Secondary Inspector(s):
Kelly Johnson
Reason for Inspection: Other
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
State Stormwater
(See attachment summary)
Exit Time: 02:40PM
Phone: 919-796-7315
Inspection Type: Transfer Renewal
page: 1
Permit: SW8111212 Owner - Project: Carolina Plantation Development Corporation
Inspection Date: 0411012019 Inspection Type Transfer Renewal Reason for Visit: Other
File Review - Yes No NA NE
Is the permit active? ! ❑ ❑ ❑
Signed copy of the Engineer's certification is in the file? ❑ 0 ❑ ❑
Signed copy of the Operation & Maintenance Agreement is in the file? 0 ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file? ❑ ®❑ ❑
Comment: Deed restrictions needed.
Certification needed.
Built Upon Area Yes No NA NE
Is the site SUA constructed as per the permit and approval plans? 0 ❑ ❑ ❑
Is the drainage area as per the permit and approved plans? ® ❑ ❑ ❑
Is the BUA (as permitted) graded such that the runoff drains to the system? 0 ❑ ❑ ❑
Comment: The built upon area appears to be consistent with the approved.plan,
5W Measyrres
Yes No NA NE
Are the SW measures constructed as per the approved plans? ❑ E ❑ ❑
Are the inlets located per the approved plans? 0 ❑ ❑ ❑
Are the outlet structures located per the approved plans? 0 ❑ ❑ ❑
Comment: The swale leading to the stormwater wetlands has not been constructed properly and water is being
diverted from the wetlands to the existing stream. The stormwater wetlands lack deep pools, vegetation
and the orifice appears to be clogged.
Operation and Maintenance Yes No NA NE
Are the SW measures being maintained and operated as per the permit requirements? ❑ 0 ❑ ❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ ❑ ❑
DWQ upon request?
Comment: The swale and stormwater wetlands require maintenance. Maintain the swale at the rear of Lots
735/736.
Other Permit Conditions Yes No NA NE
Is the site compliant with other conditions of the permit? ❑ ❑ ❑
Comment:
Other WO Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑
Comment:
page: 2
Compliance Inspection Report
Permit: SW8100510 Effective:01/15/13 Expiration: 03/10/21
Project: Great Neck Section I Crown Park Bentley Place and The Burroughs at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County: Onslow Adress: Ramsey Rd
Region: Wilmington
City/State/Zip: Jacksonville NC 28540
Contact Person: Anthony W Sydes Title: President Phone: 910-455-6956
Directions to Project:
US 17north, left onto Western Blvd, right onto Carolian Forest Blvd project is at end of strett across Ramsey Road.
Type of Project: State Stormwater - HD - Detention Pond
Drain Areas: 1 -
2-
3-
4-
On-Site Representative(s):
Related Permits:
Inspection Date: 04110/2019 Entry Time: 10:25AM Exit Time: 02:40PM
Primary Inspector: Holley A Snider
Secondary Inspector(s):
Kelly Johnson
Phone: 919-796-7315
Reason for Inspection: Other Inspection Type: Transfer Renewal
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
■ State Stormwater
(See attachment summary)
page: 1
permit: 5W8100510 Owner - Project Carolina Plantation Development Corporation
Inspection Date: 0411012019 Inspection Type Transfer Renewal Reason for Visit: Other
Inspection Summary:
STORMWATER MEASURES:
Great Neck Sect, I: Repair the level spreader and vegetated filter at the outlet structure of stormwater detention pond #2.
Repair the level spreader and vegetated filter at the outlet structure of stormwater detention pond #1. Repair erosion
adjacent to the wetlands and stream at both outlets. The portion of flume is blocked near CB #29. CB #24 has second
CB. CB#9 has second CB. CB#8 has second CB.
Crown Park: Repair the scour hole flow spreader at the end of the outlet pipe of stormwater detention pond #3.
Burroughs Sect. I: Repair the rock hole flow spreader, vegetated filter and rock check dam at the outlet structure of
stormwater detention pond. Repair the existing dislodged corrugated metal pipe within the stream. Remove sediment
from stream and repair erosive slopes.
Carolina Plantation Office Building: a pipe and curb outlet on the north side of the parking lot leading stormwater
detention pond #3 has been constructed and are not shown on the approved plan.
OPERATION AND MAINTNEANCE:
Great Neck Section I: Repair the level spreader and vegetated filter at the outlet structure of stormwater detention pond
#2. Repair the level spreader and vegetated filter at the outlet structure of stormwater detention pond #1. Repair erosion
at the wetlands and stream near both of the failed outlet structures.
Crown Park: Repair scour hole flow spreader at the outlet pipe of stormwater detention pond #3.
Burroughs Sect I: Repair the rock hole flow spreader, vegetated filter and rock check dam at the outlet structure of the
stormwater detention pond. Repair the existing dislodged corrugated metal pipe within the stream. Remove sediment
from the stream and repair erosive slopes.
page: 2
Permit SW8100510 Owner- Project: Carolina Plantation development Corporation
Inspection Date: 04/1012019 Inspection Type Transfer Renewal Reason for Visit: Other
File Review Yes No NA NE
Is the permit active? ® ❑ ❑ ❑
Signed copy of the Engineer's certification is in the file? ❑ ®❑ ❑
Signed copy of the Operation & Maintenance Agreement is in the file? ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file? ❑ M ❑ ❑
Comment: Restrictions needed.
Certifications needed.
Built Upon Area Yes No NA NE
Is the site BUA constructed as per the permit and approval plans? ■ ❑ ❑ ❑
Is the drainage area as per the permit and approved plans? 0 ❑ ❑ ❑
Is the BUA (as permitted) graded such that the runoff drains to the system? ❑ ❑ ❑
Comment: Great Neck Sect I: the built upon area appears to be consistent with the a oved plan.
Crown Park: the built upon area appears to be consistent with the approved plan.
Bentley Park: the built upon area appears to be consistent with the approved plan.
The Burroughs Sect. l: the built upon area appears to be consistent with the approved plan
Office at Carolina Plantation: the built upon area appears to be consistent with the approved plan.
SW Measures Yes No NA NE
Are the SW measures constructed as per the approved plans? ❑ ❑ ❑
Are the inlets located per the approved plans? ❑ ❑ ❑
Are the outlet structures located per the approved plans? ❑ ®❑ ❑
Comment: see summary
_Operation and Maintenance Yes No NA NE
Are the SW measures being maintained and operated as per the permit requirements? ❑ M ❑ ❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ i ❑ ❑
DWQ upon request?
Comment: see summary
Other Permit Conditions Yes No NA NE
Is the site compliant with other conditions of the permit? ❑ ❑ ❑
Comment:
Other WO Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑ ■
Comment:
page: 3
Compliance Inspection Report
Permit: SW8101110 Effective:06/27111 Expiration: 06/13/21
Project: Monarch Meadow at Carolina Plantations Stormwater
Owner: Carolina Plantation Development Corporation
County: Onslow Adress: Ramsey Rd
Region: Wilmington
CitylStatelZip: Jacksonville NC 28540
Contact Person: Anthony W Sydes Title: President Phone: 910-455-6956
Directions to Project:
From 17 N, turn left onto Western Blvd right onto Carolina Forest Blvd., proceed cross Carolina Plantations Blvd., left onto Merin
Heigh Rd site begins at stream crossing.
Type of Project: ,State Stormwater • HD - Detention Pond
Drain Areas: 1 -
On -Site Representative(s):
Related Permits:
Inspection Date: 04/10/2019 Entry Time: 10:25AM Exit Time: 02:40PM
Primary Inspector: Holley A Snider
Secondary Inspector(s):
Kelly Johnson
Phone: 919-796-7315
Reason for Inspection: Other Inspection Type: Transfer Renewal
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
0 State Stormwater
(See attachment summary)
page: 1
Permit: SW8101110 Owner - Project: Carolina Plantation Development Corporation
Inspection Date: 0411012019 Inspection Type Transfer Renewal Reason for Visit: Other
File Review Yes No NA NE
Is the permit active? ❑ ❑ ❑
Signed copy of the Engineer's certification is in the file? ❑ ❑ ❑
Signed copy of the Operation & Maintenance Agreement is in the file? ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file?
Comment: Restrictions needed.
Built Upon Area
Is the site BUA constructed as per the permit and approval plans?
Is the drainage area as per the permit and approved plans?
Is the SUA (as permitted) graded such that the runoff drains to the system?
Comment: The built upon area appears to be consistent with the a r oved plan.
5W Measures
Are the SW measures constructed as per the approved plans?
Are the inlets located per the approved plans?
Are the outlet structures located per the approved plans?
❑ ®❑ ❑
Yes No NA NE
■ ❑❑❑
M ❑ ❑ ❑
Cl ❑ ❑
as No NA NE
❑ M ❑ ❑
❑ ❑ ❑
❑■❑❑
Comment: The swales along the rear of the lots appear to be absent or in need of maintenance. The yard inlet at
function of pipes B8, B7 and B12 has failed and sink hole has formed. The rip rap apron at the outlet
pipe of the stormwater detention pond is absent or in need of maintenance.
Operation and Maintenance
Are the SW measures being maintained and operated as per the permit requirements?
Yes No NA NE
❑ ■❑❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ ❑ ❑
DWQ upon request?
Comment: The swales and riprap apron require maintenance. Repair yard inlet at the 'unction of pipes B7. B8 and
B12, fill sink hole and provideyecletative cover.
Other Permit Conditions Yes No NA NE
Is the site compliant with other conditions of the permit? ❑ ❑ ❑
Comment:
Other WQ Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑ ■
Comment:
page: 2
f tt
Compliance Inspection Report
Permit: SVV8120710 Effective: 12/03114 Expiration: 09120/20
Project: Ryker Trace Section II at Carolina Plantations
Owner: Carolina Plantation Development Corporation
County: Onslow Adress: Ramsey Rd
Region: Wilmington
City/State/Zip: Jacksonville NC 28540
Contact Person: Anthony 1N Sydes Title: President Phone: 910-455-6956
Directions to Project:
From US 17 north, go left onto Wstem Blvd., right onto Carolina Forest Blvd at intersection with Ramsey Rd., proceed across
Carolina Plantations Blvd tell on Merin His Rd left on Radiance left on Cavalier site begins past Section 1. .
Type of Project: State Slormwater - HD - Detention Pond
Drain Areas: 1 - (Ha4 Moon Creek) (03-05-02) ( C;NSW)
On -Site Representative(s):
Related Permits:
Inspection Date: 04/1012019 EntryTime: 10:25AM Exit Time: 02:40PM
Primary Inspector: Holley A Snider
Secondary Inspector(sj:
Phone: 919-796-7315
Reason for Inspection: Other Inspection Type: Transfer Renewal
Permit Inspection Type: State Slormwater
Facility Status: ❑ Compliant ❑ Not Compliant
Question Areas:
State Stormwater
(See attachment summary)
page: 1
' 'R
Permit: S11-M12C710 Owner - Project: Carolina Plantation Development Corporation
Inspection date: 0471012019 Inspection Type Transfer Rene .al Reason for Visit: Otner
File Review Yes No NA NE
Is the permit active? ❑ ❑ ❑
Signed copy of the Engineer's certi5calion is in the file? ❑ ❑ ❑ M
Sioned copy of the Operation & Maintenance Agreement is in the file? ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file? ❑ ❑ ❑ ■
Comment:
Built Upon Area
Yes No NA NE
Is the site BUA constructed as per the permit and approval plans? ❑ ❑ ❑
Is the drainage area as per the permit and approved plans? ❑ ❑ ❑
Is the BUA (as perrnilted) graded such that the runoff drains to the system? 0 ❑ ❑ E]
Comment: The built upon area appears to be consistent with the approved plan.
5W Measures Yes No NA NE
Are the S%,V measures constructed as per the approved plans? ❑ 0 ❑ ❑
Are the inlets located per the approved plans? ❑ M ❑ ❑
Are the outlet structures located per the approved plans? ❑ M ❑ ❑
Comment. The rip rap apron and trapeziodal swale at the outlet of the stormwater pond is absent or requires
maintenance. The eastern inlet pipe is not visible and the slopes near the pipe location have failed.
Operation and Maintenance
Are the SVV measures being maintained and operated as per the permit requirements
Yes No NA NE
❑ ■❑❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ E ❑ ❑
bWQ upon request?
Comment: The rip rap apron and trapeziodal swale at the outlet pipe of the stormwater pond require maintenance.
Repair slopes tc provide an outlet for the eastern inlet pipe of the stormwater pond.
Other Permit Conditions
Yes No NA NE
Is the site compliant with other conditions of the permit? ❑ ❑ ❑
Comment.
Other WQ Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑ M
Comment:
pace: 2
State Stormwater Inspection Report
General
Aroject tamer 1 ACE �t
! PerinitT °V SW9 jap-� ��
Expiration Date:
Contact Person:
Phone Number,
Inspection Type:
11Inspieciion Date:
Ti rie 131:
Time Out:
jCun ent `breather:
I Recent Rain (Date)?
Rain — in
Location
Facility Address / Location: '
City: I Zip: Counr)': Lat: "\ Long: "NV
E
Permit Information
Rule. Subject to (circle one): 1955 Coastal Rule 1995 Coastal Rule 2008 Coastal Rule Session Lave 2006-246
Goose Creek High Quality Waters Outstanding resource NVaters
Density (circle one): 141gh (HD) Love (LD)
Stormwater Best INlanagernent Practices (Bi\]Ps) (insert number of each):
1 Wet Ponds Infiltration Basins Infiltration Trenches LD Swales Stormwater Wetlands
Dry Ponds Bloretention Permeable Pavement Sand filters (circle one) Open Closed
Cistern Level Spreader/Filter Strip Other (speci)):
File Review Yes No NIA N!E
I I. Is the permit active?
f
J
' 2. Si ned Engineer's Certification on file? CV0_UV_
3fi
J
4. Recorded Deed Restrictions on file?
Site Visit: Built Ur3on Area (BUA) t,Yes -No NIA N1E
5. BUA is -constructed and consistent with the pennii re uirements?
i
6. BUA (as perrraitted is raded such that the runoff drains to fire system? (hi h density only
7. Drainage area is consistent with permit? (i.e. no un ermitted drainage to the SW BiMPs)
S. Drain e area is stabilized? (to reduce risk of sedimentation to the SW Bi`IPS)
Site Visit: _Stormwater BMPs Yes No NIA N/E
9. Stormwater BA9Ps are located per the an rovedplans?
10. Stormwater BiNIPs have dirn.ensions (eg. len ih, width; area) matching fne approved plans?
I I. Stormwater BMPs are construcied per the approved plans?
Site Visit: Or)eration and Maintenance Yes No NIA NIE
12, Access points to the site are clear and well maintained?
13, Trash has been removed as needed?
14, Excessive landscape debris (grass clippings, leaves, etc) is controlled?
1
15, Storm xater B11IPs being operated and maintained as per the 2ermif requirements?
16. Inspection and Maintenance records are available for ins ep ctioil? (hamdensity only, 1995 — present only) I L�
Site Visit: Other Permit Conditions Yes No NIA NI
17. Is the site compliant with other conditions of the ermii?
Site Visit: Other Water Quality Issues Yes No NIA N1 —
1 S. Is the site compliant with_other_ water aaality issues as noted during the inspection? ,r I I I
State Stormwater inspection Report, Version 3.4_3-09 Page ] of2
State Stormwater Inspection Report
Comments
Inspection Pictures (some of the pictures taken during the site
Compliance Status ❑ Compliant ❑ Non -Compliant
Letter Sent (circle one): Yes No Letter type CEI NOV NOVRE Other
Date Sent: Reference Number:
Inspector Name and Signature.
Date:
State Sto rnwater Inspection Report, Version 3.0_3-09 Page 2 or2
� Permit No.
1 {(o be provided by DM)
of wAr�,q
NCDENR
STORM4VATER MANAGEMENT PERMIT APPLICATION FORM
401 CERTIFICATION APPLICATION FORM
WET DETENTION BASIN SUPPLEMENT
This form must be filled out, printed and submitted.
The Required Items Checklist {Part 111) must be printed, filled out and submitted along with all of the required information.
[I. -.,PROJECT INFORMATION.'
Project name Ryker Trace Section I at Carolina Plantations
Contact person Anthony W. Sydes _
Phone number 910-455-6956
Date 12114/2011, Revised 2110)12
Drainage area number 1
IV DESIGN INFORMATION
Site Characteristics
Drainage area
1,271,986 ftz
Impervious area, post -development
502,907 fe
% impervious
39.54 %
Design rainfall depth
1.5 in
Storage Volume: Non -SA Waters
Minimum volume required 64,537 ft3 OK
Volume provided 73,272,ft3
OK, volume provided is equal to or in excess of volume required.
Storage Volume: SA Waters
1.5" runoff volume ft3
Pre -development 1-yr, 24-hr runoff ft3
Post -development 1-yr, 24-hr runoff ft3
Minimum volume required ft3
Volume provided ft3
Peak Flow Calculations
bL^^aCEI FM
Ll V i:.i
Is the pre/post control of the 1 yr 24hr storm peak flow required?
Y (Y or N)
1-yr, 24-hr rainfall depth
3.5 in
FEB 1 17 q 2012
Rational C, pre�development
0.30 (unitless)
Rational C, post -development
0.50 (unitless)
Rainfall intensity: 1-yr, 24-hr storm
2.73 inihr OK�
Pre -development 1-yr, 24-hr peak flow
4,19 ft3lset
Post -development 1-yr, 24-hr peak flow
2,11 ft3(set
PrelPost 1-yr, 24-hr peak flow control
-2.08 ft3fsec
Elevations
Temporary pool elevation
42.50 fmsl
Permanent pool elevation
39.50 fmsl
SHWT elevation (approx. at the perm. pool elevation)
fmsl
Top of 10ft vegetated shelf elevation
40.00 fmsl
Bottom of 1 Oft vegetated shelf elevation
39.00 fmsl
Sediment cleanout, top elevation (bottom of pond)
28.00 fmsl
Sediment cleanout, bottom elevation
27.00 fmsl
Sediment storage provided
1.00 ft
Is there additional volume stored above the state -required temp. pool?
N (Y or N)
Elevation of the top of the additional volume
fmsl
Form SW401-Wet Detention Basin-Rev.8-9117109 Parts 1__ It_ Design Summary, Page 1 of 2
', )
Permit No.
Y (to be provided by DWQ)
III. DESIGN INFORMATION
Surface Areas
Area, temporary pool 27,930 ft'
Area REQUIRED, permanent pool 17,808 ftZ
SAIDA ratio 1.40 (unitless)
Area PROVIDED, permanent pool, Ap ,,,_pd 18,980 ftZ OK
Area, bottom of 10ft vegetated shelf, Abc4 0r d 15,309 ft'
Area, sediment cleanout, top elevation (bottom of pond), Abatya,d 2,945 ftZ
Volumes
Volume, temporary pool
73,272 ft'
OK
Volume, permanent pool, Vim --Pm
108,877 ft3
Volume, forebay (sum of forebays if more than one forebay)
21,701 ft3
Forebay % of permanent pool volume
19.9% %
OK
SAIDA Table Data
Design TSS removal
90 %
Coastal SAIDA Table Used?
Y (Y or N)
MountairdPiedmont SAIDA Table Used?
N (Y or N)
SAIDA ratio
1.40 (unitless)
Average depth (used it SAIDA table):
Calculation option 1 used? (See Figure 10-2b)
N (Y or N)
Volume, permanent pool, Vp--,d
109,877 ft'
Area provided, permanent pool, A,.,,,,_pw
18,980 ft2
Average depth calculated
ft
Need 3 ft min.
Average depth used in SAIDA, d. (Round to nearest 0.5ft)
ft
Calculation option 2 used? (See Figure 10-2b)
Y (Y or N)
Area provided, permanent pool, Ap _"
18.980 fit
Area, bottom of 1 Oft vegetated shelf, Abt-,
15.309 ft2
Area, sediment cleanout, top elevation (bottom of pond), Ay.t_pwd
2,945 rye
"Depth" (distance btw bottom of 1 Oft shelf and top of sediment)
11.00 ft
Average depth calculated
7.01 ft
OK
Average depth used in SAIDA, d. (Round to nearest 0.5ft)
7.0 ft
OK
Drawdown Calculations
Drawdown through orifice?
Y (Y or N)
Diameter of orifice (if circular)
100 in
Area of orifice (if -non -circular)
in'
Coefficient of discharge (Cp)
0.60 (unitless)
Driving head (Ho)
1.00 ft
Drawdown through weir?
N (Y or N)
Weir type
(unitless)
Coefficient of discharge
{unitless)
Length of weir (L)
ft
Driving head (H)
ft
Pre -development 1-yr, 24-hr peak flow
4.19 Wisec
Post -development 1-yr, 24-hr peak Flow
2.11 ft3lsec
Storage volume discharge rate (through discharge orifice or weir)
0,24 1131sec
Storage volume drawdown time
3.53 days
OK, draws down in 2-5 days.
RECEIVED
Additional Information
Vegetated side slopes
3 :1
OK
FEB 9 201�
Vegetated shelf slope
10 :1
OK
d
Vegetated shelf width
10.0 ft
OK
Length of flowpath to width ratio
3 :1
OK
B Y;
Length to width ratio
3.0 :1
OK
Trash rack for overflow & orifice?
Y (Y or N)
OK
Freeboard provided
1.0 ft
OK
Vegetated filter provided?
N (Y or N)
OK
Recorded drainage easement provided?
Y (Y or N)
OK
Capures all runoff at ultimate build -out?
Y (Y or N)
OK
Drain mechanism for maintenance or emergencies is:
Pump
Form SW401-Wet Detention Basin-Rev.&-9117109
Parts 1_ — II_ Design Summary, Page 2 of 2
Permit No.
a? (to be provided by DWQ)
III. REQUIRED ITEMS CHECKLIST
Please indicate the page or plan sheet numbers where the supporting documentation can be found. An incomplete submittal package will
result in a request for additional information. This will delay final review and approval of the project. Initial in the space provided to
indicate the following design requirements have been met. If the applicant has designated an agent, the agent may initial below. If a
requirement has not been met, attach justification.
Pagel Plan
Initials Sheet No.
1. Plans (1" 50' or larger) of the entire site showing:
- Design at ultimate build -out,
Off -site drainage (if applicable),
- Delineated drainage basins (include Rational C coefficient per basin),
Basin dimensions,
Pretreatment system,
High flow bypass system,
Maintenance access,
Proposed drainage easement and public right of way (ROW),
Overflow device, and
Boundaries of drainage easement.
t l 2, Partial plan (1" = 30' or larger) and details for the wet detention basin showing:
U Outlet structure with trash rack or similar,
Maintenance access,
Permanent pool dimensions,
Forebay and main pond with hardened emergency spillway,
Basin cross-section,
Vegetation specification for planting shelf, and
Filter strip.
3. Section view of the wet detention basin (1" = 20' or larger) showing:
�1 Side slopes, 3:1 or lower,
Pretreatment and treatment areas, and
Inlet and outlet structures.
12,_ 4. If the basin is used for sediment and erosion control during construction, clean out of the basin is specified
� on the plans prior to use as a wet detention basin.
Se[. Galas 5. A table of elevations, areas, incremental volumes & accumulated volumes for overall pond and for forebay,
yy to verity volume provided.
6. A construction sequence that shows how the wet detention basin will be protected from sediment until the
entire drainage area is stabilized.
7. The supporting calculations.
B. A copy of the signed and notarized operation and maintenance (0&M) agreement.
V
tnc. 9. A copy of the deed restrictions (if required).
�� Ic• 10. A soils report that is based upon an actual field investigation, soil borings, and infiltration tests. County
UUU soil maps are not an acceptable source of soils information.
7BY:
CEIVE
C 2 2 2011
Form SW401-wet Detention Basin-Rev.8-9117109 Part Ill_ Required Items Checklist, Page 1 of 1
Permit Nurnber: �li� / Z__
(to be provided by D111Q)
Drainage Area Number: t
Wet Detention Basin Operation and Maintenance Agreement
I will keep a maintenance record on this BMP. This maintenance record will be kept in a
Iog in a known set location. Any deficient BMP elements noted in the inspection will be
corrected, repaired or replaced immediately. These deficiencies can affect the integrity
of structures, safety of the public, and the removal efficiency of the BMP.
The wet detention basin system is defined as the wet detention basin,
pretreatment including forebays and the vegetated filter if one is provided.
This system (check one):
❑ does ® does not incorporate a vegetated filter at the outlet.
This system (check one):
❑ does ® does not incorporate pretreatment other than a IForebay.
Important maintenance procedures:
— Immediately after the wet detention basal is established, the plants on the
vegetated shelf and perimeter of the basin should be watered twice weekly if
needed, until the plants become established (commonly six weeks).
— No portion of the wet detention pond should be fertilized after the first initial
fertilization that is required to establish the plants on the vegetated shelf.
— Stable groundcover should be maintained in the drainage area to reduce the
sediment load to the wet detention basin.
— If the basin must be drained for an emergency or to perform maintenance, the
flushing of sediment through the emergency drain should be minimized to the
maximum extent practical.
— Once a year, a dam safety expert should inspect the embankment.
After the wet detention pond is established, it should be inspected once a month and
within 24 hours after every storm event greater than 1.0 inches (or 1.5 inches if in a
Coastal County). Records of operation and maintenance should be kept in a known set
location and must be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall
be repaired immediately.
BMP element:
Potentialproblem:
How I will remediate theproblem:
The entire BMP
Trash/debris is present.
Remove the trash/debris.
The perimeter of the wet
Areas of bare soil and/or
Regrade the soil if necessary to
detention basin
erosive gullies have formed.
remove the gullv, and then plant a
ground cover and water until it is
established. Provide lime and a one-
time fertilizer application.
Vegetation is too short or too
Maintain vegetation at a height of
lon
—approximately six inches.
Form SW401-Wet Detention Basin 0&CM-Rev.4
F2ECEIVED
DEC 2 2.2011
Page 1 of 4
Permit Number:
(to be provided b), DIVQ)
Drainage Area Number:
BMP element:
Potentialproblem:
How I will remediate theproblem:
The inlet device: pipe or
The pipe is clogged.
Unclog the pipe. Dispose of the
Swale
sediment off -site.
The pipe is cracked or
Replace the pipe.
otherwise damaged.
Erosion is occurring in the
Regrade the swale if necessary to
swale.
smooth it over and provide erosion
control devices such as reinforced
turf matting or riprap to avoid
future eroblems with erosion.
The forebay
Sediment has accumulated to
Search for the source of the sediment
a depth greater than the
and remedy the problem if possible.
original design depth for
Remove the sediment and dispose of
sediment storage,
it in a location where it will not
cause impacts to streams or the
BMP.
Erosion has occurred.
Provide additional erosion
protection such as reinforced turf
matting or riprap if needed to
prevent future erosion problems.
Weeds are present.
Remove the weeds, preferably by
hand. If pesticide is used, wipe it on
the plants rather than spraying,
The vegetated shelf
Best professional practices
Prune according to best professional
show that pruning is needed
practices
to maintain optimal plant
health.
Plants are dead, diseased or
Determine the source of the
dying.
problem: soils, hydrology, disease,
etc. Remedy the problem and
replace plants. Provide a one-time
fertilizer application to establish the
ground cover if a soil test indicates it
is necessary.
Weeds are present.
Remove the weeds, preferably by
hand. If pesticide is used, wipe it on
the plants rather than spraying.
The main treatment area
Sediment has accumulated to
Search for the source of the sediment
a depth greater than the
and remedy the problem if possible.
original design sediment
Remove the sediment and dispose of
storage depth,
it in a location where it will not
cause impacts to streams or the
BMP.
Algal growth covers over
Consult a professional to remove
50% of the area.
and control the algal growth.
Cattails, phragmites or other
Remove the plants by wiping them
invasive plants cover 50% of
with pesticide (do not spray).
the basin surface.
FBY:
IVED
2 .ZQ1]
Form SW401-Wet Detention Basin O&M-Rev.4 Pale 2 of 4
Permit Number:
(to be provided b_y DRQ)
Drainage Area Number:
BMP element:
Potentialproblem-:
How I will remediate theproblem:
The embankment
Shrubs have started to grow
Remove shrubs immediately.
on the embankment.
Evidence of muskrat or
Use traps to remove muskrats and
beaver activity is present.
consult a professional to remove
beavers.
A tree has started to grow on
Consult a dam safety specialist to
the embankment.
remove the tree.
An annual inspection by an
Make all needed repairs.
appropriate professional
shows that the embankment
needs repair. if applicable)
The outlet device
Clogging has occurred.
Clean out the outlet device. Dispose
of the sediment off -site.
The outlet device is damaged
Repair or replace the outlet device.
The receiving water
Erosion or other signs of
Contact the local NC Division of
damage have occurred at the
Water Quality Regional Office, or
outlet.
the 401 Oversight Unit at 919-733-
1786.
The measuring device used to determine the sediment elevation shall be such
that it will give an accurate depth reading and not readily penetrate into
accumulated sediments.
When the permanent pool depth reads 11.5 feet in the main pond, the
sediment shall be removed.
When the permanent pool depth reads 11.5 feet in the forebay, the sediment
shall be removed.
Sediment Removal
Bottom Elevati
BASIN DIAGRAM
(fill in the blanks)
28.0 Pe anen\
�2L7
------------- -- Volume
.0 -ft Min.
Sediment
Storage
FOREBAI'
Form SW401-Wet Detention Basin 0RM-Rev.4
Permanent Pool Elevation 39.5
Pool
Sediment Removal Elevation 28.0 ----- Volume
------------------------------------ ------
Bottom Elevation 27.0 1-ft
MAIN POND
RECEIVED
DEC 2 2 .2011
BY:
Page 3 of 4
Storage
Permit Number:
(to he provided by DIVA)
I acknowledge and agree by my signature below that I am responsible for the
perfonnance of the maintenance procedures listed above. I agree to notify DWQ of any
problems with the system or prior to any changes to the system or responsible party.
Pi-aject name: Ryker Trace, Section I at Carolina Plantations
BMP drainage area nuniber: 1 - Wet Detention Basin
Print name: Anthony W. Sydes
Title: President
Address: PO Box 7122 Jacksonville NC 28541
Phone: 910-455-6956
Signature:
Date: a
Note: The legally responsible party should not be a homeowners association unless more than 50% of
the lots have been sold and a resident of the subdivision has been named the president.
170TWNME
a Notary Public for the State of
County of ()M[ p VV do hereby certify that
e personally appeared before me this
day ofhL4& I�C.Y �, aor , and acknowledge the due execution of the
forgoing wet detention basin maintenance requirements. Witness my hand and official
seal.
SEAL
My commission expirese (Zwba 14,v 15
Form SW401-Wet Detention Basin O&M-Rev.4
77CEIVED
fIEC 2 2 .2011
BY:
Page 4 of 4
r
A'I
��y
NCDENR
STORMWATER MANAGEMENT PERMIT APPLICATION FORM
401 CERTIFICATION APPLICATION FORM
WETLAND SUPPLEMENT
This form must be fitted out, printed and submitted.
The Required Items Checklist (Part 111) must be printed, filled out and submitted along with all the required information.
Project name
Contact name
Phone number
Date
Drainage area number
Ryker Trace, Section I at Carolina Plantations
Anthony Sydes
910-455-6956
December 14, 2011
2
o�oF W A r�,9OG
{
o
r.
A.�. ,�-�z:.:_'�n;�_ �"� ,.��:�: �.�:-'r��•„_�t .;:.-���� ._.r:����:. - i;
Site Characteristics
Drainage area 103,303.00 ft2
Impervious area 27,681.00 ft2
Percent impervious 26.8% %
Design rainfall depth 1.50 inch
Peak Flow Calculations
1-yr, 24-hr rainfall depth
3.53
in
1-yr, 24-hr intensity
2.73
inlhr
Pre -development 1-yr, 24-hr runoff
1.77
ft3lsec
Post -development 1-yr, 24-hr runoff
2.95
W/sec
PrelPost 1-yr, 24-hr peak control
1.18
ft3lsec
Storage Volume: Non -SA Waters
Minimum required volume
3,758.00
ft3
Volume provided (temporary pool volume)
3,760.00 ft3 OK
Storage Volume: SA Waters Parameters
1.5" runoff volume
ft3
Pre -development 1-yr, 24-hr runoff volume
ft3
Post -development 1-yr, 24-hr runoff volume
ft3
Minimum volume required
ft3
Volume provided
ft3
Outlet Design
Depth of temporary poollponding depth (Dp,,,J
12.00 in
OK
Drawdown time
2.88 days
OK
Diameter of orifice
1.00 in
OK
Coefficient of discharge (Co) used in orifice diameter
0.60 (unitless)
calculation
Driving head (Ho) used in the orifice diameter calculation
0.33 ft
Provide calculations to support this driving head.
REC EIVED
DEC 2 2 .2011
Form SW401-Wetland-ftev-6-11116109 BY: : Parts I and II. Project Design Summary. Page 1 of 3
r
Surface Areas of Wetland Zones
Surface Area of Entire Wetland
4,699.00 ft'
OK
Shallow Land
1,879.00 ft'
OK
The shallow land percentage is:
40% %
Shallow Water
1,922.00 ftZ
OK
The shallow water percentage is:
41 % %
Deep Pool
Forebay portion of deep pool (pretreatment)
472.00 ft2
OK
The forebay surface area percentage is:
10% %
Non-forebay portion of deep pool
426.00 ft2
OK
The non -forebay deep pool surface area percentage is:
9% %
Total of wetland zone areas
4,699.00 ft2
OK
Add or subtract the following area from the zones 0.00 ft2
Topographic Zone Elevations
Temporary Pool Elevation (TPE)
Shallow Land (top)
40.50 ft amsl
Permanent Pool Elevation (PPE)
Shallow Water/Deep Pool (top)
39.50 ft amsl
Shallow Water bottom
39.00 ft amsl
Most shallow point of deep pool's bottom
37.50 ft amsl
Deepest point of deep pool's bottom
37.50 ft amsl
Design must meet one of the following two options:
This design meets Option #1,
Y (Y or N)
Top of PPE is within 6" of SHWT, If yes:
SHWT (Seasonally High Water Table)
40.00 ft amsl
OK
This design meets Option #2,
N (Y or N)
Wetland has liner with permeability < 0.01 in/hr, If yes:
Depth of topsoil above impermeable liner
4.00 in
OK
Topographic Zone Depths
Temporary Pool
Shallow Land
12.00 in
OK
Permanent Pool
Shallow Water
6.00 in
OK
Deep Pool (shallowest)
18.00 in
OK
Deep Pool (deepest)
24.00 in
OK
Planting Plan
Are cattails included in the planting plan?
N (Y or N)
OK
Number of Plants recommended in Shallow Water Area:
Herbaceous (4*cubic-inch container)
481
Number of Plants recommended in Shallow Land Area:
Herbaceous (4'cubic-inch container), OR
470
Shrubs (1 gallon or larger), OR
75
Trees (3 gallon or larger) and Herbaceous (4+ cubic -inch)
9 and
360
Number of Plants provided in Shallow Water Area:
Herbaceous (4'cubic-inch container)
481
OK
Number of Plants provided in Shallow Land Area:
Herbaceous Wcubic-inch container)
70
More required if not planting shrubs or trees.
Shrubs (1 gallon or larger)
64
More required if not planting herb. and/or trees.
Trees (3 gallon or larger) and
0
More required if not planting herb, and/or shrubs.
Grass -like Herbaceous (4+ cubic -inch)
0
More recommended if planting trees.
RECEIVED
DEC 22.2011
BY:
Form SW401-Wetland-Rev.6-11I16/09
Parts I and !I. Project Design Summary, Page 2 of 3
Additional Information
Can the design volume be contained?
Y
(Y or N)
OK
Does project drain to SA waters? If yes,
N
(Y or N)
Excess volume must pass through filter.
What is the length of the vegetated filter?
ft
Are calculations for supporting the design volume provided in the
Y
(Y or N)
OK
application?
Is BMP sized to handle all runoff from ultimate build -out?
Y
(Y or N)
OK
Is the BMP located in a recorded drainage easement with a
Y
(Y or N)
OK
recorded access easement to a public Right of Way (ROW)?
The length to width ratio is:
2.46 :1
OK
Approximate wetland length
113.00 ft
Approximate wetland width
46.00 ft
Approximate surface area using length and width provided
5,198.00
z
ft
This approx. surface area is within this number of square feet
of the entire wetland surface area reported above:
Will the wetland be stabilized within 14 days of construction?
Y
(Y or N)
OK
REC EIv-D
DEC 2 2 1011
BY:
Form SW401-Wetland-Rev.6-11116109 Parts I and 11. Project Design Summary, Page 3 of 3
Permit No.
(to be provided by DWQ)
III. REQUIRED ITEMS CHECKLIST
Please indicate the page or plan sheet numbers where the supporting documentation can be found. An incomplete submittal package will
result in a request for additional information. This will delay final review and approval of the project. Initial in the space provided to
indicate the following design requirements have been met. If the applicant has designated an agent, the agent may initial below. If a
requirement has not been met, attach justification.
Initials Pagel Plan
Sheet No.
�•� 1 Z � �
f
T�
1. Plans (1" - 50' or larger) of the entire site showing:
Design at ultimate build -out,
Off -site drainage (if applicable),
Delineated drainage basins (include Rational C coefficient per basin),
- Wetland dimensions (and length to width ratio),
- Pretreatment system,
- Maintenance access,
Proposed drainage easement and public right of way (ROW),
- Overflow device, and
Boundaries of drainage easement.
4 J21 13
2. Plan details (1" = 50' or larger) for the wetland showing:
Wetland dimensions (and length to width ratio)
Pretreatment system,
Maintenance access,
Proposed drainage easement and public right of way (ROW),
Design at ultimate build -out,
Off -site drainage (if applicable),
Overflow device, and
RECEIVED
Boundaries of drainage easement.
DEC 2 2 Z,911
3. Section view of the wetland (1" = 20' or larger) showing:
Side slopes, 3:1 or lower
BY
Wetland layers
All wetlands: Shallow land depth, shallow water depth, deep pool depth
Option 1, no clay liner: SLWT depth
Option 2, clay liner: Depth of topsoil on top of liner, liner specifications
lr
L 3
4. A detailed planting plan (1" = 20' or larger) prepared by a qualified individual
showing:
A variety of several suitable species (not including cattails),
Sizes, spacing and locations of plantings,
Total quantity of each type of plant specified,
A planting detail,
The source nursery for the plants, and
Fertilizer and watering requirements to establish vegetation.
2, 13 5. A construction sequence that shows how the wetland will be protected from sediment until the entire
drainage area is stabilized.
En C.
6. The supporting calculations (including drawdown calculations).
1FVVC.-
7. A copy of the signed and notarized operation and maintenance (O&M) agreement.
Enc'
8. A copy of the deed restrictions (it required).
�nC
9. A soils report that is based upon an actual field investigation and soil borings. County soil maps are not an
acceptable source of soils information.
SW401-Wetland-Rev,6-11/16/09
Part III, page 1 of 1
L�
PermitNumbe
(to be provided by 1)WQ)
Drainage Area Number:
Stormwater Wetland Operation and Maintenance Agreement
1 will keep a maintenance record on this BMP. This maintenance record will be kept in a log in a
known set location. Any deficient BMP elements noted in the inspection will be corrected, repaired or
replaced immediately. These deficiencies can affect the integrity of structures, safety of the public, and
the removal efficiency of the BMP.
Important maintenance procedures:
— Immediately following construction of the stormwater wetland, bi-weekly inspections will be
conducted and wetland plants will be watered bi-weekly until vegetation becomes established
(commonly six weeks).
— No portion of the stormwater wetland will be fertilized after the first initial fertilization that is
required to establish the wetland plants.
— Stable groundcover will be maintained in the drainage area to reduce the sediment load to the
wetland.
— Once a year, a dam safety expert should inspect the embankment.
After the stormwater wetland is established, I will inspect it monthly and within 24 hours after every
storm event greater than 1.0 inches (or 1.5 inches if in a Coastal County). Records of operation and
maintenance will be kept in a known set location and will be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall be repaired
immediately.
BMP element:
Potentialproblem:
How I will remediate theproblem:
Entire BMP
Trash/debris is present.
Remove the trash/debris.
Perimeter of wetland
Areas of bare soil and/or erosive
Regrade the soil if necessary to remove the
gullies have formed.
gully, and then plant a ground cover and
water until it is established. Provide lime
and a one-time fertilizer application.
Vegetation is too short or too long.
Maintain vegetation at an appropriate
height.
Inlet device: pipe or
The pipe is clogged (if applicable).
Unclog the pipe. Dispose of the sediment
Swale
offsite.
The pipe is cracked or otherwise
Replace the pipe.
damaged if applicable).
Erosion is occurring in the Swale (if
Regrade the Swale if necessary to smooth
applicable).
it over and provide erosion control
devices such as reinforced turf matting or
riprap to avoid future problems with
erosion.
DECEIVED
Form SW401-Wetland 0RM-Rev.4 DEC 2 2.2011 Page 1 of 3
BY:
BMP element: Potentialproblem:
Forebay Sediment has accumulated in the
forebay to a depth that inhibits the
forebay from functioning well.
Deep pool, shallow water
and shallow land areas
Embankment
Micropool
Outlet device
Receiving water
Erosion has occurred.
Weeds are present.
Algal growth covers over 50% of the
deep pool and shallow water areas.
Cattails, phragmites or other invasive
plants cover 50% of the deep pool and
shallow water areas.
Shallow land remains flooded more
than 5 days after a storm event.
Plants are dead, diseased or dying.
Best professional practices show that
pruning is needed to maintain optimal
vlant health.
Sediment has accumulated and
reduced the depth to 75% of the
original design depth of the deep
pools.
A tree has started to grow on the
embankment.
An annual inspection by appropriate
professional shows that the
embankment needs repair.
Evidence of muskrat or beaver activity
is present.
Sediment has accumulated and
reduced the depth to 75% of the
original design depth.
Clogging has occurred.
The outlet device is damaged
Erosion or other signs of damage have
occurred at the outlet.
Form SW401-Wetland O&M-Rev.4
RECEIVED
DEC 2 2.2011
BY:
Permit Number.
(to be provided hr DWQ)
How I will remediate theproblem:
Search for the source of the sediment and
remedy the problem if possible. Remove
the sediment and dispose of it in a location
where it will not cause impacts to streams
or the BMP.
Provide additional erosion protection such
as reinforced turf matting or riprap if
needed to prevent future erosion
problems.
Remove the weeds, preferably by hand. If
a pesticide is used, wipe it on the plants
rather than spraying.
Consult a professional to remove and
control the algal growth.
Remove invasives by physical removal or
by wiping them with pesticide (do not
spray) - consult a professional.
Unclog the outlet device immediately.
Determine the source of the problem:
soils, hydrology, disease, etc. Remedy the
problem and replace plants. Provide a
one-time fertilizer application to establish
the ground cover if necessary.
Prune according to best professional
practices.
Search for the source of the sediment and
remedy the problem if possible. Remove
the sediment and dispose of it in a location
where it will not cause impacts to streams
or the BMP.
Consult a darn safety specialist to remove
the tree.
Make all needed repairs.
Consult a professional to remove muskrats
or beavers.
Search for the source of the sediment and
remedy the problem if possible. Remove
the sediment and dispose of it in a location
where it will not cause impacts to streams
or the BMP.
Clean out the outlet device. Dispose of the
sediment off -site.
Repair or replace the outlet device.
Contact the NC Division of Water Quality
401 Oversight Unit at 919-733-1786.
Page 2 of
Permit Number:
(to be provided by DW )
I acknowledge and agree by my signature below that I am responsible for the performance of the
maintenance procedures listed above. I agree to notify DWQ of any problems with the system or prior
to any changes to the system or responsible party.
Project name: Ryker Trace, Section 1 at Carolina Plantations _
BMP drainage area ► umber: 2- Stormwater Wetland
Print name: AnthonyW. S des
Title: President
Address: PO Box 7122, Jacksonville NC, 28541
Phone: 910-455-6956 n
Signature:
Date:
Note: The legally responsible party should not be a homeowners association unless more than 50% of the lots have been
sold and a resident of the subdivision has been named the president.
a Notary Public for the State of
(� do hereby certify that
)ersonally appeared before me this day of
e the due execution of the forgoing stonnwater wetland
maintenance requirements: Witness my hand and official seal,
.9 '
•,•���f1ifltiitltt���`
SEAL
Ceuh� q41 V7 k?
My commission expires:DI//&r 14, A01-6
Form SW401-Wetland O&M-Rev.4
RECEIVED
DEC 2 2.2011
BY:
Page 3 of 3
�. r
!'
t �.
t '
Aw
�t
Johnson, Kell
From:
Sent:
To:
Subject:
Attachments:
Kelly,
Parker & Associates, Inc. [paitext@bizec.rr.coml
Thursday, April 19, 2012 11:05 AM
Johnson, Kelly
FW: RYKER TRACE I
Skaggs (Autos aved).xIsx
I have forwarded Haywood's email responding to information requested for the Skaggs Method. His excel spreadsheet is
also attached. The pond's actual distance from the wetlands almost doubles the required setback.
Also, regarding comment #2, the open space lots for the BMP's will be recorded with the lots at the time of Final Plat.
Please let me know if you need anything else.
Sincerely,
Jonathan L. McDaniel, PE/ rmh
Parker & Associates, Inc.
Engineers * Surveyors * Planners
(910) 455-2414
Firm License Number - F-0108
From: Haywood Pittman [ma iIto: pittmansoil@yahoo.com]
Sent: Thursday, April 19, 2012 6:15 AM
To: John Parker
Subject: RYKER TRACE I
JONATHAN
I Have attached the completed spreadsheet for your review. I have revisited the site and obtained additional
information as outlined in the email from Kelly Johnson using information recommended by Dr. Skaggs. If any
additional information is needed please let me know.
Haywood Pittman LSS
Pittman Soil Consulting
PO Box 1387
Richlands, NC 28374
(910) 330-2784
i'
SWB 111212 - Ryker Trace Section I at Carolina Plantations
Add Info 02, 2/27/12
Description
Variable
Example 1
(p.10 Ska s're rt
Section 1-1
Section 2-2
CountyNew
Hanover
Onslow
Onslaw
Depth of Pit
d
Ift(ftt
20.00
16.00
16.DO
is the bat tam of the it inside the clayey impermeable Nyer?
Example Said that the
pkt is excavated down
to a ciayey
impermeable layer
Top of clayey Impermeable layer
msl
3
4
Bottom of clayey Impermeable layer
msl
1S
15
Bottom of it
msl
161
16
Distance Surface Wetland to Bottom Pit
h,
ft
22
14.2
15.3
Effective Lateral Hydraulic Conductivity
K
tn/hr
2.0
0.3
0.1
Effective Lateral Hydraulic Conductivity
K
ft/day
4.0
0.6
0.2
Orainable Porosity
f
0.03S
0.635
0.035
Surface Storage Depth
(Needed ro read T rs Table)
S
In
2.0
2.0
2.0
Water Table Elevation Above Impermeable Layer at Tts
h=ha(25cm or 10 In(
It
It
21.17
13.37
14.47
H=h/ho
H
-
0.962
0.941
0.946
D=d/h,
D
-
0.909
1.127
1.046
Boussinesq Parameter, 1/n-
1/n
0.960
1.060
1.050
Time to Drawdown to 25cm
Tis
days
3.2
4.1
3.7
Distance Surface Wetland to Water Level in Pit at Closure
it
2.0
56.0
Sfi.O
Required Setback for the Pit: D[sta nce from Ditch/3arrow Pit/Pond Where
Water Table Drawdown Is 25cm at time=Tts
x=sgrt((K/f)' h,'T25V(1/n)
x
it
93
29
17
Example 1
F-q—!. SeMeadc Hiram rk illis •c nqf.4 roc Pact Etaere of M pile
�p�iSUt,'tP+nlT
POND DEPTH MINUS SHWT
DERIVED FROM SOIL BORINGS
DERIVED FROM SOIL BORINGS
GROUND ELEVATION MINUS BOTTOM OF PROPOSED POND
General Data: Impervious, Drainage Area and Volume
PROJECT NUMBER: SW8
111212
Reviewer:
K. Johnson
DRAINAGE BASIN:
White Oak
Current Date
23-Apr-12
Original Run Date:
11-Jan-12
DA Number
1
2
3
4
5
6
7
8
9
10
BMP Type
Wet Pond
Wetland
No BMP in
DA
No BMP In
DA
No BMP In
DA
No BMP in
DA
No BMP In
DA
No BMP In
DA
No BMP in
DA
No BMP In
DA
Receiving Stream
UT Half
Moon Cr
UT Halt
Moan Cr
Stream Index
19-6
19-6
Class
C; NSW
C; NSW
1.
Impervious Area
Proposed Impervious ALL IMPERVIOUS Total ftz:
502,907
27,681
0
0
0
0
0
0
0
0
Onsite Buildings
318,500
17,500
Onsite Streets
155,851
9,513
Onsite Parking
0
0
Onsite Sidewalks
18.556
668
Onsite Other
0
0
Future
10.000
0
Offsite
0
0
Existing
0
0
P.r vi I -Permitted Im ervious Oid Rule ft2�
0
0
0
0
0
0
0
0
0
0
Onsite Buildings
Onsite Streets
Onsite Parkin
Onsite Sidewalks
Onsite Other
Future
Offsite
Existin
P.ro ased Im ervious Subject t0 2008/P.hll Rule fee-
DraInane Area
Drainage Area Total ft :
502,907
1,271,986
27,681
103,303
0
0
0
0
0
0
0
0
Onsite ft:
1,271,986
103,303
Offsite f?:
0
P.r vious -Permitted Draina a Area Old Rule f 22-
0
0
0
0
0
0
0
0
0
0
Onsite fe
0
0
Offsite ftz:
0
0
Proposed DA (Being Added By Mod) , ft :
1,271.986
103.303
Draina a Area Subject to Old Rule f?:
0
0
0
0
0
0
0
0
0
0
Drainage Area Subject to New Rule ft2:
1.271,986
103,303
Percent Impervious Overall, per DA:
39.54%
26.80%
Volume Required
Volume Required, Old Rule ft3:
RvpwD,,,,bp,,,ent, Old Rule:
Design Storm Old Rule in:
Volume Rectuired, New Rule 113:
64,527
3,760
RvPral)mlopment. New Rule:
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
Rvpe., D—I.pm,nt, New Rule:
0.41
0.29
Design StormDa Rule, in:
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1,5
1.5
1.5
Design Storm 1 r24hr in:
Subject to SA? Y or N
N
N
Volume Requiredobpule, ft :
64,527
3,760
Volume Required,yn4h„ ft :
0
0
Volume Required, Total Old +New Rule ft3:
64,527
3,760
Wet Ponds
PROJECT NUMBER: SW8
111212
Reviewer:
K. Johnson
DRAINAGE BASIN:
White Oak
Current Date
23-Apr-12
Original Run Date:
11-Jan-12
DA Number
1
2
3
4
5
6
7
8
9
10
BMP Type
Minimum Surface Area
Wet Pond
39.5%
Wetland
26.80%
No BMP In
DA
No BMP In
DA
No BMP In
DA
No BMP In
DA
No BMP In
DA
No BMP In
DA
No BMP to
DA
No BMP to
DA
% impervious
Lower Impervious
30.0%
20.0%
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Upper Impervious
40.0%
30.0%
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
TS5 85 or 90 :
90
Lower SAIDA
#NIA
#NIA
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Upper SA/DA
#NIA
#N/A
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
SA/DA ratio
#NIA
#NIA
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
PP Surface Area req, ft':
Stara a Calculations
Elevation, -l[op of Sediment bottom and jrT sl:
#NIA
28.00
#NIA
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Elevation, Bottom of shelf, fmsl:
39.00
Elevation, Permanent Pool, fmsl:
39.50
Elevation, Top of Shelf, fmsl:
40.00
Elevation, Temp. Pool, fmsl:
42.50
Area, Top of Sediment bottom pond),
2,945
Area, Bottom of Shelf,
15,309
Area, Perm Pool, ft:
18,980
Area, Top of Shelf, :
22,410
Area, Tem .Pool, :
27,930
Volume Provided (Temp Pool), DWQ Calculated, ft3:
73,273
0
0
0
0
0
0
0
0
0
Volume Provided(Temp Pool), Provided per Consultant, ft3:
73,272
Volume Required TernPool), DWO Calculated, fi :
64,527
3,760
Consultant Provided Enough Volume?
Y
Average Depth Option f or Option 2 Enter 1 or 2?
2
Average Depth Provided, ft:
0.0
Average Depth - OPTION 1 -, DWQ Calculated, ft:
5.74
#DIVID!
#DIWO!
#DIV10!
#DIV/O!
#DIV/O!
#DIV/O!
I #DIVIO!
#DIVIO!
#DIV10!
Average Depth - OPTION 2 -, DWQ Calculated, ft:
Forebay Volume
Permanent Pool Volume, ft:
7.0
108,969
#DIV10!
0
#DIVIO!
0
#DIV10!
0
#DIVIO!
0
#DIV/O!
0
#DIV/O!
0
#DIVIO!
0
#DIV/O!
0
#DIVIO!
0
Forebay Volume, Required, ft3:
21,794
0
0
0
01
0
0
0
0
0
Forebay Volume, Provided, ft3:
21,701
Percent of Permanent Pool 18-22% is Target):
20%
#DIV10!
#DIVIO!
#DIVIO!
#DIV/O!
#DIVIO!
#DIVIO!
#DIVIO!
#DIVIO!
#DIV/0!
Max. Pump, hp:
1/3
NIAJ
NIA
NIA
NIA
N/A
NIA
NIA
N/A
NIA
Drawdown
Av era a Head, ft:
0.96
0.00
0.00
0.00
0.00
0.00
0,00
0.00
0.00
0.00
Average Flow Q2, ft3/sec:
0.373
0.022
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Average Flow Q5, ft /sec:
0,149
0,009
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Q2 Area, in :
11.408
#DIVIO!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
05 Area, in :
4.563
#DIV/O!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
No. of Orifices
1
Orifice Diameter, in:
3.00
Orifice Area, in 2:
7.069
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
Weir Height, in:
Weir Length, in:
Weir C:
#DIVIO!
#DIV/O!
#DIV/O!
#DIVIO!
#DIVIO!
#DIVIO!
#DIVIO!
#DIV10!
#DIV/O!
#DIVIO!
Weir L, Effective Len th, ft:
-0.192
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
Average Orifice Flowrate, DWQ Calc (Qowo) ft1sec:
0,231
0,000 1
0.000
0.000
0,000
0.000
0.000
0.000
0.000
0.000
Average Orifice Flowrate, Reported (QRep rted) ft lsec:
0.240
Average Orifice Flowrate is Adequate? sea Range in calc
lose Enough?
Runoff Coefficient Cc:
0,250
0,250
0,250
0.250
0.250
0,250
0.250
0.250
0,250
0,250
1 yr 24 hr rainfall depth, in:
3.80
1 yr 24 hr Intensity 1in/hr:
0.158
0,000
0.000
0.000
0.000
0.000
0,000
0.000
0.000
0,000
1 yr 24 hr Pre -Development (Q), ft3lsec:
1.156
0.000
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Avg. Orifice flow<Pre Q?
OK
N
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Drawdown, days:
3.23
#DIV/01
#VALUEI
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Soils Report Data
Ground Elevation at Boring in Soils Re out, fmsL
45.70
Distance Ground to SHWT per Soils Report, in:
74.40
Distance Ground to SHWT per Soils Report, ft:
6.20
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
SHWT Elevation, DWQ Calculated, fmsl:
39.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
SHWT Elevation, Reported by Consultant, fmsl:
39.50
Distance SHWT to PP, ft:
Design OK if.- 0<= Value <= 0.5
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Permanent Pool Elevation, fmsl:
39.50
0.00
0.001
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Pump
Max HP:
1/3
NIA
N/A
N/A
NIA
NIA I
NIA
NIA
NIA I
NIA
Constructed Wetland
PROJECT NUMBER: SW8
111212
Reviewer:
K. Johnson
DRAINAGE BASIN:
White Oak
Current Date
23-A r-12
Original Run Date:
11-Jan-12
DA Number
1
2
3
4
5
6
7
8
9
10
BMP Type
Wet Pond
Wettand
N* eIMP in
DA
No BMP In
CA
No BMP In
DA
No BMP In
DA
No BMP In
DA
No BMP In
CA
No BMP In
DA
No BMP in
CA
Surface Areas
Ponding Depth, ft:
1.00
Area to Provide, Minimum, ft2:
313
Area Required, Deep Pool Non-Foreba , 5% Minimum, fe:
16
Area Required, Deep Pool Foreba , 10% Minimum, fi :
31
Area Required, Shallow Water Area, =40%, ft2:
125
Area Required. Shallow Land, 30% Minimum, ft2:
94
Area Provided, ft2:
4,699
Area Provided, Deep Pool Non-Foreba , ft2:
426
Area Provided, Deep Pool Foreba , ft2:
472
Area Provided, Shallow water Area, ft2:
(perm &2ool surface area
1,922
Area Provided, Shallow Land, ft2:
ternool surface area
1,879
% Provided, Deep Pool Non-Foreba between 5-15%
9.1%
% Provided, Deep Pool Foreba between 10-15%
10.0%
% Provided, Shallow Water, = 40%
40.9%
% Provided, Shallow Land, between 30-40%
40.0%
Area Adequate?, Deep Pool Non-Foreba :
TRUE
Area Adequate?, Deep Pool Foreba :
TRUE
Area Adequate?, Shallow Water:
TRUE
Area equate?, a ow an :
Depth & Elevation
Bottom of Deep Pool fmsl
TRUE
37.5
Bottom of Shallow Water, fmsl:
39.0
Top Shallow Water
=Bottom Shallow Land),Perm Pool Elev, fmsl:
39.5
Top Shallow Land
=Bottom Upland), Temp Pool Elev, fmsl:
40.5
Top Upland, fmsl:
Depth, Deep Pool between 1,5' and 3' ft:
1.50
Depth, Shallow Water, between 0,25' and Of),ft:
0.50
Depth, Shallow Land 1' max ft:
1.00
Depth, Upland(optional),ft:
SHWT elevation fmsl:
40.00
Depth Adequate?, Deep Pool:
TRUE
Depth Adequate?, Shallow Water:
TRUE
Depth Adequate?, Shallow Land:
Y
Volume Provided
3,760
Volume Provided(Temp Pool), DWO Calculated, ft3:
Volume Provided (TeMp Pool), Provided per Consultant, ft3:
3,760
Volume R uired TernPool), DWO Calculated, ft3:
64.527
3,760
Consultant Provided Enough Volume?
Drawdown
Y
Head, Average on Orifice, ft:
0.32
Average Flow 02, ft lsec:
0.373
0,022
Average Flow 05, ft lsec:
0.149
0,009
02Area, in :
1,151
05 Area, in :
0,461
No. of Orifices
1
Orifice Diameter, in:
1.00
Orifice Area, in2:
0.000
0.785
0.000
0.000
0.000
0.000
0,000
0.000
0.000
0.000
Weir Height, in:
Weir Len th in:
Weir C Value:
#DIV101
Weir L', eff. Length, ft:
Average Orifice Flowrate, DWQ Calc (Qo n) ftlsec:
0.015
Average Orifice Flowrate, Reported ft lsec:
0.015
Average Orifice Flowrate is Adequate?
Y
Drawdown, days:
2.93
Number of Plants:
Required, Herbaceous Plants:
=
��L
9.40
Required, Shrubs & Small Trees:
6.27
Required, 2.5" cal. Trees:
1.57
Provided, Herbaceous Plants:
64
Provided, Shrubs & Small Trees:
0
Provided, 2.5" cal. Trees:
0
ROY COOPER
Governor
MICHAEL S. REGAN
5ecmary
S. DANIEL SMITH NORTH CAROLINA
Director Env&-une►etai QuaW
September 12, 2019
Carolina Plantation Development Corporation
ATTN: Anthony Sydes, President
PO Sox 7122
Jacksonville, NC 28540
Subject: Notice of Inspection
SW8 110615
Bristol Heights of Carolina Plantations
SW8 120710
Ryker Trace Section H at Carolina Plantations
SW8 100714
Great Neck 11, Regal Hill, Tinley Estates at Carolina Plantations
SW8 111212
• Ryker Trace Section I at Carolina Plantations
SW8 100510
Great Neck I, Crown Park, The Burroughs at Carolina Plantations
SW8 101 110
Monarch Meadow at Carolina Plantation
Dear Mr. Sydes:
On September 11, 2019, the Wilmington Regional Office of the Division of Energy, Mineral and Land
Resources (DEMLR) was contacted by the HOA to check on the status of the maintenance items that
were due on September 6, 2019. The DEMLR has not received notification that this has been
addressed. Please find enclosed:
1. The May 6, 2019 letter containing the inspection detailing what needs to be done,
2. The July 16, 2019 email discussing the September 6, 2019 due date, and
3. The August 28, 2019 return letter also discussing the September 6, 2019 due date.
Please inform this Office in writing before October _14- 2019, of the specific actions that will be
undertaken and the time frame that will be required to correct the deficiencies, including an
anticipated completion date. This due date corresponds with the recommended planting season
Please act now so that you do not miss the window to adeauately crow veaetation. If this is not
addressed, a Notice of Deficiency will be issued on Tuesday, October 15, 2019, which will begin the
permit violation enforcement process.
Failure to provide the requested information, or to respond to this letter with a plan of action,
including a timeline to resolve the identified deficiencies, by October 14, 2019, are considered
violations of the permit. If the requested information is not submitted to this office by the due date,
then DEMLR staff will re -inspect the site and may issue a Notice of Violation. Please also note that
any individual or entity found to be in noncompliance with the provisions of a stormwater
management permit or the stormwater rules is subject to enforcement action as set forth in NCGS
143 Article 21, including the assessment of civil penalties of up to $25,000 per day.
�� North Carolina Department of Environmentai Quality I Division of Energy, Mineral and Land Resources
•/ Wilmington Regional Office 1 127 Cardinal Drive Extension I Wilmington, North Carolina 28405
NORTH GViOlYLI
°�'•""�a"��0i4\ � 910.796.T115
If you have any questions, please contact me at the Wilmington Regional Office, telephone number
(910)-796-7331 or via email at kelly.p.johnson@ncdenr.gov.
Sincer ly,
e y j nson
Environ ekal Engineer
Enclosure: 5/6/19 Letter
7/16/19 Email
8/28/19 Letter
GDS\kpj: \\\Stormwater\Permits & Projects\201 1\110615 HD\2019 09 CD deficient 110615
\\\Stormwater\Permits & Projects\2012\120710 HD\2019 09 CEldeficient 120710
\\\Stormwater\Permits & Projects\2010\100714 HD\2019 09 CEldeficient 100714
\\\Stormwater\Permits & Projects\201 1\1 11212 FID\2019 09 CEI deficient 1 1 1212
\\\Stormwater\Permits & Projects\2010\100510 HD\2019 09 CEI deficient 100510
\\\Stormwater\Permits & Projects\2010\101 110 HD\2019 09 CEldeficient 101 110
CC:
Cameron VanOrsdel (via email only, cameron@premiermanagementnc.com)
Leah Quinn, (via email only, leahquirn@sydescommunities.com)
Richard Muni, PLS, Parker & Associates (via email only, office@parker acksonville.com)
WiRO Stormwater Permit File, SW8 110615
WiRO Stormwater Permit File, SW8 120710
WiRO Stormwater Permit File, SW8 100714
WiRO Stormwater Permit File, SW8 111212
WiRO Stormwater Permit File, SW8 100510
WiRO Stormwater Permit File, SW8 101110
ROY COOPED
Governor
MICHAEL S. REGAN
Secretary
S. DANIEL SMITH
interim Director
dIA
d•', SL4Tf' o-
4 s�
� tr
NORTH CAROLINA
Environmental Quality
May 6, 2019
Carolina Plantation Development Corporation
ATTN: Anthony Sydes, President
PO Box 7122
Jacksonville, NC 28540
Subject: Notice of Inspection — Request for Additional Information
SW8 110615 Bristol Heights of Carolina Plantations
SW8 120710 Ryker Trace Section II at Carolina Plantations
SW8 100714 Great Neck II, Regal Hill, Tinley Estates at Carolina Plantations
SW8 111212 Ryker Trace Section I at Carolina Plantations
SW8 100510 Great Neck I, Crown Park, The Burroughs at Carolina Plantations
SW8 101110 Monarch Meadow at Carolina Plantation
Onslow County
Dear Mr. Sydes:
After receiving State Stormwater Permit Transfer Applications for the subject projects on February 25,
2019, the Wilmington Regional Office of the Division of Energy, Mineral and Land Resources (DEMLR)
inspected the subject projects on April 9, 2019, They are located in Carolina Plantation in Onslow
County.
1. HOA Information Needed: The latest data for the HOA online with the NC Secretary of State is
from 2011. Please submit the meeting minutes showing current HOA President's name and
contact information. (The transfer applications were not signed by the incoming permittee,
Carolina Plantations Owners Association. They are all signed by the current permittee, Anthony
Sydes, the President of Carolina Plantation Development Corporation.)
2. Impervious Area per Lot: Each permit contains the following language, "The permittee is
responsible for the routine monitoring of the project for compliance with the built -upon area
limits, grading, and the storm drainage system established by this permit, the permit documents,
the approved plans, and the recorded deed restrictions. " I understand that there was some
confusion about the necessity of monitoringitracking the impervious area that has been
constructed on each lot. Since there is not a spreadsheet tracking impervious area that has been
constructed, we will have to identify an alternate path forward. Please determine the impervious
area constructed on 10% of the homes (the larger horses) in each permit per county records or
other means in order to demonstrate that the homes have been constructed within the appropriate
allocations. Please submit a summary with your resubmittal.
# Lots 10%
SW8100510
356
36
SW8 100714
141
14
SW8101110
209
21
SW8110615
207
21
SW8 111212
96
10
SW8120710
45
5
North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Q
roam» cuiax�+ d
Wilmington Regional Office 1 127 Cardinal Drive Extension I Wilmington, North Carolina 28405 �J
A F-m-KP1Fw—'e°" a\ r 910,796,7215
State Stormwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 3 of 10
Attachment A - Permit Transfer, 5W8 110615
1. Most Recent Issue Date: 10/16/12, Plan Revision to reallocate BUA
2. Expiration Date: 819121 (No Extension per Legislature)
3. Session Law 2011-256: Transfer to HOAs
a. 50% lots are sold to individuals? Yes
b. Common area transferred to HOA?
i. Please submit the common area deed showing that the HOA owns it (in Bristol Heights Section
1 B).
ii. What is the bookipage number of the common area deeds for this permit?
c. Permit is in compliance?
i. File Review:
1. Deed Restrictions:
a. Permit:
i. Bristol Heights: 4,500sfllot
ii. Bartlett Square: 3,379sfllot
b. Recorded: Ail restrictions are recorded. (See the Excel file for book/page.)
i. Bristol Heights: 4,500sflEot
ii. Bartlett Square: 3,379sfllot
2. 0&M on File? Yes
3. PE Certification, Bristol Heights:
a. On File? Yes
b. Deviations? No
c. Date: 1117113
d. After Most Recent Permit? Yes
4, PE Certification, Bartlett Square: Please submit the certification for Bartlett Square.
a. On File? No
b. Deviations?
c. Date:
d. After Most Recent Permit? -
ii. BUAILot Summary:
1. Number of Lots in Permit: 207
2. Number of Lots in Summary: 207 (plus one common area)
3. Notes: The 10/16/12 Plan Revision was a single letter that did not list the number of lots.
The previous version, 5/18112, listed 207 lots.
4. Field Inspection, 4/9119:
a. BUA:
i. Bristol Heights Section I: The built upon area appears to be consistent with the approved plan.
ii. Bartlett Square: The built upon area appears to be consistent with the approved plan.
b. SW Measures:
i. Bristol Heights Sect I:
1. Three (3) additional catch basins have been installed near Lot 406/510 not shown on the
approved plan. (digital files emaiied by the Engineer on 4115/2019 show the additional
catch basins and pipes). Please address this discrepancy. (No Photo)
2. Rip rap apron at the outlet structure of the pond was not visible. Please ensure that the
rip rap apron is installed appropriately. (See Photo)
ii. Bartlett Square:
1. Stormwater structures are located per the approved plan.
2. Swales at the rear of the lots have not been installed or require slope maintenance
(between Lots 6771678, between Lots 6401641, and between Lots 636/637). (See
Photos)
c. OEM:
i. Bdstoi Heights Sect I: Please repair the slopes of swales at the rear of the lots. Please reinstall the
rip rap apron at the outlet pipe and repair the erosion at the outlet pipe.
ii. Bartlett Square: Measures appear to be maintained.
State Stormwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 4 of 10
Attachment B - Permit Transfer, SW8120710
1. Most Recent Issue Date: 12/3114
2. Expiration Date: 10/20/10 (No Extension per Legislature)
3. Session Law 2011-256: Transfer to HOAs
a. 50°% lots are sold to individuals? Yes
b. Common area transferred to HOA?
i. Please submit the common area deed showing that the HOA owns it (in Ryker Trace Section II).
ii. What is the book/page number of the common area deeds for this permit?
c. Permit is in compliance?
i. File Review:
1. Deed Restrictions:
a. Permit: 3,500sf1Lot
b. Recorded:
1. Please submit the recorded deed restrictions.
ii. Please submit the data shaded in yellow in the Excel file.
2. 0&M on File: Yes
3. PE Certification:
a. On File? Yes
b. Deviations? No
c. Date: 5122/17
d. After Most Recent Permit? Yes
ii. BUAILot Summary
1. Number of Lots in Permit: 45
2. Number of Lots in Summary: 45 (plus one common area lot)
4. Field Inspection, 419119:
a. BUA: The built upon area appears to be consistent with the approved plan.
b. SW Measures: The rip rap apron and the trapezoidal swale at the outlet of the stormwater pond is absent or
requires maintenance. The eastern inlet pipe is not visible and the slopes near the inlet pipe location have
failed.
c. 0&M: The rip rap apron and trapezoidal swale at the outlet pipe of the stormwater pond require
maintenance. Please repair slopes to provide an outlet for the eastern inlet pipe of the stormwater pond.
State Stormwater -Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 5 of 10
Attachment C - Permit Transfer, SW8100714
1. Most Recent Issue Date: 215115
2. Expiration Date: 12/31/21 (Extension Previously Granted)
3. Session Law 2011-256: Transfer to HOAs
a. 50% lots are sold to individuals? Yes
b. Common area transferred to HOA?
i. Please submit the common area deeds showing that the HOA owns them.
ii. What are the book/page numbers of the following common area deeds for this permit?
1. Common area, Great Neck Sec2A:
2. Common area, Great Neck Sec2B (Deed #1):
3. Common area, Great Neck Sec2B (Deed #2):
4. Common area, Regal Hill:
5. Common area, Tinley (Deed #1):
6. Common area, Tinley (Deed #2):
c. Permit is in compliance?
i. File Review:
1. Deed Restrictions: The permit lists "Great Neck Section II", but it appears that it should
have been "Great Neck Section 1113". Please confirm. if this is the case, I will issue a
correction with the transfer.
a. Permit:
i. Great Neck Section II (Lots 142-231): 4,500 sf; (90 lots)
ii. Regal Hill (Lots 247-274): 3,500 sf; (28 lots)
iii. Tinley Estates (Lots 1-23): 4,500 sf (23 lots)
b. Recorded: Great Neck Section 11 was included in the summary, but it does not
appear to have been included in the permit. Please clarify which permit
Section IIA is permitted under.
i. Great Neck Section 11
1. Section IIA (Lots 166-199): 4,500sf (34 lots)
2. Section IIB (Lots 142-231): 4,500sf (90 lots)
ii. Regal Hill (Lots 247-274): 3,500 sf; (28 lots)
iii. Tinley Estates (Lots 1-23): Please submit these restrictions.
2. O&M on file: Yes
3. PE Certifications: Both certifications were completed in 2014. But, the permit was
modified in 2015. That modification does not appear to have changed the design of the
systems. However, both certifications have the item, "The drainage area to the system
contains no more than the permitted amount of built -upon area." This element of the
certification was changed in 2015. Please submit the updated certifications.
a. Two Wet Pond
i. On File? Yes
ii. Deviations? No
iii. Date: 9/17/14
iv. After Most Recent Permit? No
b. One Stormwater Wetland
i. On File? Yes
ii. Deviations? No
iii. Date: 11114/14
iv. After Most Recent Permit? No
ii. BUAILot Summary
1. Number of Lots in Permit: 141
2. Number of Lots in Summary: 141 (plus six common areas)
State Stormwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 6 of 10
4. Field Inspection, 419/19:
a. BUA:
i. Great Neck Section II: The built upon area appears to be consistent with the approved plan.
ii. Regal Hill: The built upon area appears to be consistent with the approved plan.
iii. Tinley Estates: The built upon area appears to be consistent with the approved plan.
b. SW Measures:
i. Great Neck Section Il: Additional catch basins and pipes have been installed not shown on the
.approved plan. (Digital files emailed by the Engineer on 411512019 show the additional catch
basins and pipes). Please address this discrepancy.
iii. Regal Hill: The stormwater measures appear to be constructed in accordance with the approved
plans.
iii. Tinley Estates: The stormwater measures appear to be constructed in accordance with the
approved plans.
C. O&M:
is Great Neck Section II: A large hole has formed next to the manhole over near the stormwater
wetlands. The outlet structures of wet detention basin #1 and 92 lack riprap aprons and require
repairs. The orifice of the stormwater wetlands appear to be clogged and the wetland vegetation is
absent in some areas. Please maintain these items.
ii. Regal Hill: Measures appear to be maintained.
iii. Tinley Estates: Measures appear to be maintained.
State Stormwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 7 of 10
Attachment D • Permit Transfer, SW8111212
1. Most Recent Issue Date: 4/23/12
2. Expiration Date: 4/23/2020 (No Extension per Legislature)
3. Session Law 2011-256: Transfer to HOAs
a. 50% lots are sold to individuals? Yes
b. Common area transferred to HOA?
I. Please submit the common area deed showing that the HOA owns it.
ii. What is the book/page number of the common area deed for the common area in Ryker Trace
Section IC?
c. Permit is in compliance?
i. File Review:
1. Deed Restrictions:
a. In Permit:
I. Ryker Trace 1A: 3,500sf
ii. RykerTrace 1B: 3,500sf
iii. RykerTrace 1C: 3,500sf
b. Recorded:
i. RykerTrace 1A: 3,500sf
ii. RykerTrace1B: 3,500sf
iii. Ryker Trace 1 C:
1. Please submit the deed restrictions.
2. Please provide the data shaded in purple in the Excel file.
2. 0&M on file: Yes
3. PE Certification: There are two certifications on file. One is for the wetland. The other is
for "Ryker Trace, Section I at Carolina Plantations" (which does not specify that it is for
the wet pond). Please verify that the 4/8113 certification was for the wet pond.
a. Stormwater Wetland
i. On File? Yes
ii. Deviations? No
iii. Date: 4125/13
iv. After Most Recent Permit? Yes
b. Wet Pond
i. On File? Yes (need clarify)
ii. Deviations? No
iii. Date: 418113
iv. After Most Recent Permit? Yes
ii. BUA1Lot Summary
1. Number of Lots in Permit: 96
2. Number of Lots in Summary:
a. Should be 96
b. Lots were omitted from the original Excel files. Emailed engineer 4/30/19.
4, Field Inspection, 419119:
a. Bt1A: The built upon area appears to be consistent with the approved plan.
b. SW Measures: Please address the following issues:
i. The Swale leading to the stormwater wetlands has not been constructed properly and water is
being diverted from the wetlands to the existing stream.
ii. The stormwater wetlands lack deep pools and vegetation.
iii. The stormwater wetland's orifice appears to be clogged.
c. 0&M: Please address the following issues:
i. The swale and stormwater wetlands require maintenance.
ii. Maintain the swale at the rear of Lots 7351736.
State Storrnwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 8 of 10
Attachment E - Permit Transfer, SW8100510
1. Most Recent Issue Date: PR 1115l13
2. Expiration Date: 6/21120 (Extension Previously Granted)
3. Session Law 2011-256: Transfer to HOAs
a. 50% lots are sold to individuals? Yes
b. Common area transferred to HOA?
i. Please submit the common area deeds showing that the HOA owns them.
ii. What are the book/page numbers of the following common area deeds for this permit?
1. Burroughs Section 2A:
2. Burroughs Section 2B:
3. Great Neck Section 1 (Deed #1):
4. Great Neck Section 1 (Deed #2):
5. Great Neck Section 1 (Deed #3):
6. Great Neck Section 1 (Deed #4):
c. Permit is in compliance?
i. File Review:
1. Deed Restrictions:
a. In Permit:
L Crown Park: 3,500sf (103 lots)
ii. Great Neck Section I: 4,500sf (38 lots)
iii. Bentley Park: 10,000sf (16 lots)
b. Recorded: There are several recorded covenants on file. However, I cannot
line them up to the permitted lots. For instance, I have "Crown Park Section
III", "The Burroughs, Section iB", "The Burroughs at Carolina Plantations", "The
Burroughs, Section 1A", "Great Neck", and a variety of other titles that do not
match the section names in the permit. Also, the permit shows that there are
157 lots in the permit. But, the summary indicates 362 lots. Please address
this discrepancy by providing:
i. Clarification on the recorded restrictions
ii. The data in green in the Excel file.
Row Lab eb
swa 100510
1 Bentle ark Secl
BentleyPark Sec2
Burroughs S1A
Burroughs SIB
Burroughs SIC
Burroughs S2A
Burroughs S2B
CrownPark Secl
CrownPark Sec2
CrownPark Se-c3
GreatNeck Secl
2. O&M on file: Yes
X Count of OBJEC71D
362
11
2
54
18
72
25
35
26
59
18
42
State Stormwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 9 of 10
3. PE Certification:
a. Pond 1: The certification was completed in 2113/12. But, the permit was
modified in 2013. That modification does not appear to have changed the
design of the systems. However, the certification has the item, "The drainage
area to the system contains no more than the permitted amount of built -upon
area." This element of the certification was changed in 2013. Please submit
the updated certification.
i. On File? Yes
ii. Deviations? Project Area Not Fully Constructed
iii. Date: 2113/12
iv, After Most Recent Permit? No
b. Pond 2
i. On File? Yes
ii. Deviations? No
iii. Date: 5/21 /13
iv. After Most Recent Permit? Yes
c. Ponds 3 & 4
i. On File? Yes
ii. Deviations? No
iii. Date: 11/19/13
iv. After Most Recent Permit? Yes
ii. BUAILot Summary: Please address this discrepancy.
1. Number of Lots in Permit: 157 Lots Total
2. Number of Lots in Summary: 356 (plus 6 common area lots)
4. Field Inspection, 419/19:
a. BUA:
i. Great Neck Sect I: the built upon area appears to be consistent with the approved plan.
ii. Crown Park: the built upon area appears to be consistent with the approved plan.
iii. Bentley Park: the built upon area appears to be consistent with the approved plan.
iv. The Burroughs Sect. I: the built upon area appears to be consistent with the approved plan
v. Office at Carolina Plantation: the built upon area appears to be consistent with the approved plan.
b. SW Measures.- Please address the following issues:
i. Great Neck Sect. 1: Repair the level spreader and vegetated filter at the outlet structure of
stormwater detention pond #2. Repair the level spreader and vegetated filter at the outlet structure
of stormwater detention pond #1. Repair erosion adjacent to the wetlands and stream at both
outlets. The portion of flume is blocked near CB #29. CB #24 has second CB. CB#9 has second
CB. CB#8 has second CB.
ii. Crown Park: Repair the scour hole flow spreader at the end of the outlet pipe of stormwater
detention pond #3.
iii. Burroughs Sect. I: Repair the rock hole flow spreader, vegetated filter and rock check dam at the
outlet structure of stormwater detention pond, Repair the existing dislodged corrugated metal pipe
within the stream. Remove sediment from stream and repair erosive slopes.
iv. Carolina Plantation Office Building: a pipe and curb outlet on the north side of the parking lot
leading stormwater detention pond #3 has been constructed and are not shown on the approved
plan.
c. OW Please address the following issues:
i. Great Neck Section I: Repair the level spreader and vegetated filter at the outlet structure of
stormwater detention pond #2. Repair the level spreader and vegetated filter at the outlet structure
of stormwater detention pond #1. Repair erosion at the wetlands and stream near both of the
failed outlet structures.
6. Crown Park: Repair scour hale flow spreader at the outlet pipe of stormwater detention pond #3.
iii. Burroughs Sect is Repair the rock hole flow spreader, vegetated filter and rock check dam at the
outlet structure of the stormwater detention pond. Repair the existing dislodged corrugated metal
pipe within the stream. Remove sediment from the stream and repair erosive slopes.
State Stormwater Permit No.
SW8 110615, SW8 120710, SW8 100714, SW8 111212, SW8 100510, and SW8 101110
Page 10 of 10
Attachment F -Permit Transfer, SW8101110
1. Most Recent Issue Date: 6127111 PR to reallocate
2. Expiration Date: 12/8/2020 in Permit, Need to Extend to 6/1812
3. Transfers:
a. Session Law 2011-256: Transfer to HOAs
i. 50% lots are sold to individuals? Yes
b. Common area transferred to HOA?
1. Please submit the common area deeds showing that the HOA owns them.
ii. What are the book/page numbers of the following common area deeds for this permit?
1. Monarch Meadows Section 1A
2. Monarch Meadows Section 26
c. Permit is in compliance?
i. Permit Correction Needed: The permit was originally written in 2010. That permit said, "The
subdivision is permitted for 130 lots (current section) and 81 lots (future section), each allowed a
maximum of 3,500 square feet of built -upon area." It was modified in 2011 to show, "the final
layout and built -upon -area allocation for Section II of the approved Monarch Meadow plan." The
2011 Plan Revision was a single cover letter. It did not update the permit text; however, it should
have done so in order to clarify that the deed restrictions from the 2010 "future section" became
"Section 11" in 2011. 1 will clarify this in the permit when it is transferred.
ii. File Review:
1. Deed Restrictions:
a. Permit
i. Monarch Meadow Section 1: 3,500sf (130 lots)
ii. Monarch Meadow Section 2: 3,500sf (81 lots)
b. Recorded:
i. Monarch Meadow Section 1A: 3,500sf (46 lots)
ii. Monarch Meadow Section 1 B: 3,500sf (45 lots)
iii. Monarch Meadow Section 1C: 3,500sf (39 lots)
iv. Monarch Meadow Section 2A: 3,500sf (44 lots)
v. Monarch Meadow Section 213:
1. Please submit these restrictions.
2. Please submit the data shaded blue in the spreadsheet.
2. 0&M on file: Yes
3. PE Certification:
a. On File? Yes
b. Deviations? Yes
c. Date: 11/7113
d. After Most Recent Permit? Yes
iii. BUA/Lot Summary
1. Number of Lots in Permit: 209
2. Number of Lots in Summary: 209 (plus two common area lots)
4. Field Inspection, 419/19:
a. BUA: The built upon area appears to be consistent with the approved plan.
b. SW Measures: 'lease address the following issues:
i. The swales along the rear of the lots appear to be absent or in need of maintenance.
ii. The yard inlet at junction of pipes B8, B7 and B12 has failed and sinkhole has formed.
iii. The rip rap apron at the outlet pipe of the stormwater detention pond is absent or in need of
maintenance.
c. 0&M: Please address the following issues:
i. The swales and riprap apron require maintenance.
ii. Repair yard inlet at the junction of pipes B7, B8 and B12, fill sink hole and provide vegetative
cover.
Johnson, Kelly
From: Johnson, Kelly
Sent: Tuesday, July 16, 2019 8:47 AM
To: office@parkerjacksonville.com
Cc: leahquinn@sydescommunities.com; Tony Sydes (asydes4851 @gmail.com)
Subject: FW: [External] Carolina Plantations Stormwater Transfer (SW8 110615, SW8 100714,
SW8 120710, SW8 111212, SW8 100510, SW8 101110)
Rick, -
I received a large package yesterday that looks like it is a single submittal for six permit actions, but this is not a
complete package? Below, I have re -Formatted the list of items in your previous email to organize each item per
permit. The blue items were received. The red items were not received. (And, FYI, the green items were received but
are not needed. We do not need copies of documents that DEMLR has previously approved.)
I have not gone through the package to compare what was received to the May 6th additional information request
letter. If items requested in that letter were not received, please ensure that everything is submitted, For instance:
1. There are several permits that needed revised plan sheets to show the revised configuration, but no plan sheets
were submitted.
2. For SW8 100714, please clarify which permit Section IIA is permitted under.
3. For SW8 111212, there was a discrepancy in the number of lots in the Excel file provided v/s the permit.
4. For SW8 100510, there were additional discrepancies.
5. There maybe more instances. I only spot-checked the submittal.
ease consider this a second request for additional information and
A become complete after that, I will unfortunately have to return the
transfer application packages.
In the future it would be helpful to receive a separate package for each permit because they are all filed separately. In
cases like this we typically receive a single package, but binder -clipped sections labefed with which items go with which
permit.
Thanks,
Kelly
Minor Modification Applications Submitted:
a. SW8 110615: Bristol Heights of Carolina Plantations
i. Minor Niodification Application for SW8-1 10615 — Received but need original signature
ii. Certification (this wasn't on the list below, but it was received)
iii. Carolina Plantations H.O.A. Meeting Minutes
iv. :approved Name Change for Permit 4SW8-1 10615
b. _SW8 100714: Great Neck II, Regal Hill, Tinley Estates at Carolina Plantations
i. Minor ytodification Application for SW8-100714
ii. Common Area Deed for Regal Hill/Tinley Estates (SW8-100714)
iii. Restrictive Covenant Affidavit for SW8-100714
iv. Certification (this wasn't on the list below, but it was received)
v. Amendment to Declarations for Great Neck II/Regal Hill (SW8-100714)
vi. Carolina Plantations H.O.A_ Meeting lvlinutes
Additional Information R uest Responses
a. SW8 120710 Ryker Trace Section H at Carolina Plantations
i. Common Area Deed for Ryker Trace I (SW8-120710)
ii. Carolina Plantations H.O.A. Meeting Minutes
b_ SW8 111212 _Ryker Trace Section I at Carolina Plantations
i. Common Area Deed for Ryker Trace Section I (SW8-1 l 12121)
ii. Stormwater Wetland Swale Narrative for Ryker Trace, Section I (SW8-1 1 1212)
iii. Final Stormwater Certification for Ryker Trace I (SW8-1 1 1212)
iv. Carolina Plantations H.O.A. Meeting Minutes
c. SW8 100510 Great Neck I, Crown Park, The Burroughs at Carolina Plantations
i. Common Area Deed for Crown Park (SW8-100510)
ii. Common Area Deed for Crown Park/Burroughs (SW8-100510)
iii. Common Area Deed for The Burroughs I (SW8-100510)
iv. Certification (this wasn't on the list below, but it was received)
v. Carolina Plantations H.O.A_ Meeting Minutes
vi. approved Plan Revision for SW8-100510
vii. Approved Plan Revision and Extension for SW8-1W 10
d_ SW8 101110 Monarch Meadow at Carolina Plantation
i. Certification (this wasn't on the list below, but it was received)
ii. Carolina Plantations H.O.A. Meeting Minutes
3. Which permits do the_foliowina items support?:
a. Common Area Deed for The Burroughs 11 A&B — This wasn't in the package
b. Common Area Deed Book 4397. Page 895 for Great Neck 1. Regal Hill, Great Neck II -A. Monarch Meadow 1-A.
Great Neck 11-B. Bristol Heights I-B, Carolina Plantations Commercial Tract, Ryker Trace 11, Tinley Estates and
Burroughs I I -A. —This wasn't in the package
c. Restrictive Covenants Deed Book 3435, Page 457 for the above referenced sections. — This is a 50-page
document. If there are relevant portions per permit please list the page numbers per permit that are applicable.
d. Amendment to Restrictive Covenants Deed Book 3490, page 915 for the above referenced sections.
From: Johnson, Kelly
Sent: Thursday, July 11, 2019 11:17 AM
To: office@parkerjacksonville.com
Subject: RE: [External] Carolina Plantations Stormwater Transfer
Have the hard copies been mailed? I haven't seen them yet.
Thanks,
Kelly
From: Rick Muni fmailto:office@parkerlacksonville.com
Sent: Thursday, July 4, 2019 9:54 AM
To: Johnson, Kelly <kelly.p.johnson@ncdenr.gov>; Snider, Holley <holley.snider@ncdenr.gov>; Scott, Georgette
<georgette.scott@ ncdenr.gov>
Subject: [External] Carolina Plantations Stormwater Transfer
Ms. Johnson,
In response to your request for additional information dated June 7, 2019, we submit the following:
1) Carolina Plantations H.O.A. Meeting Minutes
2) Approved Name Change for Permit #SW8-110615
3) Minor Modification Application for SW8-110615
4) Common Area Deed for Ryker Trace [I (SW8-120710)
5) Cornmon Area Deed for Regal Hill/Tinley Estates (SW8-100714)
6) Restrictive Covenant Affidavit for SW8-100714
7) Amendment to Declarations for Great Neck H/Regal Hill (SW8-100714)
8) Minor Modification Application for SW8-100714
9) Common Area Deed for Ryker Trace Section I (SW8-111212)
10) Stormwater Wetland Swale Narrative for Ryker Trace, Section I (SW8-111212)
11) Final Stormwater Certification for Ryker Trace I (SW8-111212)
12) Common Area Deed for Crown Park (SW8-100510)
13) Common Area Deed for Crown Park/Burroughs (SW8-100510)
14) Approved Plan Revision and Extension for SW8-100510
15) Common Area Deed for The Burroughs I (SW8-100510)
16) Approved Plan Revision for SW8-100510
17) Common Area Deed for The Burroughs 11 A&B
18). Common Area Deed Book 4397, Page 895 for Great Neck I, Regal Hill, Great Neck II -A, Monarch
Meadow I -A, Great Neck 11-13, Bristol Heights I-B, Carolina Plantations Commercial Tract, Ryker Trace Il,
Tinley Estates and Burroughs [I -A.
19) Restrictive Covenants Deed Book 3435, Page 457 for the above referenced sections.
20) Amendment to Restrictive Covenants Deed Book 3490, page 915 for the above referenced sections.
Please review the enclosed information. Hard copies will follow as required.
Thanks.
Richard C. Muni, P.L.S. / dih
Parker & Associates, l[iuc
Jacksonville NC, 28540
Firm License Number F-0108
910-455-2414 - Office
3
ParkerJacksonville. com
virus -free. www.avast.com
ROY COOPER
Governor
MICHAEL S. PEGAN
Secretary
S. DANIEL SMITH
Director
August 28, 2019
NORTH CAROLINA
Environmental Quality
Carolina Plantation Development Corporation
ATTN: Anthony Sydes, President
PO Box 7122
Jacksonville, NC 28540
Subject: PROJECT RETUR-N
SW8 120710 Ryker Trace Section U at Carolina Plantations
SW8 l 1 1212 Ryker Trace Section I at Carolina Plantations
SW8 100510 Great Neck I, Crown Park, The Burroughs at Carolina Plantations
SW8 101110 Monarch Meadow at Carolina Plantation
Onslow County
Dear Mr. Svdes:
The Wilmington Regional Office received and accepted State Stormwater Management Transfer Permit
Applications for the subject projects on February 25, 2019 and requested additional information on May
6, 2019. A partial response was received on July 4, 2019. On July 16, 2019, I sent a second request for
additional information requesting both a complete response and collated responses with data organized
Per permit so that it could understand which items were submitted for each of the four permits. On
August I, 2019 we received another submittal which was also incomplete and not collated per permit.
We discussed the situation via email and over the phone with your consultant on several occasions in
August, and eventually set August 27, 2019 as the final response date. Unfortunately, complete responses
have not been received. The permits transfers cannot be issued for the projects as proposed. Per the
requirements of Title 15A NCAC 02H .1045(4)(a)(ii) of the Stormwater Management Rules, this Office is
hereby returning the subject application as incomplete. The four (4) $505.00 application fees have been
forfeited and new fees will need to be provided if you choose to resubmit these applications in the future.
Maintenance and Resubmittai:
1. #1v! h enance:7Please'1
Resubmittal:
a. Minor Modification: Please apply for minor modifications for any applicable projects to
correct the items discussed in the May 6ffi letter. Modifications need to be processed
before permit transfers. Modifications must also have an original signature per 15A
NCAC 02H .1040(1) as opposed to a photocopy or emailed copy. (7f you determine that a
major modification is needed in lieu of a minor modification as you address the May 6th
letter, then please submit the full major modification package including the fee.)
b. May 6, 2019 Letter: After obtaining the necessary modifications, please address the
items in the May 6, 2019 letter in your transfer resubmittals.
c. Collated Submittal: In order to clarify which documents submitted are for each of the
four permits, please collate the submittals such that they can be put directly into four
different folders. This will ensure that I review the intended items for each permit. For
instance, when we receive a package with a single roil of plans that do not have permit
numbers on there. I cannot ensure that I have everything that you intended to be reviewed
for that permit. Similarly, if there is a single stack of deed restrictions that are not labeled
per permit I cannot determine which documents were intended for each file. We will not
be able to accept incoming packages that are not collated per permit.
North Carolina Department of Environmental Quality 1 Division of Energy, Mineral and Land Resources
,ORTn CAAOU rn e
Wilmington Regional Office 1 127 Cardinal Drive Extension E Wilmington, North Carolina 28405
910.7963215
d. Plans: The plans must be sued, dated, sealed, and to scale. Please submit two copies
[15A NCAC 02H.1042(2)(g), .1042(2)(h), .1042(2)(1), .1042(2)(m), and .1050(16)]
If you.wish to pursue construction of this proposed project, you must reapply for a permit to the Division -
Your application package must include a completed and signed application form; supplement form;
signed O&M agreement; application fee; signed, sealed and dated calculations; and 2 sets of signed,
sealed and dated site layout and grading plans with details.
Please note that the most recent permits for each project remain in full force and effect. Please be aware
that the construction of any changes to the originally approved and permitted plans prior to the receipt of
a modified permit is a violation of NCGS 143-215.1 and is subject to enforcement action pursuant to
NCGS 143-215.6A.
If you have any questions concerning this matter, please contact Kelly Johnson at (910) 796-7215 or via
e-mail at kelly.p.johnson@ncdenr.gov.
S inceryely,
S. Daniel Smith, Director
Division of Energy, Mineral and Land Resources
GDS/kpj: 111StormwaterlPermits & Projects120121120710 HD12019 08 return_project 120710
WStormwaterTermits & Projects1201 111 11212 HD12019 08__ return —project 111212
WStormwaterTermits & Projects120101100510 HD12019 08 return_project 100510
WStormwaterTermits & Projects120101101110 HD12019 08_ return_project 101110
cc: Richard_ Muni, PLS, Parker & Associates
PO Box 976, Jacksonville, NC 28541-0976
Building Inspector, Onslow County Building Inspections
Onslow County Engineering
WiRO Stormwater Permit File, SW8 120710
WiRO Stormwater Permit File, SW8 111212
WiRO Stormwater Permit File, SW8 100510
WiRO Stormwater Permit File, SW8 101110
ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
S. DANIEL SMITH
Director
August 28, 2019
NORTH CAROLINA
Environmental Quality
Carolina Plantation Development Corporation
ATTNN: Anthony Svdes, President
PO Box 7122 J
Jacksonville_ \1C 28540
Subject: PROJECT RETURIN
SW8 120710 Rvker Trace Section II at Carolina Plantations
SW8 l 1 1212 Rvker Trace Section 1 at Carolina Plantations
SW8 100510 Great Neck 1, Crown Park; The Burroughs at Carolina Plantations
SW8 lOil 10 Monarch Meadow at Carolina Plantation
Onslow County
Dear Mr. Sydes:
The Wilmington Regional Office received and accepted State Stormwater Management Transfer Pennit
Applications for the subject projects on February 25, 2019 and requested additional information on May
6, 2019. A partial response was received on July 4, 2019. On July 16, 2019, 1 sent a second request for
additional information requesting both a complete response and collated responses with data organized
per permit so that it could understand which items were submitted for each of the four permits. On
August, I, 2019 we received another submittal which was also incomplete and not collated per permit.
We discussed the situation via email and over the phone with your consultant on several occasions in
August, and eventually set August 27, 2019 as the final response date. unfortunately, complete responses
have not been received. The permits transfers cannot be issued for the projects as proposed. Per the
requirements of Title 15A NCAC 02H .1045(4)(a)(11) of the Stormwater Management Rules, this Office is
hereby returning the subject application as incomplete. The four (4) $505.00 application fees have been
forfeited and new fees will need to be provided if you choose to resubmit these applications in the future.
Maintenance and Resubmittai:
1. Maintenance: Please be reminded that the maintenance issues raised in the May 6, 2019 letter are
due on September 6, 2019 as discussed in the Julv 16, 2019 email.
Resubmittal:
a. Minor Modification: Please apply for minor modifications for any applicable projects to
correct the items discussed in the May 6' letter. Modifications need to be processed
before permit transfers. Modifications must also have an original signature per 1 5A
NCAC 02H .1040(1) as opposed to a photocopy or emailed copy. (Ifyoi! determine that a
major modification is needed in lieu of a minor modification as you address the May 6"'
letter, then please suhinit the full major modification package including the fee.)
b. May 6, 20] 9 Letter: After obtaining the necessary modifications, please address the
items in the May 6, 2019 letter in your transfer resubmittals.
Collated Submittal: In order to clarify which documents submitted are for each of the
four permits, please collate the submittals such that they can be put directly into four
different folders. This will ensure that I review the intended items for each permit. For
instance, when we receive a package with a single roll of plans that do not have permit
numbers on them I cannot ensure that I have everything that you intended to be reviewed
for that permit. Similarly, if there is a single stack of deed restrictions that are not labeled
per permit I cannot determine which documents were intended for each file. We will not
be able to accept incoming packages that are not collated per permit.
e North Carolina Department ofEnvironmental Quality I Division of Energy, Mineral and Land Resources
/ Wilmington Regional Office 1 IZ7 Cardinal Drive Extension I Wilmington, North Carolina 28405
IJ(1FiSH CNRJLR'N
910.796.7215
Plans: The plans must be signed, dated, sealed, and to scale. Please submit two copies
[I5A NCAC 02H. 1 042(2)(g), .1042(2)(h), _I042(2)(i), .1042(2)(m), and .1050(16)]
If vou.wish to pursue construction of this proposed project, you must reapply for a permit to the Division.
Your application package must include a completed and signed application form; supplement form;
signed O&M agreement; application fee; signed, sealed and dated calculations; and 2 sets of signed;
sealed and dated site layout and grading plans with details_
Please note that the most recent permits for each project remain in full force and effect. Please be aware
that the construction of anv changes to the originally approved and permitted plans prior to the receipt of
a modified permit is a violation ofNCGS 143-215.1 and is subject to enforcement action pursuant to
NCGS i43-215.6A.
If you have any questions concerning this matter, please contact Kelly Johnson at (910) 796-7215 or via
e-mail at kelly.p.johnson@ncdenr.gov.
Since elY;
i
S. Daniel Smith. Director
Division of Energy, Mineral and Land Resources
GDS/kpj: %StormwaterTermits & Projects120121120710 HD12019 08 return_project 120710
m A\\Stormwater\Perits 8 Projects1201 I\1 1 1212 4D12019 08_ retumproject 1 1 1212
%StorTnwvaterTernnits R Projects120101100510 HD12019 08 retumproject 100510
%Stormwater-Termits R ProjectA20I0\101 1 10 I-1.D12019 08_ rerurn_project 101 1 10
cc: Richard Muni. PLS. Parker R. Associates
PO Boh 976, Jacksonville, NC 28541-0976
Building Inspector, Onslow County Building Inspections
Onslow County Engineering
WiRO SCorMWater Permit File, SW8 120710
WiRO Stormwater Permit File, SW8 1 1 1212
WiRO Stormwater Permit File, SW8 100510
WiRO Stormwater Permit File, S W8 101 1 10