Loading...
HomeMy WebLinkAbout20061203 Ver 2_Western Wake PDT Meeting Summary (4-24-2008)_20080424of Engineer-s° ti"?,'irnintor? D- r Meeting Summary To: Western Wake Project Delivery Team Prepared By: CDM Date: April 24, 2008 Subject: Western Wake Regional Wastewater Management Facilities Project Delivery Team Meeting No. 10 - April 24, 2008 A Project Delivery Team (PDT) Meeting was held on Thursday, April 24, 2008 at the Herb Young Community Center in Cary to discuss the Western Wake Regional Wastewater Management Facilities (WWMF) project. The following were in attendance: Tim Bailey, Town of Cary Bill Kreutzberger, CH2M HILL Patrick Barnes, Chatham County Commissioner George Lucier, Chatham County Commissioner Paul Barth, New Hill Community Association Melba McGee, NCDENR Jason Beck, CDM Sheila Morrison, New Hill Chris Belk, Hazen and Sawyer Jamie Revels, Town of Cary Steve Brown, Town of Cary John Roberson, Wake County Ken Bruce, Brown and Caldwell Seth Robertson, NCDENR DWQ CG&L Buzz Bryson, Progress Energy Randel Sink, New Hill Community Association Bob DiFiore, Hazen & Sawyer Stephanie Sudano, Town of Holly Springs Tim Donnelly, Town of Apex Tim Sullivan, Poyner and Spruill Ina Evans, New Hill Ruth Swanek, CH2M HILL James Harris, New Hill Fred Tarver, NCDENR Jennifer Haynie, NCDENR DWQ CG&L Jeffrey Weiler, Engineering, e2M Kevin Irby, CDM Henry Wicker, USACE Bob Kelly, New Hill Community Association The following briefly summarizes the meeting and is organized per the meeting agenda (attached). 1) Handout Distribution Mr. Wicker stated that several handouts have been distributed, as listed on the agenda (attached). A summary of the March 27, 2008 PDT meeting, revised draft description of criteria to be used for final evaluations, draft secondary and cumulative impacts analysis and a draft environmental justice analysis. o? Western Wake PDT Meeting Summary April 24, 2008 Page 2 2) Harris Lake Modeling Mr. Kreutzberger gave a presentation on the updates to the Harris Lake Discharge modeling efforts. He said that four sampling locations had been monitored in the past. In addition to those four, two other locations will be monitored in 2008 as part of the modeling efforts. The upcoming schedule for the modeling is as follows: Model calibration - April/ May 08 Model sensitivity to discharge - May 08 Preliminary model report - June 08 Updated model analyses and reports - Jan 09 Mr. Sink asked if the model run data is based on the four current sampling locations. Mr. Kreutzberger said that the model will be developed using those four locations, and we will know more about the adequacy of the data for calibration in June. Mr. Kelly asked if the lake modeling accounts for plans by Progress Energy to raise the lake elevation. Mr. Kreutzberger said that it does. Mr. Sink asked at what water depth the samples are taken. Mr. Kreutzberger said that the chlorophyll sampling and other chemical parameters are collected as a composite sample and that is taken in the photic zone to the depth that light penetrates and where algae can grow. Other physical parameters are measured in increments from the surface to bottom. Mr. Lucier asked if sediment samples would be taken. Mr. Kreutzberger said that sediment samples were not taken and Mr. Lucier asked why they were not. Mr. Kreutzberger said that sediment sampling is typically a research effort and not a modeling effort. Mr. Lucier mentioned that sediment sampling is important for fish and wildlife such as the metal content in the sediments. Mr. Kreutzberger said that the state is only requiring nutrient modeling. 3) Final Site Evaluations The design engineers were provided the results of the wetlands delineations and they provided site layouts for each site minimizing impacts. For sites 19 and 30, the entrance road will cross parcels where wetlands were not delineated. Ms. Swanek said that the Partners require permission for land access on those sites for wetland delineations. In addition, the bridge on Friendship Road will need improvements. Mr. Kelly asked if the bridge replacement at site 19 accounted for the raising of Harris Lake. Mr. Kreutzberger said that he did not know but that it would be looked at. Mr. Kelly asked for clarification on the on the purple areas shown on the map and why some of them were larger than the affected roadways. Ms. Swanek said that the purple areas show locations that need further investigation for impacts and that the impacts associated with road construction are not only limited to the roadway. Mr. Wicker said that the impact areas associated with the road construction are consistent with DOT projects. o? Western Wake PDT Meeting Summary April 24, 2008 Page 3 Mr. Kreutzberger said that the impact analysis will continue with the GIS data until site access is permitted. Mr. Kelly asked if there were any additional areas shown on site 21/23. Ms. Swanek confirmed that there were not any. Mr. Sink asked if an alternative location was available for the bridge near site 19. Mr. Wicker said that the construction of a bridge is a DOT project and all location options will be investigated. Mr. Bailey said that having two bridges crossing a river does not minimize impacts to the surrounding environment. Mr. Wicker asked for comments on the final site evaluations if something appears to be lacking. Mr. Kelly asked if that statement was true for pipelines as well. Mr. Wicker confirmed that it was. Mr. Barth said that New Hill had already submitted comments on the materials from the previous PDT meeting. Mr. Wicker said that he did not receive any and requested that comments be resubmitted and that they would be distributed at the next PDT meeting. 4) Secondary and Cumulative Impacts Ms. Swanek gave a presentation on secondary and cumulative impacts in which she defined secondary and cumulative impacts, gave a general overview of master mitigation plans, gave both a geographic and temporal scope of the analysis, and listed future conditions that were under consideration. Mr. Barth said that Harris Lake should be mentioned as a nuclear facility and Mr. Kelly added that people were impacted before the lake was filled due to land condemnation, etc. Ms. Swanek said that a short description could be added to the document. For the summary tables of past wetland and stream impacts, Mr. Wicker stated that computer data conversion issues required that the data range be 2000 through 2006. Mr. Kelly asked why the power transmission lines were not included in the analysis. Mr. Wicker requested that those concerns be included in the submitted comments. Regarding the DWR hydrologic model, Mr. Barth asked whether Progress Energy's plans for withdrawal from the Cape Fear River had been incorporated into the model. Ms. Swanek said that the model update currently being completed by TJ Council of Governments will address this issue, and the document will be updated once the modeling results are available. Mr. Tarver asked if it is reasonable to assume that impacts stop at the service boundary. Ms. Swanek said that no water or sewer is provided outside of the service area. Therefore, impacts should be minimal and are not addressed outside the service area. o? Western Wake PDT Meeting Summary April 24, 2008 Page 4 Mr. Kreutzberger requested that all comments/concerns be addressed now before the draft EIS is completed. Mr. Tarver asked if the total capacity of the plant would be installed by 2030. Ms. Swanek confirmed that the majority of the capacity will be installed by 2030. Mr. Kelly requested that Wake County be added to the secondary and cumulative impacts summary of mitigation programs. 5) Environmental Justice Data Mr. Kreutzberger gave a presentation on the environmental justice (EJ) analysis in which he outlined four major steps within the process. He said that steps one and two have been worked on at this point. He emphasized that public participation is an important factor throughout the process. In the presentation, Mr. Kreutzberger presented a set of revised maps for site 19 and stated that site 19 was only used as an example and that the same analysis was completed for the remaining sites. Mr. Barth asked if weighting was involved in the analysis. Specifically, Mr. Barth asked if an entire census block would be included if only a small corner of a census block touched the boundary of interest. Mr. Wicker confirmed that all census blocks that are crossed or touched by the boundary of interest will be included and not weighted, but will be analyzed in more detail in the document. Mr. Sink asked if information could be determined for people that lived in the small portion of a census block that was included in the WWTP boundary. Mr. Kreutzberger said that the required information (income, minorities) cannot be obtained with further investigation such as door to door surveys, only numbers of people. Mr. Kreutzberger said that the state requires that no weighting factors are used in the EJ analysis and that a qualitative analysis must be completed. Ms. Morrison asked if the half mile boundary was from the site boundary or the center of the site. Mr. Kreutzberger said that it is measured from the boundary of the site. Ms. Morrison also asked if an impact was temporary (traffic), should it be included in the analysis. She will email her comment. Mr. Sink requested that the document elaborate on the community benefits because some are confusing. Mr. Kreutzberger said that they will be clarified. Mr. Wicker requested comments on the meeting materials by Friday, May 2nd Army Corp,-' Engineers Wilmington District MEETING AGENDA NEPA EIS Project Delivery Team Western Wake Regional Wastewater Management Facilities Project PDT Meeting No. 10 April 24, 2008 10:00 am to 12:00 pm Herb Young Community Center (Room A) 101 Wilkinson Avenue, Cary, NC 27513 1) Introductions and Handout Distribution a) Summary of March 27, 2008 PDT Meeting No. 9 b) Revised draft description of criteria to be used for final evaluations c) Draft secondary and cumulative impacts analysis d) Draft environmental justice analysis 2) Harris Lake Discharge a) Update PDT on potential discharge of effluent at Harris Lake 3) Final Site Evaluations a) Discuss status of final site evaluation field work and evaluations b) Review access road alignments for Sites 19 and 30 c) Discuss draft criteria to be used for final evaluations 4) Secondary and Cumulative Impacts a) Review draft secondary and cumulative impacts analysis b) Submit comments by May 2, 2008 5) Environmental Justice Data a) Review draft environmental justice analysis b) Submit comments by May 2, 2008 MEETING AGENDA NEPA EIS Project Delivery Team Western Wake Regional Wastewater Management Facilities Project April 24, 2008 6) Future PDT Meeting Dates a) May 29, 2008- 10:OOAM to 12:00 PM, Herb Young Community Center in Cary, Room A b) June 26, 2008 -10:00 AM to 12:00 PM, Page Walker Arts and History Center 7) Review Proposed Meeting Objectives for May 29, 2008 Meeting a) Secondary and cumulative impact analysis b) Environmental justice c) Results of final site evaluations 8) Other Business a) Provide comments on PDT meeting materials to USACE by Friday, May 2, 2008 9) Adjourn NEXT MEETING May 29, 2008 10:00 am to 12:00 pm Herb Young Community Center (Room A) 101 Wilkinson Avenue, Cary, NC 27513 Project Website (through US Army Corps of Engineers' website): http://www.saw. usace. army. m i I/wetl ands/Pro jects/WW-WTP/i ndex. htm I