HomeMy WebLinkAboutNCC203749_ESC Approval Submitted (2)_20200901Title 15A NCAC 4B .O 118(a) and the NCGO1 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G. S. 113A-61.1(a) of our right of periodic
inspection to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate to
meet the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina
General Statute 113A-51 through 66), this office may require revisions to the plan and
implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with`Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances
or rules may also apply to this land -disturbing activity. This approval does not supersede
any other permit or approval.
Please note that this approval is based in part on the accuracy of the information
provided in the Financial Responsibility Form, which you provided. You are requested to
file an amended form if there is any change in the information included on the form. This
permit allows for a land -disturbance, as tailed for on the application plan, not to
exceed the approved acres. Exceeding the acreage will be a violation of this permit and
would require a revised plan and additional application fee, Any addition in impervious
surface, over that already noted on the approved plan, would also require a revised plan
to verify the appropriateness of the erosion control measures and the stormwater retention
measures. (GS 113A-54. I (b)). In addition, it would be helpful if you notify this office of
the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
Sincerely,
chi
Chris Baker
Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Scott Brown, P. E., 4D Site Solutions, Inc. — electronic copy
Michael Baily, City of Fayetteville Permit Office — electronic copy