HomeMy WebLinkAbout20201086 Ver 1_GMisc_U5026_R5720_Avoidance_and_Minimization_&_4A_Measures_20200825AVOIDANCE AND MINIMIZATION
The NCDOT is committed to incorporating all reasonable and practicable design features to
avoid and minimize jurisdictional impacts, and to provide either on-site or compensatory
mitigation of all remaining, unavoidable jurisdictional impacts. Avoidance measures were taken
during the planning and NEPA/SEPA compliance stages; minimization measures were
incorporated as part of the project design.
Avoidance and Minimization
All jurisdictional features were delineated, field verified and surveyed within the right of way for
U-5026/R-5720. Using these surveyed features, preliminary designs were adjusted to avoid
and/or minimize impacts to jurisdictional areas. NCDOT employs many strategies to avoid and
minimize impacts to jurisdictional areas in all of its designs. All wetland areas not affected by
the project will be protected from unnecessary encroachment. Individual avoidance and
minimization efforts are detailed below for the project. Site specific measures are detailed by
name and impact sheet number for ease in identification in the plan set.
General Avoidance and Minimization Efforts
• NCDOT will minimize long-term water quality impacts using the most recent Best
Management Practices for Protection of Surface Waters, as identified in the Federal Aid
Highway Program (FHPM) and North Carolina Administrative Code, Chapter 4.
• Sediment and erosion control measures will accommodate a 25-year storm event.
• NCDOT will avoid placing erosion control devices in wetlands.
• Special sediment control fence will be used at wetlands and low areas along the standard silt
fence.
• Riprap will only be placed in the bed of the channels during stabilization of outlet structures
as necessary to prevent further degradation of the stream systems. These locations are
illustrated on the attached plans.
• The use of 3:1 fill slopes in jurisdictional areas where practicable.
• Ditches and pipes that outlet adjacent to wetlands have been designed to have non-erosive
velocities.
• Bank stabilization is being utilized along jurisdictional features to minimize erosion potential
at channel ties or pipe/culvert outlets.
Avoidance of Jurisdictional Resources
• Impacts have been avoided for the features SA, SG, WA, WC, WD, WE, WF, WG, WH, WI,
WJ, WM, WP, WQ, WR, WS, WU, WV, WW, WX, and WY within the U-5026 project area.
Impacts have been avoided for Stony Creek within the R-5720 project area.
• Impacts to buffers of SA and SG within the U-5026 project and Stony Creek within the R-
5720 project were avoided.
Avoidance/Minimization of Impacts to Stormwater Control Measures
• Existing Stormwater Control Measures (SCM) were avoided to the extent practical
throughout the project.
• A stormwater management plan has been developed and is attached.
Stream Relocation
Stream F (Site 6) is located parallel to the north side of Sunset Avenue. Roadway fill accounts for
1,192 linear feet of permanent impacts to Stream F. Instead of piping, 990 linear feet of channel
will be relocated and tied in further downstream. A 1.3 acre streambank reforestation plan has been
developed for the new channel alignment. Please see attached documents.
NEPA/404 MERGER TEAM AGREEMENT
Concurrence Point No. 4A: Avoidance and Minimization Measures
PROJECT DESCRIPTION:
Sunset A venue (SR 1770) Interchange and Improvements
Nash County
STIP Project No. U-5026
STIP Project# U-5026 involves converting the existing Sunset Avenue (SR 1770) grade
separation with I 95 to an interchange; widening Sunset Avenue between Old Carriage Road (SR
1603) and Halifax Road (SR 1544); and extending the existing collector-distributor along I-95 at
US 64 to the south of the proposed interchange. The proposed project is in Rocky Mount, which
is located in eastern Nash County.
A voidance and Minimization
A voidance and minimization measures are described for the jurisdictional resources in the
August 21,2019 Concurrence Point (CP) 4A merger packet and summarized below. Additional
minimization may be achieved during final design, when hydraulic design (CP 4B and 4C) and
utility relocation design commence.
Measures to avoid and minimize impacts to potential jurisdictional waters of the US were
incorporated into the best fit design of the project. The presence of residential and commercial
buildings, existing structures, and utility transmission lines were also taken into consideration.
As designs are refined, reductions to stream and wetland impacts are anticipated.
Opportunities for avoidance and minimization were limited due to the nature of the project and
the location of the potentially jurisdictional resources located in the vicinity of the project. The
preliminary design includes a 17'6" median instead of a 23' median where possible, east of the
roundabout at Nash Community College along Eastern Avenue/Sunset Avenue, to reduce the
project footprint.
During the August 21,2019 Concurrence Point 4A Merger Meeting, the Merger Team requested
supplemental information regarding design decisions and avoidance and minimization efforts.
Accordingly, the following table acknowledges the impacted features and characterizes the
related constraints and/or minimization efforts incorporated into the proposed project.
Summary of Design Constraints and A voidance and Minimization
Env. Feature Impacting Design Design Constraint or Minimization/ A voidance
Feature Effort
WetlandB SB entrance ramp Ramp/loop must be placed in southern quadrants
due to ramp spacing requirements
WetlandJ Freight Rd tie Minor widening at project tie; impacts may be
eliminated in final design
WetlandL Southern terminus of Wetland pocket runs adjacent to 1-95 corridor;
SB C-D road impacts by C-D road unavoidable
WetlandO Southern terminus of Wetland pocket runs adjacent to 1-95 corridor;
NB C-D road impacts by C-D road unavoidable
WetlandBA SR 1770 widening Wetland pocket located north of existing road;
widening is proposed more to the south in an effort
to minimize impacts
WetlandBB SR 1770 widening just Grade dictated by vertical clearance requirements
east ofl-95 for 1-95 bridge; existing RR bridges along 1-95
present southern constraint
WetlandBD SB C-D road Wetland pocket runs adjacent to 1-95 corridor;
impacts by C-D road unavoidable
Wetland BE SB C-D road Wetland pocket runs adjacent to 1-95 corridor;
impacts by C-D road unavoidable
WetlandBF SB entrance ramp Ramp/loop must be placed in southern quadrants
due to ramp spacing r~uirements
WetlandBJ Southern terminus of Wetland pocket runs adjacent to 1-95 corridor;
SB C-D road impacts may be eliminated in final design
WetlandBK NB C-D road Wetland pocket runs adjacent to 1-95 corridor;
impacts by C-D road unavoidable
WetlandBM SR 1770 widening Proposed U-turn bulb-out located to serve Ben
Layton Circle; bulb-out could potentially be shifted
to west to avoid impact
WetlandBN SR 1770 widening Located opposite Stream B; alignment avoids
residential relocations on Gardenia Cir
Wetland T NB C-D road Wetland pocket runs adjacent to 1-95 corridor;
impacts by C-D road unavoidable
StreamB SR 1770 widening Located opposite Wetland BN; design avoids
residential relocations on Gardenia Cir
Stream C SB C-D road Located immediately adjacent to 1-95 corridor;
impacts by C-D road unavoidable
StreamD SR 1770 widening just Horizontal layout to achieve deflection at
east ofl-95 roundabout; grade dictated by vertical clearance
requirements for 1-95 bridge
StreamE SB entrance ramp Ramp/loop must be placed in southern quadrants
due to ramp spacing requirements
Stream F SR 1770 widening east Grade dictated by vertical clearance requirements
and west of 1-95 for 1-95 bridge; existing RR bridges along 1-95
present southern constraint
The Project Team has concurred by signature and date below on the avoidance and
minimization measures that have been incorporated into the project design to-date, as
described in detail in the CP 4A merger packet.
Agency Signature Agency Signature
9/18/2019 9/17/2019
~ips of Engineers nviroruriental Protection Agency
~--~ .).1~ ~~ 9/18/2019
~JfsW<tfA4<f·wildlife Service
9/19/2019
~~/2019 ~Of Water Resources
~~ 9/16/2019
N=Opartment of Transportation Federal Highway Administration
9/19/2019