HomeMy WebLinkAboutNCG120107_Tier II Relief Request and Sampling Interruption_20200928W. 7 WASTE MAINAGEMEINT September 28, 2020 Annette Lucas, PE Stormwater Program Supervisor NCDEQ- Division of Energy, Mineral and Land Resources 217 W Jones Street Raleigh, NC 27603 (Via email: annette.lucas@ncdenr.gov) Waste Management of Carolinas, Inc. 3597 Old Cedar Falls Road Randleman, NC 27317 RE: WASTE MANAGEMENT — GREAT OAK LANDFILL (NPOES CDC# NCG120107) RANDLEMAN, NC ADDITIONAL DOCUMENTATION - RELIEF FROM TIER II SAMPLING (MARCH 2020-AUGUST 2020) Dear Ms. Lucas: The purpose of this letter is to provide a response to your September 24, 2020, email (Attachment 1) requesting "a more detailed explanation as to how COVID prevented monthly sampling" at the Waste Management of Carolinas, Inc. — Great Oak Landfill facility. As you are aware, this was in response to our retroactive request for relief from the Tier II Monthly sampling requirements from March 2020 through August 2020. Great Oak Landfill operates with a full-time staff of approximately 14 specialized employees. The facility serves numerous counties and municipalities in the piedmont region of North Carolina. For all practical considerations, Great Oak is the only disposal option for these constituents without timely and onerous contract negotiations to change the flow of residential and industrial waste within the respective communities. From the onset of this pandemic, the corporate leadership at Waste Management has realized that an outbreak of COVID-19 at any given waste disposal facility (e.g., one with 14 employees that cannot be readily replaced) would have the potential for massive disruptions to local communities to which we are contracted. From the start of the virus outbreak, Great Oak has been under strict corporate mandates to cease all non -essential site visits by, not only our internal environmental and engineering staff, but also all contractors and consultants such as those performing the NPDES sampling at our site. It should be noted that the latter activities require safety briefings, site logins, and inevitable interactions with our full-time staff. Despite these precautions, COVID-19 was detected at our facility during this time. There were multiple cases of the virus on a construction crew that had been deemed essential as they were constructing a new time - critical landfill cell. Work on this project had to temporarily cease for quarantining of the impacted crew. ADDITIONAL DOCUMENTATION - RELIEF FROM TIER II SAMPLING (MARCH 2O20-AUGUST 2020) September 28, 2020 Page 2 of 2 In spite of increased site precautions and restrictions, multiple key members of our 14 person staff had to be quarantined to prevent another potential outbreak at our facility. Moreover, it was because the potential for the combined factors as outlined above, that the referenced stormwater sampling activities were temporarily halted. We would like to note that, although Great Oak halted the Tier II sampling with our contractor in March 2020, the facility continued with required weekly inspections of the outfalls (provided as Attachment 2). Further, an evaluation of storm events (provided as Attachment 3) illustrates that while sampling was suspended, no qualifying storm events transpired. As mentioned previously, all permit required compliance monitoring at the facility has now resumed. Great Oak Landfill appreciates the Division's consideration of relief on this matter and is prepared to promptly reply to any questions or concerns regarding this request. Should you have any questions or require clarification, please contact me at (984) 328-0129 or by email below. Sincerely, Waste Manageroent /'11OLI --- Don Mi enheimer Environmental Protection Manager dmisenhe@wm.com Attachments: 1. Original Relief Request Email 2. Weekly Outfall Inspection Forms 3. Storm Event Evaluation Cc: Bethany Georgoulias (NCDEQ-DEMLR) Michael McFeeley (Great Oak Landfill) ATTACHMENT 1 Original Relief Request (email) Misenheimer, Don From: Lucas, Annette <annette.lucas@ncdenr.gov> Sent: Thursday, September 24, 2020 10:09 AM To: Georgoulias, Bethany; Misenheimer, Don Cc: Morman, Alaina Subject: RE: [External] RE: Industrial Stormwater Monitoring Question: Don, Can you please provide a more detailed explanation as to how COVID prevented monthly sampling at your facility? We do have many facilities throughout the state who have been able to conduct sampling in a safe, socially distant manner. Sincerely, Annette Annette Lucas, PE Stormwater Program Supervisor Division of Energy, Mineral and Land Resources North Carolina Department of Environmental Quality Office: (919) 707-3639 Cell: (919) 817-2514 Fax: (919) 715-0999 Email: annette.lucasBncdenr.aov Web site: deg.nc.gov/SW Physical Address: 512 North Salisbury Street, Office 640L, Raleigh, NC 27604 Mailing Address: 1612 Mail Service Center, Raleigh, NC 27699-1612 From: Georgoulias, Bethany <bethany.georgoulias@ncdenr.gov> Sent: Thursday, September 24, 2020 8:21 AM To: Misenheimer, Don <dmisenhe@wm.com> Cc: Lucas, Annette <annette.lucas@ncdenr.gov>; Morman, Alaina <alaina.morman@ncdenr.gov> Subject: RE: [External] RE: Industrial Stormwater Monitoring Question: Don, I see the note you put on all those DMRs. I think that's a start, but the suspension will likely need more explanation am deferring to my supervisor and colleague to guide you further. 244wur rainfall Chemkal OMen I Fecal canferm amount, Demand Cakcnies WtOD m! Inchee 4 la 1000 �— 4652 00340 32616 .l ue t� Ub1 1D-19 and the safety ct J -- eat Oak employees and Contractors, I monthly Tier H sampling (85 W) has erg suspended. Crew Oak will aline to assess the available idance and w;ll resume sampling on we are able. st h"i-n wo.h the second eonsevotive benchmark exceedance fc Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 707 3641 office bethany.georgouliasPncdenr.gov 512 N. Salisbury Street, Raleigh, NC 27604 (location) 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) Website: http://deq..nc.gov/about/divisions/energy-mineral-land-resources/stormwater Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging time. From: Misenheimer, Don [mailto:dmisenhe@wm.com] Sent: Wednesday, September 23, 2020 2:34 PM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Subject: [External] RE: Industrial Stormwater Monitoring Question: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov Bethany: Thank you for your response- I am out in Georgia today with some bad service. I will be glad to prepare a letter tonight and get to you tomorrow with any additional documentation that I need to provide. Please find the attached zip file with the 2020 DMRs as submitted (the Tier 2 reports have a statement in red). We have resumed monthly monitoring earlier this month. Please let me know if I need to provide anything additional. I need to check with management on how much particulars I can share about the COVID that was present at our site, but I am sure I can provide an overview without difficulty. Thank you again for your time - DON M. MISENHEIMER Environmental Protection Manager (North Carolina and South Carolina) dmisenhe(a)wm.com C: 984.328.0129 From: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Sent: Wednesday, September 23, 2020 12:36 PM To: Misenheimer, Don <dmisenhe@wm.com> Cc: Lucas, Annette <annette.lucas@ncdenr.gov>; Morman, Alaina <alaina.morman@ncdenr.gov> Subject: RE: [External] Industrial Stormwater Monitoring Question: Don, The word we have from Division management is that suspensions in monitoring monthly as a result of COVID-19 restrictions may be excused, but the reasons should be clearly explained and documented. This explanation for the monitoring gap (and specifically which periods it impacted) can be sent to us (e-mail is fine), and we will keep it with the permit file. What are the permit numbers that you submitted the DMRs for? I can take a look at what you included on there and let you know if additional explanation is advised. Bethany Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 707 3641 office bethany.georgouliasOncdenr.gov 512 N. Salisbury Street, Raleigh, NC 27604 (location) 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) Website: http/Ideq..nc.gov/about/divisions/energy-mineral-land-resources/stormwater Yam„ Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging time. From: Misenheimer, Don [mailto:dmisenhe@wm.com] Sent: Monday, September 21, 2020 10:15 AM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Subject: [External] Industrial Stormwater Monitoring Question: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov Bethany : I hope you are well. Would you have time for a quick call to discuss monitoring frequency at one of our facilities during the past few months due to COVID? A brief run down is below: • The site is currently in Tier 2 status (SB2W for Fecal) subsequent to the 1st Semi-annual event of 2020. Due to COVID-19 and for the safety of Great Oak employees and Contractors, the monthly Tier II sampling (SB2W) was suspended through August 2020. When WM travel loosened at the beginning of September 2020, sampling was resumed (September samples have been taken) after EP was able to meet with contractor to discuss new sample location. • Tier 2 Status: The site has cleaned basins, repaired/replaced skimmers, and has recently moved the sample location closer to the property line. Additionally, the site has taken upstream samples (September 2020) for Fecal. Wildlife is abundant in the immediate and surrounding areas; documentation of wildlife activity will begin for a future request for variance of the Fecal threshold. As you can see, I halted our contractors monitoring of our facility in March (scheduling due to the unknowns of COVID, and issues with COVID present in other contractors at our facility). I documented this on DMR forms that were electronically submitted. I just want to discuss any ramifications from your division for us having to do this. Thank you for your time - DON M. MISENHEIMER Environmental Protection Manager (North Carolina and South Carolina) dmisenhe(a)wm.com C: 984.328.0129 wn�n ���aMcn� Recycling is a good thing. Please recycle any printed emails. ATTACHMENT 2 Weekly Outfall Inspection Farms GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— WEE Y ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): v DATE: O Z TIME: np Ws . WEATHER CONDITIONS: 3c r IS DISCHARGE OCCURING: YES IO IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE a FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SOO S82E STOMRWATER QUALITY POND SB2W SOO SB2W STORMWATER QUALITY POND S81W SOO SBIW STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND S84W SOO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ,J ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM EKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): �� „�, DATE: .319 /ZaZO TIME: 0 WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES O 11F YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE rj o tJ d r- 0 FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND S132E SDO SB2E STOMRWATER QUALITY POND S62W SDO S62W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO S83W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ,J o ,_j ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : Sou i1 4-9 GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1 EKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): 1p DATE: tOZ t7 TIME: D dO WEATHER CONDITIONS: ri IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE to FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND S82W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : Ljc,. - - -k fl, es S e . rc ' 64L c .j s-✓ � r 'r t f ka -1V Elus JJ e.J 4 Pff ; ,t eaol d Itz GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1 LY ROUTINE FACILITY INSPECTION INSPECTORS) (print and sign): DATE: 2 Z TIME: pd WEATHER CONDITIONS: L ° IS DISCHARGE OCCURING: NO IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SBZW SDO SB2W STORMWATER QUALITY POND SBiW SDO S81W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) �,,�i ,,Jp,�J ,�1 ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : its S v.r w Lem er Z✓ aJtoo4 wL..�l wks� e�a� .L.�, r_.o�-t �^-t w�`�, T' 6 5, ejcJ 4-4 weAgA GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1- WE ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: 7- o Z J TIME: p o WEATHER CONDITIONS: S ° IS DISCHARGE OCCURING: YES O IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE r-S o n FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND S83W SDO SB3W STORMWATER QUALITY POND SB4W SDO S64W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) p,�a F ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 17KLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: y d -Z O TIME: WEATHER CONDITIONS: p " IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMMWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SBiW SDO SBiW STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) 0 .,_3 fi O D ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1; EKLY ROUTINE FACILITY INSPECTION INSPECTORS) (print and sign): DATE: q 11,110 't- a TIME: WEATHER CONDITIONS: IS DISCHARGE OCCURING: NO iF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE ti0 FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SBZE SDO SB2E STOMRWATER QUALITY POND SBZW SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : O!Q GREAT OAK LANDFILL STORMWATER BMP PLAN FORMA:_EKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: qAx( zo Z o TIME: ojfoo WEATHER CONDITIONS: IS DISCHARGE OCCURING: 5 NO IF YES PROVIDE DISCRIPTION: L: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o a c7 FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SBZE STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND S64W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1- WEEKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): {, DATE: tAJK 0 TIME: oC) WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o a a FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND S81E SDO-SBlE STORMWATER QUALITY POND S82E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SBiW SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— WgjjY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: ZO Z_D TIME: WEATHER CONDITIONS: / o IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE ,•j 0 FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAG EM ENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SBZE STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND S63W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1 : LY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): t.K� DATE: I1 Zp Zp TIME: oO WEATHER CONDITIONS: [� ° YES IS DISCHARGE OCCURING: IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE n d FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SBiW SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1-WE OUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): owe DATE: TIME: p9oo WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE a a o FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SBIE SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SBZW SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND S83W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1- W OUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: _ Z G - Z D Z J TIME: p "$Q WEATHER CONDITIONS: IS DISCHARGE OCCURING: NO IF YES PROVIDE DISCRIPTION: Ir COMMENTS: ki ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND S82W SDO SB2W STORMWATER QUALITY POND SB1W SDO SBIW STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SO4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) 40 ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM EEKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: 1 TIME: %p WEATHER CONDITIONS: CA&AZ 7 S e IS DISCHARGE OCCURING: YES O IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SBlE STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND S132W SDO SB2W STORMWATER QUALITY POND SBlW SDO SB1W STOMRWATER QUALITY POND SB3W SDO S83W STORMWATER QUALITY POND S84W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) DITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : r Eo GREAT OAK LANDFILL STORMWATER BMP PLAN FORM EEKLY ROUTINE FACILITY INSPECTION INSPECTORS) (print and sign): b DATE: Zo Z c7 TIME: WEATHER CONDITIONS: L10C&A IS DISCHARGE OCCURING: YES NO IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE m o FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND S83W SDO SB3W STORMWATER QUALITY POND S64W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : n GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— LY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): .. DATE: 1j /Z.07 O TIME: d p WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE IJ o a FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND S81E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SBZW SDO SBZW STORMWATER QUALITY POND SBZW SDO SBiW STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : �J GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1- Y ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): b DATE: 4 1 Z 7- TIME: osoo WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES N IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE rj b r.30 FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SRO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— W KLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: -7 -zo / z o Z o TIME: oo WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES I O IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SBIW STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : NJ GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— KLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: p e) TIME: 091Bp WEATHER CONDITIONS: [ IS DISCHARGE OCCURING: YES I N IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o O FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SBlE STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND S63W SDO SB3W STORMWATER QUALITY POND S84W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : x< <; I( rcor.�- o GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— EKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): ,e ... DATE: Zp LO TIME: oq DO WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES NO IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SB2E SDO 582E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND S83W SDO SB3W STORMWATER QUALITY POND SB4W SDO 5B4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : GREAT OAK LANDFILL STORMWATER BMP PLAN FORM KLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: p Z TIME: ing p 0 WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE JJ o tic. i1i o FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SBZE SDO SBZE STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : 5 4- OQC 51Outer Se '.� GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 17EKLY ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: Z4 L D TIME: C>5 00 WEATHER CONDITIONS: .� NO IS DISCHARGE OCCURING: IF YES PROVIDE DISCRIPTION: or�-L tiv� COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE Jj o n FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND S131E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND S132W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : oA Ire J n GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1- ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): DATE: ?-Lk ZoZ d7 TIME: p-1 30 WEATHER CONDITIONS: ° YES I <LNW IS DISCHARGE OCCURING: IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE o ra u FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND S131E SDO-SB1E STORMWATER QUALITY POND SB2E SDO SB2E STOMRWATER QUALITY POND SBZW SDO SBZW STORMWATER QUALITY POND SBiW SDO SB1W STOMRWATER QUALITY POND SB3W SDO 563W STORMWATER QUALITY POND SB4W SDO SB4W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON-COMPLIANCE, ADDITIONAL CONTROL MEASURES REQUIRED, ETC.) : er f cdol&A 5, - . 4- '- I o G cl o c . rk GREAT OAK LANDFILL STORMWATER BMP PLAN FORM 1— ROUTINE FACILITY INSPECTION INSPECTOR(S) (print and sign): b DATE: g g I 2 a z. O TIME: p WEATHER CONDITIONS: IS DISCHARGE OCCURING: YES IF YES PROVIDE DISCRIPTION: COMMENTS: ROUTINE FACILITY INSPECTION CHECKLIST (REFER TO APPENDIX B - DETAILED SITE MAP) LOCATION EVIDENCE OF SPILL REQUIRE MAINTENANCE REQUIRE REPLACEMENT ADMINISTRATIVE OFFICE FUEL STORAGE/TRANSFER AREA MAINTENANCE SHOP LEACHATE MANAGEMENT AREA STORMWATER QUALITY POND SB1E SDO-SB1E STORMWATER QUALITY POND SBZE SDO SB2E STOMRWATER QUALITY POND SB2W SDO SB2W STORMWATER QUALITY POND SB1W SDO SB1W STOMRWATER QUALITY POND SB3W SDO SB3W STORMWATER QUALITY POND SB4W SDO S64W WORKING FACE DRAINAGE DITCHES ROCK CHECK BERMS OTHER (DESCRIPTION/LOCATION) ADDITIONAL COMMENTS (NOTE INCIDENTS OF NON--CCOMPLIANCE, ADDITIONAL CONTROL MEASURES` REQUIRED, ETC.) : l � rk JOJ ♦ G��-CJ G. � , C� ` r ATTACHMENT 3 Storm Event Evaluation Great Oak - Rainfall March 1, 2020 - March 31, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 3/1/2020 Sunday 0 0.00 in 3/2/2020 Monday 0 0.00 in 3/3/2020 Tuesday 0 0.26 in 3/4/2020 Wednesday 0 0.00 in 3/5/2020 Thursday 0 0.00 in 3/6/2020 Friday 0 0.02 in 3/7/2020 Saturday 0 0.00 in 3/8/2020 Sunday 0 0.00 in 3/9/2020 Monday 0 0.00 in 3/10/2020 Tuesday 0 0.01 in 3/11/2020 Wednesday 0 0.00 in 3/12/2020 Thursday 0 0.00 in 3/13/2020 Friday 0.16 0.14 in 8:00 AM N 3/14/2020 Saturday 0 0.00 in 3/15/2020 Sunday 0 0.01 in 3/16/2020 Monday 0 0.00 in 3/17/2020 Tuesday 0.2 0.05 in 5:30 AM N 3/18/2020 Wednesday 0 0.01 in 3/19/2020 Thursday 0.07 0.19 in 1:29 AM N 3/20/2020 Friday 0 0.00 in 3/21/2020 Saturday 0.16 0.30 in 6:30 PM N 3/22/2020 Sunday 0 0.00 in 3/23/2020 Monday 0.4 0.47 in 1:09 AM N 3/24/2020 Tuesday 0.32 0.40 in Same event as above Same event as above 3/25/2020 Wednesday 0.61 1.06 in Same event as above Same event as above 3/26/2020 Thursday 0 0.00 in 3/27/2020 Friday 0 0.00 in 3/28/2020 Saturday 0 0.00 in 3/29/2020 Sunday 0 0.00 in 3/30/2020 Monday 0 0.00 in 3/31/2020 Tuesday 0.26 0.01 in 5:25 PM N * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDLIO) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable meansthat one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform) Great Oak - Rainfall April 1, 2020 - April 30, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 4/1/2020 Wednesday 0 0.00 in 4/2/2020 Thursday 0 0.00 in 4/3/2020 Friday 0 0.00 in 4/4/2020 Saturday 0 0.00 in 4/5/2020 Sunday 0 0.00 in 4/6/2020 Monday 0 0.01 in 4/7/2020 Tuesday 0 0.01 in 4/8/2020 Wednesday 0 0.00 in 4/9/2020 Thursday 0.18 0.35 in 5:54 AM N 4/10/2020 Friday 0 0.00 in 4/11/2020 Saturday 0 0.00 in 4/12/2020 Sunday 0.24 0.09 in 6:00 PM N 4/13/2020 Monday 0.78 1.35 in Same event as above Same event as above 4/14/2020 Tuesday 0 0.00 in 4/15/2020 Wednesday 0 0.00 in 4/16/2020 Thursday 0 0.00 in 4/17/2020 Friday 0 0.00 in 4/18/2020 Saturday 0.1 0.16 in 7:40 AM N 4/19/2020 Sunday 0 0.00 in 4/20/2020 Monday 0.57 0.73 in N 4/21/2020 Tuesday 0 0.00 in 4/22/2020 Wednesday 0 0.00 in 4/23/2020 Thursday 0.27 0.17 in 2:19 AM N 4/24/2020 Friday 0 0.04 in 4/25/2020 Saturday 0.84 0.75 in 11:24 PM N 4/26/2020 Sunday 0.29 0.31 in Same event as above Same event as above 4/27/2020 Monday 0 0.00 in 4/28/2020 Tuesday 0 0.00 in 4/29/2020 Wednesday 0 0.01 in 4/30/2020 IThursday 1 1.35 11.96 in 1 12:09 AM I N * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDL10) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable meansthat one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform) Great Oak - Rainfall May 1, 2020 - May 31, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 5/1/2020 Friday 0 0.00 in 5/2/2020 Saturday 0 0.00 in 5/3/2020 Sunday 0 0.00 in 5/4/2020 Monday 0 0.00 in 5/5/2020 Tuesday 0.12 0.00 in n/a N 5/6/2020 Wednesday 0.3 0.02 in 1:30 AM N 5/7/2020 Thursday 0 0.00 in 5/8/2020 Friday 0.31 0.1 7in 4:45 AM N 5/9/2020 Saturday 0 0.00 in 5/10/2020 Sunday 0 0.00 in 5/11/2020 Monday 0 0.00 in 5/12/2020 Tuesday 0 0.00 in 5/13/2020 Wednesday 0 0.02 in 5/14/2020 Thursday 0.08 0.00 in n/a N 5/15/2020 Friday 0 0.00 in 5/16/2020 Saturday 0 0.00 in 5/17/2020 Sunday 0 0.00 in 5/18/2020 Monday 0 0.03 in 5/19/2020 Tuesday 1.21 2.52 in 12:04 AM N 5/20/2020 Wednesday 0.59 2.19 in Same event as above Same event as above 5/21/2020 Thursday 1.14 1.79 in Same event as above Same event as above 5/22/2020 Friday 0.19 0.12 in Same event as above Same event as above 5/23/2020 Saturday 0 0.00 in 5/24/2020 Sunday 1.14 1.07 in 9:04 PM N 5/25/2020 IMonday 0 0.00 in 5/26/2020 Tuesday 0 0.00 in 5/27/2020 Wednesday 0.81 1.29 in 10:54 AM N 5/28/2020 Thursday 0 0.20 in 5/29/2020 Friday 0.71 0.63 in Same event as above Same event as above 5/30/2020 Saturday 0 0.00 in 5/31/2020 ISunday 0 0.00 in * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDLIO) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable meansthat one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform) Great Oak - Rainfall June 1, 2020 - June 30, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 6/1/2020 Monday 0 0.00 in 6/2/2020 Tuesday 0 0.00 in 6/3/2020 Wednesday 0 0.00 in 6/4/2020 Thursday 0 0.00 in 6/5/2020 Friday 0 0.06 in 6/6/2020 Saturday 0.13 0.08 in 12:09 AM N 6/7/2020 Sunday 0 0.00 in 6/8/2020 Monday 0 0.00 in 6/9/2020 Tuesday 0 0.00 in 6/10/2020 Wednesday 0.5 0.22 in 6:59 PM N 6/11/2020 Thursday 0.28 0.58 in Same event as above Same event as above 6/12/2020 Friday 0 0.00 in 6/13/2020 Saturday 0 0.00 in 6/14/2020 Sunday 0 0.00 in 6/15/2020 Monday 0 0.17 in 6/16/2020 Tuesday 1.2 1.24 in 12:34 AM N 6/17/2020 Wednesday 0 0.00 in 6/18/2020 Thursday 0.23 0.08 in Same event as above Same event as above 6/19/2020 Friday 0.34 0.29 in Same event as above Same event as above 6/20/2020 Saturday 0 0.01 in 6/21/2020 Sunday 0 0.00 in 6/22/2020 Monday 0 0.00 in 6/23/2020 Tuesday 0 0.00 in 6/24/2020 Wednesday 0 0.00 in 6/25/2020 Thursday 0.15 0.06 in 12:09 PM N 6/26/2020 Friday 0 0.00 in 6/27/2020 Saturday 0 0.00 in 6/28/2020 Sunday 0 0.00 in 6/29/2020 Monday 0 0.00 in 6/30/2020 ITuesday 1 0 10.00 in * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDLIO) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable meansthat one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform) Great Oak - Rainfall July 1, 2020 - July 31, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 7/1/2020 Wednesday 0 0.00 in 7/2/2021 Thursday 0 0.00 in 7/3/2020 Friday 0 0.00 in 7/4/2020 Saturday 0.11 0.00 in n/a N 7/5/2020 Sunday 0 0.00 in 7/6/2020 Monday 0 0.00 in 7/7/2020 Tuesday 0.52 0.00 in n/a N 7/8/2020 Wednesday 0.81 0.05 in 4:59 PM Same event as above 7/9/2020 Thursday 0 0.00 in 7/10/2020 Friday 0.47 0.22 in 9:59 PM N 7/11/2020 Saturday 0 0.01 in 7/12/2020 Sunday 0 0.00 in 7/13/2020 Monday 0.26 0.00 in n/a N 7/14/2020 Tuesday 0 0.00 in 7/15/2020 Wednesday 0 0.00 in 7/16/2020 Thursday 0 0.01 in 7/17/2020 Friday 1.35 1.61 in N 7/18/2020 Saturday 1 0.15 in Same event as above Same event as above 7/19/2020 Sunday 0 0.01 in 7/20/2020 Monday 0 0.25 in 7/21/2020 Tuesday 0 0.00 in 7/22/2020 Wednesday 0 0.00 in 7/23/2020 Thursday 1 0.79 in 5:54 PM N 7/24/2020 Friday 0 0.00 in 7/25/2020 Saturday 0 0.00 in 7/26/2020 Sunday 0 0.00 in 7/27/2020 Monday 0 0.00 in 7/28/2020 Tuesday 0 0.00 in 7/29/2020 Wednesday 0.44 1.89 in 12:29 AM N 7/30/2020 Thursday 0 0.12 in 7/31/2020 IFriday 1 0 10.00 in * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDL10) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable means that one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform) Great Oak - Rainfall August 1, 2020 - August 31, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 8/1/2020 Saturday 0 0.00 in 8/2/2020 Sunday 0 0.00 in 8/3/2020 Monday 0.85 1.95 in 11:09 AM N 8/4/2020 Tuesday 0.1 0.49 in Same event as above Same event as above 8/5/2020 Wednesday 0 0.00 in 8/6/2020 Thursday 1.56 0.78 in Same event as above Same event as above 8/7/2020 Friday 0.8 0.09 in Same event as above Same event as above 8/8/2020 Saturday 0 0.00 in 8/9/2020 Sunday 0 0.00 in 8/10/2020 Monday 0 0.17 in 8/11/2020 Tuesday 0 0.00 in 8/12/2020 Wednesday 0 0.00 in 8/13/2021 Thursday 0.3 0.00 in n/a N 8/14/2020 Friday 0.47 0.52 in 3:49 AM N 8/15/2020 Saturday 0.32 0.74 in Same event as above Same event as above 8/16/2020 Sunday 0 0.04 in 8/17/2020 Monday 0.18 0.71 in Same event as above Same event as above 8/18/2020 Tuesday 0 0.01 in 8/19/2020 Wednesday 0 0.00 in 8/20/2020 Thursday 0.24 0.01 in 11:49 AM N 8/21/2020 Friday 0.55 0.05 in Same event as above Same event as above 8/22/2020 Saturday 0 0.20 in 8/23/2020 Sunday 0 0.00 in 8/24/2020 Monday 0.14 0.00 in n/a N 8/25/2020 Tuesday 0 0.00 in 8/26/2020 Wednesday 0 0.00 in 8/27/2020 Thursday 0 0.00 in 8/28/2020 Friday 0 0.00 in 8/29/2020 Saturday 0.19 0.07 in 8:24 AM N 8/30/2020 Sunday 0 0.01 in 8/31/2020 Monday 0.32 0.23 in 8:19 AM N * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDLIO) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable meansthat one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform) Great Oak - Rainfall September 1, 2020 - September 30, 2020 Date Day of Week On -Site Gauge* Secondary Local Reading** Secondary Local Precip Start Time Sampleable NPDES Event?*** 9/1/2020 Tuesday 0 0.00 in 9/2/2020 Wednesday 0.16 0.04 in 9/3/2020 Thursday 0 0.00 in 9/4/2020 Friday 0 0.00 in 9/5/2020 Saturday 0 0.00 in 9/6/2020 Sunday 0 0.00 in 9/7/2020 Monday 0 0.01 in 9/8/2020 Tuesday 0 0.00 in 9/9/2020 Wednesday 0.32 0.16 in 9/10/2020 Thursday 0 0.03 in 9/11/2020 Friday 0 0.02 in 9/12/2020 Saturday 0 0.04 in 9/13/2020 Sunday 0 0.00 in 9/14/2020 Monday 0 0.00 in 9/15/2020 Tuesday 0 0.00 in 9/16/2020 Wednesday 0 0.00 in 9/17/2020 Thursday 1.44 2.64 in Sample taken 9/18/2020 Friday 0.15 0.25 in 9/19/2020 Saturday 9/20/2020 Sunday 9/21/2020 Monday 9/22/2020 Tuesday 9/23/2020 Wednesday 9/24/2020 Thursday 9/25/2020 Friday 9/26/2020 Saturday 9/27/2020 Sunday 9/28/2020 Monday 9/29/2020 Tuesday 9/30/2020 lWednesday * On -site weather station is having connectivity issues. Will be relocated from top of Leachate tank to Scale House. Temporaty on -site gage being utilized currently. ** Seconday weather station information from Asheboro WWTP (KNCRANDLIO) located approx. 2.3 miles NW of site. *** An NPDES event not sampleable meansthat one of the following criteria were not met and sampling was not performed: 1. No Flow from Outfall 2. Event occurred outside of operating hours 3. Event not representation/first flush occurred hours prior to site operations. 4. Hold times at lab prevent event from being sampled (Fecal coliform)