LETTER OF APPROVAL WITH MODIFICATIONS
City of Burlington
ATTN: Hardin Watkins, City Manager
PO Box 1358
Burlington, NC 27216
RE: Project Name: Burlington-Alamance Regional Airport Outfall
Acres Approved: 1.95
Project ID: ALAMA-2021-017
County: Alamance
City: Burlington
Address: Anthony Rd.
River Basin: Cape Fear
Stream Classification: WS-V ; NSW - Jordan Lake Watershed
Submitted By: City of Burlington
Date Received by LQS: July 24, 2020
Plan Type: New
Dear Mr. Watkins:
This office has reviewed the subject erosion and sedimentation control plan. We find the
plan to be acceptable with modifications and hereby issue this letter of Approval with
Modifications. The Modifications Required for Approval are listed on the attached page. This plan
approval shall expire three (3) years following the date of approval, if no land -disturbing activity
has been undertaken, as is required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit
an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCGO10000 Construction Stormwater General Permit. This form MUST be submitted and COC
issued prior to the commencement of any land disturbing activity on the above -named project.
The NOI form may be accessed at deq.nc.gov/NCG01. Please direct questions about the NO[ form
to Annette Lucas at Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. After you
submit a complete and correct NO [ Form, a COC will be emailed to you within three business days.
Initially, DEMLR will not charge a fee for coverage under the NCG01 permit. However, a $100 fee
will soon be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff
in Raleigh.
D ��� North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
•/ Winston-Salem Regional Office 1 450 West Hanes Mill Road, Suite 300 1 Winston-Salem, North Carolina 27105
taaairs cwa�rca �""
336.776.9800
Letter of Approval
City of Burlington
August 11, 2020
Page 2 of 3
Title 15A NCAC 413,0118(a) and the NCG01 permit require that the following documentation be
kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection
to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Program is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, it is determined that the erosion and sedimentation control plan
is inadequate to meet the requirements of the Sedimentation Pollution Control Act of 1973
(North Carolina General Statute 113A-51 through 66), this office may require revisions to the
plan and implementation of the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws, regulations, and rules. In addition, local city or county ordinances or rules
may also apply to this land -disturbing activity. This approval does not supersede any other
permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. This permit allows for a land -disturbance,
as called for on the application plan, not to exceed the approved acres. Exceeding the acreage
will be a violation of this permit and would require a revised plan and additional application fee.
You are requested to file an amended form if there is any change in the information included on
the form. In addition, it would be helpful if you notify this office of the proposed starting date for
this project. Please notify us if you plan to have a preconstruction conference. Your cooperation
is appreciated.
Sincerely,
Zacha ntz, EI
Assistant Regional Engineer
Land Quality Section
Enclosures: Certificate of Approval
Modifications Required for Approval
NCG01 Fact Sheet
c: WSRO file
Letter of Approval
City of Burlington
August 11, 2020
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Burlington-Alamance Regional Airport Outfall
Project ID: ALAMA-2021-017
County: Alamance
Modifications pursuant to applicable North Carolina General Statutes and/or Regulations:
North Carolina recently issued a new NCG01 General Construction Stormwater Permit.
Please ensure the NCG01 Ground Stabilization and Materials Handling and Self -Inspection,
Recordkeeping and Reporting requirements are on your plans. The NCG01 compliance plan
sheets for these can be found at https:,(ldeq.nc.gov/about/divisions/energy-mineral-land-
resources ener -mineral-land- permits stormwater- permits Iconstruction-sw Printing
these sheets out and adding them to your plans is a requirement of the NCG01 permit,
or their entire contents must be included in your plans with reference for each requirement
provided to this office, prior to construction.
Additional Comments:
1. Additional measures may be required - The applicant is responsible for the control of
sediment on -site. If the approved erosion and sedimentation control measures prove
insufficient, the applicant must take those additional steps necessary to stop sediment from
leaving this site. [15A NCAC 4B .0115]
2. Be advised the 7/14-day soil stabilization requirements apply to any section of the project
where land -disturbing activities have temporarily or permanently ceased and shall
supersede any less stringent stabilization requirement on the plans. [G.S.143-215.1]
Ref: G.S.113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities