HomeMy WebLinkAboutSWA000079_2020-09-24 Construction Sequence_20200930United Rentals —Salisbury, NC 9/24/2020 CONSTRUCTION SEQUENCE PHASE 1 1. NOTIFY ROWAN COUNTY OF PENDING CONSTRUCTION PER PERMIT REQUIREMENTS, AND HOLD REQUIRED PRE -CONSTRUCTION MEETING. ALL CONTRACTORS MUST ATTEND THE PRE -CONSTRUCTION MEETING. 2. CLEAR AND GRUB AS NECESSARY TO INSTALL PERIMETER CONTROLS, SILT FENCE, DIVERSIONS, INLET PROTECTION, AND TEMPORARY CONSTRUCTION ENTRANCE. 3. ONCE PERIMETER CONTROLS, SILT FENCE, DIVERSIONS, INLET PROTECTION, AND CONSTRUCTION ENTRANCE HAVE BEEN INSTALLED, INSTALL STRUCTURE #5, R1 & R2 WITH INLET PROTECTION. BEGIN MASS CLEARING & GRUBBING. DISPOSE OF DEBRIS OFF -SITE IN PROPER MANNER. EXCAVATED MATERIALTO BE STOCKPILED ONSITE & SURROUNDED BY SILT FENCE. 4. CONSTRUCT SEDIMENT BASINS AND CONTRACTOR TO PROVIDE A STOCKPILE AREA. STOCKPILE AREA IS FOR THE EXCAVATED DIRT FROM THE SEDIMENT BASIN CONSTRUCTION. 5. UPON COMPLETION, BEGIN ROUGH GRADING OF THE SITE. PHASE 2 1. INSTALL TEMPORARY SEEDING AND MULCH STABILIZATION TO ALL AREAS WHERE WORK WILL BE CEASED FOR A PERIOD OF MORE THAN 14 DAYS. 2. BEGIN REMAINING STORM DRAIN CONSTRUCTION. INSTALL INLET PROTECTION MEASURES AS EACH CATCH BASIN IS INSTALLED. 3. CONTINUALLY INSPECT AND MAINTAIN ALL BMP'S. REPAIR BMP'S AS NEEDED. 4. BEGIN BUILDING CONSTRUCTION. 5. APPLY SOD/PERMANENT SEEDING TO ALL AREAS AS SOON AS THEY ARE COMPLETE. DO NOT WAIT UNTIL JOB COMPLETION TO PERMANENTLY STABILIZE DISTURBED AREAS. 6. INSTALL UTILITIES. 7. INSTALL CURB AND GUTTER AND FINE GRADE PARKING AREAS. STONE BASE SHALL BE INSTALLED IN ALL PAVED AREAS AS SOON AS PRACTICABLE. PAVE SITE AND INSTALL APPROPRIATE INLET PROTECTION DEVICES FOR PAVED AREAS AS WORK PROGRESSES. 8. COMPLETE CONSTRUCTION OF SIDEWALKS, PLANTINGS, ETC. 9. REMOVE TEMPORARY BMP'S AS SOON AS THEIR CONTRIBUTING DRAINAGE AREAS HAVE BEEN STABILIZED. SEED AND MULCH ANY DISTURBANCE FROM REMOVAL OF TEMPORARY BMP'S. 10. CONTACT ROWAN COUNTY FOR FINAL INSPECTION. 11. CLEAN UP SITE.