HomeMy WebLinkAboutNCC203783_ESC Approval Submitted_20200902ROY COOPER.
Governor
MICHAEL S, PSGAN
Seaway,
BRI 4N WRENN
AangDlroctoY
Glandon Forest Equity, LLC
ATTN: George Barnes, manager
3825 Barrett Dr., Suite 100
Raleigh, NC 27609
NORTH CAROLINA
Environmentol,oAgltcy,
July 27, 2020
LETTER OF APPROVAL
RE: Project Name: Dollar General
Acres Approved: 1.63
Project ID: ALAMA-2020-047
County: Alamance
City: Elon
Address: Hub Mill Rd.
River Basin: Cape Fear
Stream Classification: WS-V; NSW
Submitted By: Triangle Site Design
Date Received by LQS: June 29, 2020
Plan Type: New
Dear Mr. Barnes:
This office has reviewed the subject erosion and sedimentation control plan. We find
the plan to be acceptable and hereby issue this Letter of Approval. The enclosed
Certificate of Approval must be posted at the job site. This plan shall expire three (3)
years following the date of approval, if no land -disturbing activity has been
undertaken, as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and
submit an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage
(COC) under the NCG010000 Construction Stormwater General Permit.
This form MUST be submitted prior to the commencement of any land disturbing
activity on the above named project. The NOI form may be accessed at
deq.nc.g_ov/NCG01. Please direct questions about the NOI form to Annette Lucas at
Annette.lucas@ncdenr.gov_ or Paul Clark at Paul. clark ncdenr. ov. After you submit
a complete and correct NOI Form, a COC will be emailed to you within three business
days. Initially, DEMLR will not charge a fee for coverage under the NCG01 permit.
However, a $100 fee will soon be charged annually. This fee is to be sent to the DEMLR
Stormwater Central Office staff in Raleigh.
North Cbrollna Department of Environmental quality I Mislon ofEnergy, Mineral and Land Rnources
aE
J! Winston-SaleinRcglorial:pFflce. 450 West Hanes Mlll Road Suite &00 (Vylnston-Salem, North Carolina 27105
336.77§.980.0.
Fact Sheet on the New NCGO1 Permit
April 2019
Organizational Updates
The new permit:
Repeats state requirements for E&SC
Plans and organizes them with federal
construction activity requirements;
Is clearly organized by topic; and
Has less text and more tables.
Technical Updates
The new permit:
• Requires that the E&SC Plan meet
SWPPP requirements (p. 2);
• Provides a list of items that must be
included in the SWPPP, such as the
construction sequence, plans,
calculations, etc. (p. 2-4);1
• Has updated language on bypasses and
upsets that is tailored to construction
activities (p. 10);
• Puts all timeframes for inspections,
record -keeping and reporting in
"calendar days" for clarity and
consistency (p. 11-14);'
• Changes the inspection frequency
(during business hours) to at least
once per 7 calendar days and after
every storm > 1.0 inch (previously 0.5
inch);' and
• Excludes weekends, state and federal
holidays from normal business hours
unless construction activities take
place (p. 23).
1 This list is based on website guidance
by the DEMLR Sediment Program.
z The number of calendar days was
selected to be as equivalent as
possible with the previous permit.
3 The intent .is to provide predictability
to the inspection schedule.
Acronyms to Know
COC: Certificate of Coverage, proof of coverage under an NCGO1 permit
DEMLR: NC Division of Energy, Mineral, and Land Resources
E&SC: Erosion & Sedimentation Control
e-NOL Notice of Intent, application form for the NCGO1 permit
e-NOT: Notice of Termination, form for closing out the NCGO1 permit
SWPPP: Stormwater Pollution Prevention Plan, required by the NCGO1
The NCGO1 Process
The new NCGO1 applies to permits approved on or after April 1, 2019.
Permittees will no longer receive a copy of the NCGO1 permit in the mail
with their E&SC Plan approvals and be considered as covered under the
permit. Federal rules require that DEMLR receive an N01 on each
construction project and issue each construction project its own COC.
Under the new NCG01 process, construction sites will continue to
receive approval for E&SC Plans from either DEMLR or the delegated
local E&SC program just like before. After receiving E&SC Plan approval,
permittees will officially obtain coverage under the NCGO1 by
completing an a-NOI (available at dep.nc.gov/NCG01). The a-NOI will
only take about 20 minutes to fill out and submit on-line.
Initially, there will be no charge associated with applying for an NCGO1
permit but on or around June 1, 2019, DEMLR will begin charging a $100
annual general permit fee as required per §143-215.3D.
DEMLR is working on creating a single application form that will allow an
applicant to simultaneously apply for an E&SC permit and an NCGO1
COC. That effort is part of a larger Permit Transformation project at
DEMLR.
ROY COOPER
Energy, Mineral
and LandResources
ILNVtROµMENTAL QUALITY
Governor
MICHAEL S. REGAN
Secretary
TRACY DAVIS
Announcement of Combined Self -Monitoring and Self -Inspection Form
Director
The Sedimentation Pollution Control Act was amended in 2006 to require that persons
responsible for land -disturbing activities inspect a project after each phase of the project
to make sure that the approved erosion and sedimentation control plan is being followed.
Rules detailing the documentation of these inspections became effective October 1, 2010.
To simplify document of Self -Inspection Reports and NPDES Self -Monitoring Reports, a
combined form is now available. The new form was developed to satisfy the requirements
of the Sedimentation Pollution Control Act and the NPDES Stormwater Permit for
Construction Activities, NCG 010000. Beginning August 1, 2013, the Division of Energy,
Mineral, and Land Resources is responsible for administering both the SPCA and the NPDES
Stormwater Permit for Construction Activities- NCG 010000. The combined form should
make it easier to comply with self -inspection requirements.
The Combined Self -Monitoring form is available as a PDF and Word document from the
Land Quality web site.
htt Rortal,ncdenr.orgZweb/Ir/erosion
If you have questions, please contact the Land Quality Section at a DEQ Regional Office
State oFNorth Caroline I Environmental Quality I Energy, Mineral and Land Resources
450 West Hanes Mill Road, Suite 300 J Wiaston-Salem, NC 27105
336 776-9800 Phone/ 336 776-9797 FAX