HomeMy WebLinkAbout20190289 Ver 1_Response to USACE Non-compliance_20200903Strickland, Bev From: Rodney Carpenter < rcarpenter@gray.com > Sent: Thursday, September 3, 2020 3:14 PM To: David.E.Bailey2@usace.army.mil Cc: Randy Barber; Kevin Wurschmidt; Homewood, Sue; John Fisher; 'Floyd Freeman' Subject: [External] RE: Action ID: SAW-2018-00240 Attachments: D.Bailey ACOD Resp_2020_09-03.pdf Follow Up Flag: Flag Status: Follow up Flagged External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov Mr. Bailey, Please see our attached response to your below questions. Let me know how I can be of further assistance. Rodney Carpenter VICE PRESIDENT, DISTRIBUTION & COMMERCIAL MARKE- G ray 10 Quality Street Lexington, KY 40507-1450 Office: 859.281.2513 Mobile: 859.618.7607 rcarpenter@gray.com gray.com LINKEDIN I TWITTER I FACEBOOK This e-mail, and any documents, files or previous e-mail messages attached to it may contain confidential, privileged or proprietary information. If you have received this communication in error, please contact the sender and destroy all copies of this email. From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil> Sent: Wednesday, August 19, 2020 4:19 PM To: Rodney Carpenter <rcarpenter@gray.com> Cc: Randy Barber <Randy.Barber@publix.com>; Kevin Wurschmidt <kwurschmidt@gray.com>; Homewood, Sue <sue.homewood@ncdenr.gov>; John Fisher <John.Fisher@publix.com> Subject: RE: Action ID: SAW-2018-00240 Mr. Carpenter, Thank you for your response letter and coordination efforts to resolve non-compliance items related to the subject Department of the Army (DA) permit (SAW-2018-00240). Having reviewed your letter and referenced plans, I am providing the following responses regarding each Compliance Site originally listed in my email dated 7/2/2020: Compliance Site 1: The Corps is generally agreeable to your proposal to leave the check dam in place at its current location until the site has reached a more stabilized state. However, we require the following additional information: 1) Your letter does not specify whether you propose to restore the stream to pre -grading conditions, or request consideration via after -the -fact permitting to stabilize the site in a different state. Please provide this information, including the timeframe for submitting a specific restoration plan (including a completion date) or after -the -fact permitting request; Compliance Sites 2 and 3: no further action required from the Corps. Compliance Site 4: The Corps is generally agreeable to your proposal to "complete the re -work in this area." It is our understanding that you will restore the stream to pre -grading conditions, and that you require 3-4 days of suitable weather conditions to complete the work. However, we require the following additional information: 1) Please provide the "as built" survey of the fill slope for this area, showing the reach of stream impacted outside of permitted limits; 2) Please provide a specific restoration plan (including an estimated completion date), including how you propose to return the area to pre -grading conditions (i.e. grade and contour), and how you plan to stabilize the area using native vegetation and/or natural channel design structures; Compliance Site 5: The Corps is generally agreeable to your stream and wetland restoration proposal in this area. However, we require the following additional information/considerations: 1) We are concerned about the highly erodible nature of soils in the proposed work area. Have you considered whether or not the proposed sill structures are appropriate/sufficient to prevent the stream/water from simply working around the structures? 2) The last (i.e. most downstream) structure shows a —2' drop into the receiving steam. Typically we would not expect more than a 1' vertical drop between structures and/or the receiving stream bed in this region. Could the restoration plan be amended to accommodate this shorter vertical drop? 3) Please provide an estimated completion date; Compliance Site 6: no further action required from the Corps. Please provide the above requested information within 2 weeks of the date of this email, and let me know if you have any questions. Sincerely, Dave Bailey David E. Bailey, PWS Regulatory Project Manager US Army Corps of Engineers CE-SAW-RG-R 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 Phone: (919) 554-4884, Ext. 30. Fax: (919) 562-0421 Email: David.E.Bailey2@usace.army.mil We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is located at: http://corpsmapu.usace.army.mil/cm apex/f?p=136:4:0 Thank you for taking the time to visit this site and complete the survey. From: Rodney Carpenter <rcarpenter@gray.com> Sent: Tuesday, August 18, 2020 8:58 PM To: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil> Cc: Randy Barber <Randy.Barber@publix.com>; Kevin Wurschmidt <kwurschmidt@gray.com> Subject: [Non-DoD Source] Action ID: SAW-2018-00240 Mr. Bailey, Please see the attached letter and drawings in response to the letter from Mr. Scott McLendon dated July 29, 2020. Please contact me if you have any questions. Rodney Carpenter VICE PRESIDENT. DISTRIBUTION & COMMERCIA Gray 10 Quality Street Lexington, KY 40507-1450 Office: 859.281.2513 Mobile: 859.618.7607 rcarpenter@gray.com gray.com LINKEDIN I TWITTER I FACEBOOK This e-mail, and any documents, files or previous e-mail messages attached to it may contain confidential, privileged or proprietary information. If you have received this communication in error, please contact the sender and destroy all copies of this email. SENT VIA EMAIL September 3, 2020 Mr. David Bailey Wilmington District, Corps of Engineers 69 Darlington Avenue Wilmington, NC 28403-1343 RE: Action ID: SAW-2018-00240 (email response 08.20.20) Dear Mr. Bailey, The following is our response to your email of August 20, 2020 requesting additional information for the below items: Compliance Site 1 Question: Your letter does not specify whether you propose to restore the stream to pre -grading conditions, or request consideration via after -the -fact permitting to stabilize the site in a different state. Please provide this information, including the timeframe for submitting a specific restoration plan (including a completion date) or after -the -fact permitting request. Response: Plateau will restore the stream to pre -grading conditions. It is our intent to perform an as -built prior to construction. Any disturbance if past the LOD will be removed. The original existing conditions will be staked. It is the intent to restore the existing ground to pre -disturbed condition with riparian seed and a coir fiber mat. If Live Stakes are required, then work will have to proceed after November 15t and before March 15t when those planting go dormant. Given the current time of year the FOR would suggest planting wetland sedge plugs at a density of 2ft on center along the soil lifts and along the streambanks of the restored channel. A repair condition as -built will be provided when the work is complete. Plateau can perform this work within a 3-4 day window of consistent dry weather. Plateau will be performing this scope under the guidance of an Environmental Engineer from Wildlands Engineering and Central Carolina Seeding. Compliance Site 4 Question: The Corps is generally agreeable to your proposal to "complete the re -work in this area." It is our understanding that you will restore the stream to pre -grading conditions, and that you require 3-4 days of suitable weather conditions to complete the work. However, we require the following additional information: 1) Please provide the "as built" survey of the fill slope for this area, showing the reach of stream impacted outside of permitted limits; Response: As -Built Survey is accompanying this letter. gray.com 10 Quality Street T: 859.281.5000 Lexington, KY F: 859.252.5300 Mr. David Bailey September 3, 2020 Page 2 2) Please provide a specific restoration plan (including an estimated completion date), including how you propose to return the area to pre -grading conditions (i.e. grade and contour), and how you plan to stabilize the area using native vegetation and/or natural channel design structures; Response: Plateau will restore the stream to pre -grading conditions. It is our intent to perform an as -built prior to construction. Any disturbance if past the LOD will be removed. The original existing conditions will be staked. It is the intent to restore the existing ground to pre -disturbed condition with riparian seed and a coir fiber mat. If Live Stakes are required, then work will have to proceed after November 15t and before March 15t when those planting go dormant. Given the current time of year the FOR would suggest planting wetland sedge plugs at a density of 2ft on center along the soil lifts and along the streambanks of the restored channel. A repair condition as -built will be provided when the work is complete. Plateau can perform this work within a 3-4 day window of consistent dry weather. Plateau will be performing this scope under the guidance of an Environmental Engineer from Wildlands Engineering and Central Carolina Seeding Compliance Site 5: The Corps is generally agreeable to your stream and wetland restoration proposal in this area. However, we require the following additional information/considerations: 1) We are concerned about the highly erodible nature of soils in the proposed work area. Have you considered whether or not the proposed sill structures are appropriate/sufficient to prevent the stream/water from simply working around the structures? Response: From Timmons Engineering (EOR): To provide the corps with a greater level of comfort, the sills can be installed with clay plugs. Clay plugs will create a barrier for the water, pushing it up to the surface where the water will daylight in the channel. Plateau is following the direction and engineered plans from Timmons Engineering for this work along with supervision from an Environmental Engineer from Wildlands Engineering and Central Carolina Seeding. A detail has been added to the revised plans (accompanying this letter) to show the installation of the clay plug and location. 2) The last (i.e. most downstream) structure shows a —2' drop into the receiving steam. Typically, we would not expect more than a 1' vertical drop between structures and/or the receiving stream bed in this region. Could the restoration plan be amended to accommodate this shorter vertical drop? Response: From Timmons Engineering (EOR): The tributary restoration is tying into an incised channel along the main reach. Due to the incision and a channel of this size it will be more stable along the left and right banks of the tributary to have a 2 ft drop into the main channel. The amount of energy from the tributary will not negatively affect the main channel due to their vast size differences. Without restoring the main channel, we feel this is the best approach. Stability of the left and right banks of the tributary will be key in this area. The last rock sill has been extended to provide added boulder toe protection along the main channel. Mr. David Bailey September 3, 2020 Page 3 3) Please provide an estimated completion date. Response: This is very dependent on the start date which needs to be considered when clear weather is available along with dormant conditions if Live Plantings are being used. The current time frame given from two environmental sources is 3-4 weeks to complete. Plateau will be performing this scope under the guidance of an Environmental Engineer from Wildlands Engineering and Central Carolina Seeding to efficiently complete the work to the satisfaction of the ACOE. Plateau is prepared to expedite the work as soon as a clear weather path is provided and all design conditions are known. Our entire team is committed to maintaining compliance with the Department of the Army (DA) permit and continues to work diligently to address any matters on a timely basis. Should you have any questions, please contact Mr. Kevin Wurschmidt via telephone at (859) 314-2715 or email (kwurschmidt@gray.com). Sincerely, Rodney Carpenter VP, Distribution & Commercial Market c: Randy Barber Publix Super Markets, Inc. 3300 Publix Corporate Parkway Lakeland, FL 33811-3002 Kevin Wurschmidt Gray Construction 10 Quality Street Lexington, KY 40507 NOTE Z PIPES AND DRAINAGE STRUCTURES h SHOWN HEREON ARE FOR co n REFERENCE ONL Y. W O � SCALE 1 "=20' 0' 20' 40' EXHIBIT FOR CHECK DAM ASBUILT PUBLIX - GREENSBORO DISTRIBUTION CENTER MCLEANSVILLE GUILFORD CO., NC Date: 8/13/20 Scale: 1 " = 20' Sheet 1 of 1 J. N.: 45015 Drawn by: TJ Checked by:JP 610 E. MOREHEAD ST., SUITE 250 1 CHARLOTTE, NC 28202 THIS DRAWING PREPARED AT THE TEL 704.376-1073 FAX 704.376-1076 www.timmons.com T I M M O N S GROUP ••••~ CHARLOTTE OFFICE North Carolina License Number C-1652 .� • YOUR VISION ACHIEVED THROUGH OURS \ ( ` ST 30+07. 0 \ \ r \ \V \V \ l r \ \ TOf 638.W \ \ \ ; I \ o IIJVIN 30.7\\7(E26)\ \ 1 I I °b \ \ 1 �I/ �'\�'/ \I/ / I-7 l /I)IIIIIII \ \ \ I NV (;UT 6�0k6 E28) \\� I \ \ 111fIIII 1 / I \ \ \ \ \ \ \ \ \ / II 1 / 1 1 o \ \. \\ o I \ \ \ \ \ \ \ v 0 III \ 1 1 ~ \ \ \ \ \ \ \ \ \ \ \ \ \ ° \� \� \\ V/ V/ \ II 1 Il / 1 o \ \ \ I\/ \ \\ - I /\ I / \ ' \ /1�1111 // 1 11 \ \ / \ 1 \\ \ \ \ \ \ \ \ \ \ \ \ \o'' V� \ \ \\\ 1 // 1 111 \ �\ J / \\ 1 I \ \\ \\ \\ \\ \ 74�0�\ \ \ \ \\ \\ \o \ \ \ \ \ \ \\\\ 1 PVC \\ \ \ \ \ \0 1 �j \I/\�\���� @35°%\\ \\ \ \ \ \ \ \ \l0 �� \ \ \t t/ll/�////iI 11 \ \ \ \ 'I \ ` \ RIPARIAN SEED, PLANTINGS AND \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ 10 1 \ / �\ �\ \� \ 1 I I I \ \ I I 1 700g COIR MATTING WITHIN III I \ \ \ 11 II j PUMP AROUND TO BE USED UPSTREAM OF THE \ �\ \I�\� \ 1 , LIMITS OF GRADING. LIVETAKES E29 \ \ \ \ PROJECT AREA TO DEWATER THE STREAM \ \ \ I \ &HERBACEOUS PLUGS ALONG \ \ \ STA 0+81.03 \ \ \ DURING CONSTRUCTION. FILTER BAG TO BE \ _ STREAM BANK. REF. SHEET 1.02. I / \ \TOP 638'90� USED AT DISCHARGE POINT OF PUMP AROUND. \ \ \ \ \ \ \\ ) \ I / •1 III _ -JJ�/ I i \ \ \ \ \ IN\� 626.20 28 ° \ \ I / I III '% - INSTALL REINFORCED SOIL LIFTS, \ \ IN ) \ \ \ \ \ \ \ 1 1 \ �o ♦ I / / / /,/- \1 \ \ \ \ \ \ \ INa/ OUT�28.'FO (E3Q) \ \ \ \ \ \ \ \ \ \ 1 0 1 E30 C\ 0\\y\ _ - \ \ \ \ \ ` \ \ \ \ o\ 95' O� \ \�O \ - �OQ , / I /�Ir/, SEED & PLANT W1 LIVESTAKES & ° \ 12" PVC \ I �l /l /ll HERBACEOUS PLUGS \\ \ \ \ \ \\ \\ \ \ \ \ � l /71, W I 1 o EX. WOODY VEGETATION TO BE \� \ �0 / , I b TRANSPLANTED WHERE POSSIBLE ca )IIII \ \ \ \ \ \ \ \ \ \ \ \ \ \ ^ 1 \ \ \ \ STA 3i+7U28 II1111 111 ` x \ 1 1IIII \ \ \ \ \ \ \\ \ \\ \\ \ \ \ \ \ \ \\ \ \ \ \ \ \ \ \ \ o TOP�9.31 7 111i1(11.- \ \ \ \ CLAY PLUG + I \ \ I \ INV IN 624.14�30)- I I I \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ ° INS/ A-UT624.04 (E32) (TYP. 61 \ \ \ I 10 \ \ \ \ O \ \ \ \ \ \ \ \ \ \\ \ \ 1 \ \ � \ \ \ \� \ o\ 1 In , 1 \/ \\ \\ \ \\ 1 \ \ \ \\ \ \ \ \ \ \\ \\ \ \\ \ \ \ \\ \\ \\ \ \ \ \o \ 0\ 1 M \ \ 1 \ \ \ \ \ \ \ \ \ \ 0 Lq \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ 1 0 1 I co c° \ \\ \\ \ \\ \ \\ , \ \ \\ \\ \\ \ \ \ \\ \�\\\\\� \ \ \ \ \ \� \\ \0 1 12"�Anil \ ` 1\ \ \\ \ \\ \\\\\\ \\ \I 2�9EOF \\ \ \\� \ \I°c 1 REMOVE RIPRAP, INSTALL '"SAN 112" Qucti6Irony \ , \ \ \ REINFORCED SOIL LIFTS, l\ I @ 1�.00%\\ � 11 , �\\ \\ \\ SEED PLANT W1 LIVESTAKES &HERBACEOUS PLUGS I +68.5 I II 1 II`1111 \1' / y11 111111 III( , , Iin of _ I,- \\ \ \ �'I\\� \\ \ \\ , \ \ 1' \\ 1 \ 1°o 0 \ \ \ II o\ \�----- \ 1- \\ \ , ,'III 1 1 , \\ \ I , 1 \ \° o / , I I I lo0/ / / \ , / 1 1 I 1 1Iq /II/d d p I / / II�Il1/I i° Fl TRIBUTARY TYPICAL CROSS SECTIONS 700 g COIR FABRIC 700 g COIR FABRIC (L Riffle Dimensions Cross Sectional Area (ft2) 5.9 Top Width (ft) 8.1 Bankfull Depth (ft) 0.7 Maximum Depth (ft) 1.0 TYPICAL RIFFLE SECTION Straight Pool Dimensions Cross Sectional Area (ft) 14.4 Top Width (ft) 10.0 Maximum Depth (ft) 2.4 TYPICAL STRAIGHT POOL SECTION SCALE 1 "=5' 0 5' 10, 645 640 635 630 CLAY P 625 620 615 610 9+90 10+00 - - = REMOVE RIPRAP, INSTALL REINFORCED SOIL LIFTS, SEED & PLANT W1 LIVESTAKES & HERBACEOUS PLUGS 4N I I I I 1 /' "%%' / I 1 \ • _ril��`il��ril� - ■ ■I\■ :!�■�i� M ■I\■ 11\■ ���1 IN `dIME 11\■ ■imi M ■■1\111h�I\ ■I�1 ■ ■1\\11 Mimi ■ ■1\\11 ■M1= 111M■■1\\II\■■II\ 111M■■1\\11\■■MIM �■��\CIA\��I�\ MCI 11. wMR ME .01 . \ ME 10+40 645 640 635 630 625 620 615 610 10+68.56 4 0 20 PROFILE SCALE i ' I I \ 1 I 1 I I d I II 1 1, 1 1 1 � d I I I I I I I l I l l I I / i� � I I\\ \ 1 / 1 / \\11111 ll b II I I I 11 1 1 1 I 1 1 1 1 I I I/ _, // 1 1 I I / I I I / / I \ \ 1I II \\ ' II 1 1 I I 1 // I 1 10 1 \I\III I I I I I °� °\ / -\\\ of , / \ \ NOTE: 1 CONSTRUCTION TO BEGIN AT STA 10+00 1 / WORKING UPSTREAM TO DOWNSTREAM 1 I 1 1\ \ \ I I \\ \\ \ \ \ I I • \ 11 II�II� 0 1 I i I 11 11 �\I I ,` I✓/�j II °\ I I I I I I I 1 1 \ \\\ \ \ \ o of \`\\o�\ 1 \ 1 \ \ \ \ \ \ \ \ \ o / I EX1 / - 0-0 _ STA 34+05.61 / \ ° o \ _ \ ° TOP633.00__� I �\ ���_� \ INV IN621.75 (E32) \ ° / \ 0 0 0 0 o\ i \ I \ 1 011 .\ / - - - STRUCTURE TABLE TRIBUTARY SILL/HEADER TABLE STRUCTURE NAME STATION ELEVATION ROCK SILL 10+05.24 630.74 ROCK SILL 10+26.99 629.80 ROCK SILL 10+45.03 628.86 ROCK SILL 10+62.90 628.01 NOTE: 1. EXISTING RIPRAP AT SANITARY SEWER CROSSING TO BE REMOVED. INSTALL REINFORCED SOIL LIFTS ALONG BOTH BANKS. 2. SEED, STRAW, AND INSTALL 700g COIR MATTING ON ALL DISTURBED AREAS WITHIN THE LIMITS OF GRADING. 3. PLANT LIVESTAKES AND HERBACEOUS PLUGS ALONG STREAM BANKS USING 2FT SPACING. 4. REFERENCE SHEET 1.01 FOR CONSTRUCTION DETAILS. 5. REFERENCE SHEET 1.02 FOR SEED & PLANT SPECIES AND QUANTITIES. 6. CONSTRUCT TRIBUTARY FROM UPSTREAM TO DOWNSTREAM BEGINNING AT STA 10+00. PROPOSEDIMPROVEMENTS LIMITS OF DISTURBANCE/ BARRICADE TAPE - - - - - - LIMITS OF GRADING DESIGN STREAM CENTERLINE MAJOR CONTOUR MINOR CONTOUR ROCK SILL REINFORCED SOIL LIFT M M 0 Q z SCALE 1 "=20' NOR 0 20' 40' NOTE: 1. STREAM SUBSTRATE TO BE INSTALLED AT LOCATIONS INDICATED IN THE GRADING PLAN. REFERENCE THE SUBSTRATE MIX SPECIFICATIONS DETAIL ON SHEET 1.01. r1r1/,r•11 r' EXISTING GRADE (FIELD TOPO) PROPOSED GRADE DESIGN BANKFULL ROCK STRUCTURE CLAY PLUG rff f, ',, SEAL 4 C �� �- ft"'rri�1h, NO M E � o rj � 0 z EUi w o� 0 H 3: (D Q W 3 U 0 ILL ;v �p _ ¢O - o a `o N 0 L M LU > M = Z � M U 3: w X Q LU � Z p � O = Y o > ~ D 1° O M N M '�t J 00 W K Q w Q 0 DATE 0811112020 D RAW N BY JTS DESIGNED BY BAS CHECKED BY BC SCALE AS NOTED Uj CL z w U z O N H l0 LLI ' J U � a z LUL z DC<� LU a z (n 66 0 a z O� J OU 0 oz 0 Q O U 0� ? Q = z `D O LL �w LL' V X t-� MJ W JOB NO. 42407 SHEET NO. 1.00 6 N U 0 M 3 0 0 2- Q 0 0 Q 0 O �a N � �O �Er CL Iv z °O -2� 0 E° �U) �N d o c C7 � ZN O� �Q �x o .L.. Q Q� >Sd �N U iu O O U L 3 L STATIONS AN PROVIDED (BEGIN STEF TO END STEF STREAMBED FLOW BACKFILL WITH SUBSTRATE MIX 6 OZ NON -WOVEN GEOTEXTILE EXTENDING MIN 4' UPSTREAM r.rniTrr� HEADER ROCK OCKS SHALL XTEND MIN. 3' JTO BANKS PLAN VIEW \- BASEFLOW a-------- SUBGRADE FILL SUBSTRATE MIX (WHEN APPLICABLE) (PLACE THROUGHOUT ENTIRE STEP POOL) PROFILE VIEW NOTES: 1. REFER TO SUITABLE ROCK SIZE DIAGRAM ON SHEET 1.01 FOR ROCK DIMENSIONS. 2. THE ROCK SILL IS TO BE CENTERED IN THE CHANNEL WITH ALL HEADER ROCKS FLUSH WITH THE PROPOSED GRADE. ALL ROCKS PLACED TIGHTLY TO EACH OTHER WITH SUBSTRATE MIX COMPACTED AROUND EACH. 3. ANY GAPS OBSERVED DURING INSTALLATION SHOULD BE CHINKED USING SMALLER SUBSTRATE. THESE AREAS SHALL BE INSPECTED BY THE PROJECT ENGINEER TO VERIFY INSTALL. 4. EXTEND 6 OZ NON -WOVEN GEOTEXTILE TO THE MIDPOINT ALONG THE TOP FACE OF THE HEADER ROCK. 5. REFER TO STRUCTURE TABLE ON SHEET 1.00 FOR STATION AND ELEVATION OF POOL AND ROCK STRUCTURES. REV. 8/22/19 ROCK SILL NO SCALE EXTEND BLANKET A MINIMUM OF 3' >VER CREST OF SLOPE, SEE DETAIL 4/12. . " . " . " " " TRENCHING NEEDED IF MINIMUM OF 3' ." " ."" IS NOT AVAILABLE AT THE CREST OF SLOPE OR IF OVERLAND FLOW IS y y y ' ' ��� . " . ' . ANTICIPATED FROM UPLAND AREAS, .... . - . - SEE DETAILS 5/12 &6/12.... / �� �� ""•"•""" .... � . . . .y.y."." ... / / ......Y ...... .... / ...... / ... FOR END ROLL ...... OVERLAP, SEE DETAIL 2/12 / ....." " ... X .... BLANKET TO EXTEND A """ ; : SIDE SEAM OVERLAP, MINIMUM OF T BEYOND SEE DETAIL 7/12 TOE OF SLOPE. FOR ."."."."."" " BOTTOM OF SLOPE TERMINATION, SEE DETAIL 3/12 BLANKET OVERLAP 2" - 4" END SEAM OF BLANKETS OVERLAP 2 - 4". / STAKES ARE PLACE STAKES, ONE ON EACH CORNER OF THROUGH BLANKET, 12" O.C. ALONG BLANKET AND BOTH BLANKETS. THROUGH STITCHING ON BOTH BLANKETS. UPSLOPE BLANKET LAPS OVER DOWNSLOPE DETAIL 7/12: SIDE SEAM BLANKETS IN A SHINGLE EFFECT. OVERLAP STAKE DETAIL DETAIL 2/12: END ROLL OVERLAP SPLIT 2x4 STAKE 12" O.C. ALONG BOTTOM OF BLANKET AT THE END OF SLOPE 1 ROW OF SPLIT 2x4 STAKES, 12" O.C. DETAIL 4/12: SLOPE CREST ANCHOR METHOD "A" (NO TRENCH) SOIL PILE TRENCH APPROX. FROM TRENCH 10" WIDE x 8" DEEP SLOPE TO PROTECT TOP OF BLANKET 1 ROW OF STAKES, 2 ROWS OF STAKES, 12" O.C. STEP 1 STAGGERED, 6" O.C., EA. DIR. 2 ROWS OF STAKES, STAGGERED, 6" O.C., EA. DIR. SOIL FILLED FROM SOIL PILE STEP 2 DETAIL 5/12: SLOPE TRENCHING METHOD "B" NOTE: TRENCHING NOT REQUIRED IF BLANKET CAN BE EXTENDED A MINIMUM OF T OVER THE SLOPE CREST. SOIL PILE FROM TRENCH TRENCH APPROX. 10" WIDE x 8" DEEP -1 18" STAKE 12" O.C. ALONG SLOPE TO BLANKET AT SLOPE PROTECT ^' ' ",NGE DETAIL 3/12: BOTTOM OF SLOPE TERMINATION V V �2 ROWS OF STAKES, 1 ROW OFJ STAKES, STEP 1 STAGGERED, 6" O.C., 12" O.C. EA. DIR. 2 ROWS OF STAKES, 4" APART STAGGERED, 6" O.C., STAKES TO BE PLACED CLOSE TO EDGE OF BLANKET SOIL FILLED FROM SOIL PILE STEP 2 DETAIL 6/12-SLOPE TRENCHING METHOD "C" NOTES: 1. IN THE EVENT A SINGLE ROLL OF BLANKET WILL SPAN FROM TOP OF BANK TO TOE OF SLOPE, A PARALLEL INSTALLATION MAY BE USED. 2. BLANKET TO EXTEND TO PROPOSED LIMITS OF SUBSTRATE. BLANKET SHALL BE INSTALLED PRIOR TO SUBSTRATE. 3. STAKE SHALL BE HANES GEO COMPONENTS ECO STAKE OR APPROVED EQUAL. 4. SOURCE: AMERICAN EXCELSIOR COMPANY - EARTH SCIENCE DIVISION. DATE: 05/01/03. REFER TO MOST RECENT MANUFACTURER'S INSTALLATION RECOMMENDATIONS. REV. 11/11/13 700g COIR FABRIC SLOPE APPLICATION DETAIL NO SCALE LIMITS OF FLOODPLAIN PROPOSED HEADER ROCK GRADE (REFER TO BANKFULL STRUCTURE 0 0 ° ELEVATION DETAIL). �0°000 �0000000 °0°0°0°0°0 000�0�0�0�0�0�00 O O O roc NATIVE BACKFILL >o°o°o°o°0°0°0°00000 0 J c > O O O O O O O O O 00, OR TOPSOIL >°0°o°o°O°0°O°O°o°o°o . 0 0 0 0 0 0 0 0 0 0 0 0"0"0"0-0"0"0"0 O O O O O O O O O � 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 °o°o°O°O°0°0°O°O°0°0°O°O°0°o°O°O°o° 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 >O°0°OOOOOOOOOOOOO°°°00000°00000000� > 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O O O O O O O O O O O O O o d > O O O O O O O O O O O O O O O O I 10-0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 TOP OF PLUG SHALL J XTEND TO ELEVATION EQUIVALENT TO BOTTOM CLAY PLUG ' OF SILL SUBSTRATE MIX TOP DRESS MIN. 12" DEPTH l AGGREGATE BACKFILL BACKFILL EXISTING GROUND PLANTINGS MIN. 3' KEY INTO EXISTING 700g COIR c GROUND MAT O°c o° °o°o O O O c O O°O°000 00-000G O O 00 Oo0o0 °o°O O°o°o °O°c 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o O c O O O_O_O_O_O_O_O O O O O O O O O O o°0000cSOIL -MIN. 1FT O°o o°O°O°o°o°o O°o° j% °0°0°c 0°0°0°0°0°0 0°0° O O O DEPTH o 0 0 0 0 0 o c O O c o o 0 0 0 0 0 0 0 0 it o o O O O O O O 0 O O O o o O c 0 0 0 o 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 00000000000000000 0 0 0 0 0 0 0 0` OOOOOOOOO O O O O o O O O O O O O O O O O O O O O O O 0000 0 0 0 0 0 0 0 0 0 0 0 °-I BACKFILL CLAY - VARIABLE DEPT (REFER TO PROFILE SHEETS) /�\ EXISTING </�\/�\' l � GROUND /� SECTION VIEW HEADER ROCK FLOW - - - - - - - - - - - - - BASEFLOW III - FOOTER ROCK 12" MIN INTO G CLAY PLUG PROFILE VIEW EQUAL TO WIDTH OF FOOTER ROCK NOTES: 1. REFER TO GRADING PLAN AND PROFILE SHEETS FOR PLUG DIMENSIONS. 2. BOTTOM OF PLUG SHALL EXTEND A MINIMUM OF 12 INCHES INTO UNDISTURBED IN -SITU SOIL MATERIAL. 3. PLUG SHALL EXTEND AT LEAST 5 FT FROM THE ASSOCIATED SILL AND KEY INTO EXISTING SIDE SLOPES. CLAY PLUG NO SCALE REV. 11 /07/17 i PLANTINGS UNDISTURBED Q /O� EARTH SEED SURFACE A/�5�'G� 700g COIR- UNDER MAT %Q/`GPI' MAT DEWATERING DEVICE DIRT/SEDIMENT LIVE STAKES ( TYP. O BAG) DIVERSION PUMP ( ) / o°O°o 0 00o O 0000000000 o000000000000 �� �� UNCOMPACTED 700g COIR FABRIC (NEDIA 18" TO 36" / O O O O O O O O O O O ���� DISCHARGE HOSES o 0 0 0 O O O O O O O O EARTH ENTERPRISE, INC. OR o o O o 0 0 0 0 INTAKE o 0 0 0 0 0 0 0 0000000000000 / 0 0 0 0 0 0 0 O O HOSE APPROVED EQUAL)000000 o 0 0 0 0 0 0 000000000000000 0 \ O O O 000000 O O O O O O O O O O O O O / O O O O O O O O O O O O O O O O O 0000 DEWATERING PUMP o00 0 0 0 0 00°0°0°0°0°0°0°0°0°0°0 0°0°0, ...... P (AS NEEDED) LIVE STAKES (T OC) / °O 2 0 o O00000000o0o0o0o0o00000 000� 0 0 0002 0 0 0 0 0 0 0 0 0 0 0 0 o c ............................... ... / 0000 °0000000 0 0 0 0 0 0Vo 0 0 o °O° °O°O°O°0°O O°O°0�,O OOOO O O O O O O O O O O O o 0 0 0 00 0 0 oO O O O O O O 4" WEDGE OOOOOO OO OOOOOO Or' XFLOW A A FLOW 000000000000000 0O0 0 0 000 �' 0000000000000 000000000000 O O o 0 0 0 STAKES 0000000000000 0 0 0 0 0 c WORK AREA o000000000000000000o0o0o0 00000° 0000000 °O 0000000000000O°O°O°O°O°O°O°O00000 SANDBAG/STONE O O c NATIVE BACKFILL 9" - 18" HIGH O o 0 0 0 0 0 0 0 0 0 0 0 ° °0°o°O°0°0°O OR TOPSOIL O O O O O O O O O O O O 0000000 O O O O O O BARRIER SOIL LIFT o°o°o°o°o°o o°o°o°o°o°o°o°O o°o°o o°o°o°o°oc SUMP HOLE OR 0000 0 0 0 0 0 0 0 0 0 0 0 0 0 00000000 - ......................................................... POOL V MIN DEPTH / 000000000 000000000000000 000000 0000 ............ 0000000000000000000000000000000 000 oo0oc 2 MIN DIAMETER o 0 0 00000 o 0 0 0 0 0 0 0 0 0 0 0 0 0 O O WORK AREA LENGTH O o 0000 0 0 0 0 0 0 0 0 0 0 O O O O c - DISCHARGE PUMP o 0 0 0 0 0 0 0 0 0 0 0 0 0 o O000000000000 INTO VELOCITY NOT TO EXCEED BASEFLOW ----- DISSIPATER THAT WHICH CAN BE JO O O O O C l 1 COMPLETED IN ONE DAY 12" HIGH BASE USING ���� 3-6" AGGREGATE _�/ _�/� �_` UNDISTURBED BACKFILL �O _MIN.5 III EARTH REV. 9/26/11 PLAN VIEW ANO EINFORCED SOIL LIFTS SCALE 6 OZ NON -WOVEN GEOTEXTILE (ACF N060 OR EQUALN WORN AREA BASE FLOW + 1' (2' MINIMUM) CROSS SECTION OF SANDBAG/STONE DIVERSION SECTION A -A PUMP AROUND NO SCALE y + x_< ROCK z SUITABLE ROCKS WILL HAVE THE FOLLOWING THREE PRIMARY DIMENSIONS (±2"): x = LONGEST DIMENSION y = INTERMEDIATE DIMENSION z = SHORTEST DIMENSION REACH (SLOPE) INTERMEDIATE DIMENSION, Y (in.) TRIBUTARY 42 REV. 9/26/11 SUITABLE ROCK SIZE DIAGRAM NO SCALE REACH (SLOPE) MATERIAL SIZE (D5o) in. SIZE (D50) mm TRIBUTARY COBBLE 10 254 1. ALL MATERIAL USED FOR SECTIONS OF THE STREAM CHANNEL THAT ARE RAISED ABOVE EXISTING GRADE SHALL BE REVIEWED AND APPROVED BY THE PROJECT ENGINEER PRIOR TO PLACEMENT IN THE STREAM CHANNEL. 2. COBBLE AND GRAVEL MATERIALS SHALL BE ROUNDED IN NATURE AND COMMON TO RIVERBED FORMATIONS. 3. SUBSTRATE SHALL BE NATURAL ROUNDED ROCK. 4. THE APPROVED MIX WILL BE DOCUMENTED TO ACCOMMODATE MIXING AT THE PLANT AND ENSURE CONSISTENCY WITH SITE DELIVERED LOADS. REV. 08/16/18 SUBSTRATE MIX SPECIFICATIONS NO SCALE rff If $�o f� SEAL 42 8 �p �: reffff�f,�'CI�O m E C-)6 N � 0 z E L o o w +� Q W N U H o Lu u- _ ¢O—o z w O M N O a � > 0-0 w a (D LA M M = z Ln W a X U Q U (n af W a� o�U)� z w ul)y 1-4 cn z � o > " N c� H `ko° o w M N M � J w 0 w Q 0 DATE 0811112020 D RAW N BY JTS DESIGNED BY BAS CHECKED BY BC SCALE NONE uj z uj U z O cV J H� I U z W O I --I O z �QC;6 w �uU) z w w H O 0 U z 0 z J Qz z0�O J O U 0 0 O U m LL DC = C� cn z z 0 Lu O w U ce V X I --I MJ W r) JOB NO. 42407 SHEET NO. 1.01 N cn m U) N 0 2- C Q c m 0 a> 0 c m U) C Q `o O � a �O Df 20 °z �> O o E O c� �N c D 0 U) zN O2 �Q x �_ a> O L 0 a� 0 QE O § >` (00 �N U N O O U �3 �N (6 0 ul o c o a) E� U N O 0.9 U N c cn ,o O U -0 2 �N N O c U N O Q0 L HERBACEOUS PLA k CARE OF SEEDLINGS UNTIL PLANTED SEEDLINGS SHOULD BE PLANTED IMMEDIATELY. IF IT IS NECESSARY TO STORE MOSS -PACKED SEEDLINGS FOR MORE THAN 2 WEEKS, ONE PINT OF WATER PER PKG. SHOULD BE ADDED. IF CLAY -TREATED, DO NOT ADD WATER TO PKG. PACKAGES MUST BE SEPARATED TO PROVIDE VENTILATION TO PREVENT "HEATING". SEPARATE PACKAGES WITH WOOD STRIPS AND STORE OUT OF THE WIND IN A SHADED, COOL (NOT FREEZING) LOCATION. CARE OF SEEDLINGS DURING PLANTING TREEMAT WHEN PLANTING, ROOTS MUST BE KEPT MOIST UNTIL TREES ARE IN THE GROUND. DO NOT CARRY SEEDLINGS IN YOUR HAND EXPOSED TO THE AIR UNCOMPACTED HEIGHT VARIES AND SUN. KEEP MOSS -PACKED SEEDLINGS IN A CONTAINER PACKED WITH WETLAND WITH PLANTS WET MOSS OR FILLED WITH THICK MUDDY WATER. COVER CLAY -TREATED GRADE - SEEDLINGS WITH WET BURLAP ONLY. ALL BARE ROOT SEEDLINGS SHALL BE TREATED WITH ROOT DIP ABSORBENT POLYMERS AND MYCORRHIZAL ROOT DIP INOCULATES IN ACCORDANCE WITH MANUFACTURERS 12" RECOMMENDATIONS. SAID ROOT DIP SHALL BE MYCORTREEO ROOT DIP MIN. OR APPROVED EQUAL. 11=1 11=1 11=1 11=1 I\\ -III-III-III=III=III=III=III=III=III=III=III=11 HAND PLANTING (8") G VJ.GIIIIII 1 SOD STAPLE TREE MAT AVAILBLE FROM: EcoDepot, LLC www.ecodepotsales.com REV. 6/27/19 TREEMAT (CIRCULAR NO SCALE vl�vly I vlww SUBSURFACE REV. 7/22/13 HERBACEOUS PLANTING DETAIL NO SCALE SEEDING SCHEDULE QUANTITY PER ZONE BOTANICAL NAME COMMON NAME INDICATOR STATUS MIX DENSITY SEEDING RATE (LBS / ACRE) TOTAL QUANTITY AREA: LOD (AC) (LB) (ACRES) 0.09 Panicum clandestinum Deertongue FACW 30% E/ymus virginicus Virginia Wildrye FACW 20% Andropogon gerardii Big Bluestem FAC 12% Sorghastrum nutans Indiangrass UPL 11% Panicum virgatum Switchgrass FAC 5% Chamaecrista fasciculata Partridge Pea FACU 4% Verbena hastata Blue Vervain FACW 4% Juncus effusus Soft Rush FACW 3% Rudbeckia hirta Blackeyed Susan FACU 3% RIPARIAN BUFFER MIX Heliopsis helianthoides Asc/epias incamata Oxeye Sunflower Swamp Milkweed FACU OBL 2% 1% (ERNMX-178) Aster novae-angliae New England Aster FACW 1 % Aster umbellatus Flat Topped White Aster FACW 1 % Eupatorium perfoliatum Boneset FACW 1 % Agrostis perennans Autumn Bentgrass FACU 1 % Helenium autumnale Common Sneezeweed FACW 1 % Monarda fistulosa Wild Bergamot FACU 1 % Vemonia noveboracensis New York Ironweed FACW 1 % Pycnanthemum tenuifolium Narrowleaf Mountainmint FACW 0.4% Solidago patula Roughleaf Goldenrod FAC 0.4% Eupatorium fistulosum Joe Pye Weed FACW 0.3% Lobelia siphilitica Great Blue Lobelia OBL 0.3% Aster puniceus Purplestem Aster UPL 0.2% TOTAL QUANTITY 100% 20 1.70 0.09 1.70 STARTUP MIX BOTANICAL NAME COMMON NAME INDICATOR STATUS MIX DENSITY SEEDING RATE (LBS/ACRE) TOTAL QUANTITY AREA: LOD (AC) (LB) (ACRES) 0.09 Echinochloa muricata Barnyardgrass FACW 50% 30 1.3 0.09 E/ymus virginicus IVirginia widrye I FAC 1 50%1 1 1.3 0.09 SEEDING SCHEDULE NOTES: 1. The above referenced seed mixes are available from Ernst Convservation Seeds, 8884 Mercer Pike, Meadville PA 16335; Phone: (800) 873-3321. 2. Seeding quantities are for convenience only and shall be verified by the Planting Contractor based on the specified density (pounds/acre) prior to bidding. 3. Substitutions shall only be made with the approval of the Project Engineer. PLANTING SCHEDULE ZONE STRATUM GROUPS SPECIES PLANT SPACING (FEET O.C.) TOTAL QUANTITY LOD (AC) BOTANICAL NAME COMMON NAME INDICATOR STATUS PLANTS PER ACRE # OF PLANTS 0.09 TUBE LING QTY RIPARIAN TREE LAYER 1 Platanus occidentalis American sycamore FACW 6-10' 500 43 43 Betula nigra River birch FACW 6-10' Liquidamb ar styraciflua Sweetgum FAC 6-10, Acer rubrum Red maple FAC 6-10' Liriodendron tulipifera Tuliptree FACU 6-10' Juniperus virginiana Eastern red cedar FACU 6-10' FOREST Tota 1 43 SHRUB LAYER 1 Comus amomum Silky dogwood FACW 6-10' 500 43 43 Corpus alba Red osier dogwood FACW 6-10' Morella cerifera Wax myrtle FAC 6-10' Magnolia virginiana Sweetbay FACW 6-10' Cercis canadensis Eastern redbud FACU 6-10' Total �43 ZONE STRATUM GROUPS SPECIES PLANT SPACING (FEET O.C.) TOTAL QUANTITY STREAM CHANNEL PER STREAM LENGTH # OF PLANTS 348 BOTANICAL NAME COMMON NAME INDICATOR STATUS LIVESTAKE LIVE STAKES 1 Salix negra Black willow FACW 2 348 348 348 Corpus sericea Red osier dogwood FACW j 2 STREAM BANK STRATUM GROUPS SPECIES PLANT SPACING (FEET O.C.) TOTAL QUANTITY STREAM CHANNEL PER STREAM LENGTH # OF PLANTS 348 BOTANICAL NAME COMMON NAME INDICATOR STATUS PLUGS HERBACEOUS 1 Carex lurida Shallow sedge OBL 2 348 348 348 Juncus effusus lCommon rush OBL 2 PLANTING SCHEDULE NOTES: 1. Quantities are based on estimated areas of planting, including areas of disturbance. Additional plantings shall conform to the materials and rate of this schedule. 2. Substitutions shall only be made with the approval of the Project Engineer. 3. Seeding shall occur prior to planting. 4. Tubelings shall be planted at a density of 1,000 stems/acre. 5. Like stakes quantities are cumulative for entire length of stream (both sides of banks). 6. Tubelings in riparian areas are to be installed with tree mats. 7. Planting shall occur between dormancy period, September 15th through March 15th. All planting shall occur during frost free conditions with unfrozen soils. 1►►U11010 1:1010111&y,&III I A RVAII CelliI BENDING ROOTS. FIRM SOIL AROUND SEEDLING WITH FEET. RIGHT WRONG PLACE SEEDLING AT CORRECT DEPTH WITH ROOT CROWN LEVEL WITH IN -SITU SOIL OR SLIGHTLY HIGHER. USE NEARBY TOPSOIL TO PLACE AROUND SEEDLING TO COVER ROOT CROWN BY 1-2". REE MF TEST PLANTING BY PLACE 1 1/2" - 2" PULLING LIGHTLY DEEP AND INSTALL ON SEEDLING. TREE MAT. DON'T EXPOSE PLANT SEEDLINGS ROOTS TO AIR UPRIGHT - NOT AT DURING FREEZE OR AN ANGLE. PLANT IN FROZEN GROUND. ROOT COLLAR SHALL BE 1 %2" BELOW SOIL. DO NOT BEND ALWAYS PLANT IN ROOTS SO THAT SOIL - NEVER THEY GROW LOOSE LEAVES OR UPWARDS OUT OF DEBRIS. PACK SOIL THE GROUND. TIGHTLY. PLANTING SHALL RESULT IN A MOUND 2-3" ABOVE SURROUNDING ELEVATION. SATURATE PLANTING HOLE WITH WATER. RIGHT WRONG TUBELING AND BARE -ROOT SEEDLING INSTALLATION NO SCALE INSTALL ALONG BOTTOM OF BANK (TOE) ANGLING TOWARDS CHANNEL AND DOWNSTREAM 24" (0.4M) MIN. PLANT 80% OF THE STAKE IN THE GROUND LIVE STAKING NO SCALE SINGLE RO A� 13' STAGGER STAKING 3' (1 M) APART O.C. CUT TOP OF STAKE SQUARE 2 TO 5 BUD SCARS SHALL BE ABOVE THE GROUND. REMOVE ADDITIONAL LENGTH BEYOND 4" (90MM) ABOVE GROUND. TRIM BRANCHES CLOSE 1/2"-l" (12-23MM) DIAMETER MAKE ANGLED CUT AT BUTT -END (BASAL). 5555551 1171d11 err ♦� � r i SEAL 342 9 � +� jt- .7 irr rn E 0 0 N � 0 z E L o LU Q W U H o 0 ¢O -o z LL O M N OLu 5Q > L a �7m� z_ Z M Lr) W X U Q U (n a � o��� z o w y T Z _ �o - > ~ N o� H ko `D =O M M w W N M � J UJ 00 F- • • • REV.4/23/12 • ►7 n r n DATE 0811112020 D RAW N BY JTS DESIGNED BY BAS CHECKED BY BC SCALE NONE LW 1 z W U O O m z w w X H� MJ W r) U) 11- 4 a W C) T W O z JOB NO. 42407 REV. 07/23/18 SHEET NO. 1.02 L