HomeMy WebLinkAboutSW5200602_Responce to Comments_2020082091st� �:srvi,cs Ilune.
® Sta nt@C 227ArysIeyTown Blvd. Suite 300, Charlotte, NC 28273
August 14, 2020
File: 178440214
Attention: Mr. Jim Farkas
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources - Stormwater Program
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699
Dear Mr. Farkas,
Reference: Comment Response Letter
This is our response to comments received from your office on July 15, 2020. We have reviewed these
comments and respond in the following manner:
1. Since this project is not claiming vested rights, Section IV, 2b should not be checked off.
Revised
2. The River Basin shown in Section IV, 3 should just be "Tar -Pamlico".
Revised
3. The drainage area information shown in Section IV, 10 should only be an accounting of the areas that
drain directly to the proposed SCMs, not the study points. This is also true for the drainage areas in
the Supplement-EZ Form.
Updated.
4. Please provide additional calculations (Section VI, 7). Additional calculations should include the
following:
a. Since this project drains to a Nutrient Sensitive Watershed (NSW), please provide
calculations showing that the requirements outlined in 15A NCAC 02B .0731 have been
fully addressed.
Used Snap to model Nitrogen and phosphorus annual loading and by utilizing SCMS
such as proposed sandfilters and level spreader filter strips, 15A NCAC 02B .0731
rule has been met.
b. Calculations showing that the inlets and outlets of the proposed SCMs are stable (General
MDC 4).
August 14, 2020
Mr. Jim Farkas
Page 2 of 5
Reference: Comment Response Letter
ST added to the stormwater calculation report. Summary shown
on sheet C-603.
c. Design volume calculations. The design volume should be calculated using either the
Simple Method (For the entire drainage area to the proposed SCM) or the Discrete NRCS
Curve Number Method (Using both the pervious and impervious portions of the entire
drainage area to the proposed SCM). More information can be found in Part B of the
Manual.
Recalculated using the simple method.
d. It was noted during the review that the sum of the areas (square feet) in the post -
construction drainage area 1 a curve number calculation table did not add up properly.
Please ensure that all provided calculations are correct and consistent.
Revised.
5. Please provide plans folded to approximately 8.5" x 14" (Section VI, 8). This is required so that we may
mail an approved plan set to the Applicant with the approved Permit. Plans that do not contain
information pertinent to the review (such as utility sheets, detail sheets, E&SC sheets, etc...) do not
need to be included and the plan sheets can be reduced to 24" x 36" or a comparable size.
Provided.
6. Please dimension the property boundary with bearings and distances (Section VI, 8i).
Property boundary dimensions have been included.
7. Please dimension and/or label all existing, removed, and proposed BUA (Section VI, 8j). The
information shown in the calculations and Application should be verifiable on the plans. You may wish
to provide a table, similar to the one in the Application, breaking down the on -site BUA on each of
these plan sheets. You may also wish to add callouts/labels, similar to the square footage labels on
the buildings on sheet C200, for all BUA areas.
Pre and Post BUA summary sheets and tables added.
8. Please delineate the wetlands on the plans or provide a note stating that no wetlands exist. Provide
documentation of the qualifications and identity of the individual who made this determination (Section
VI, 8m).
Note added to plan. See sheet C001.
9. Please delineate the drainage areas to the proposed SCMs in the main set of plans (Section
Added as sheet C307 in the plan set.
10. Please show the maintenance accesses and easements to the proposed SCMs on the plans (General
MDCs 8&9).
August 14, 2020
Mr. Jim Farkas
Page 3 of 5
Reference: Comment Response Letter
A maintenance access easement area has been identified on the plans. See sheet C300.
11. An SCM cannot be both a sand filter and a dry detention basin at the same time. We do allow sand
filters to be designed with an open bottom and attenuate peak flows so this review was completed
under the assumption that Pond 1 is a sand filter. If this assumption is incorrect, please let me know.
a. Please correct the Supplement-EZ Form and O&M Agreement Form so that Pond 1 is
listed as a sand filter only. Both of these forms will need to be re -signed.
Revised.
b. Please provide a SHWT boring in the area of the proposed sand filter so that separation
from the SHWT can be assessed (Sand Filter MDC 1).
Per Geotech report by Terracon Consultants dated on 0211212020, ground water was
not observed in project test borings.
c. The volume of the sediment chamber and the sand chamber should be equal or close to it
(Sand Filter MDC 2). The sediment chamber can be oversized since the facility is being
designed for peak attenuation (Per the guidance in the Manual), but the sediment chamber
should not be smaller than the sand chamber.
Revised. See plan
d. Please ensure that the treatment volume is calculated correctly (Sand Filter MDC 3, See
earlier comment).
Re -designed and re -calculated. (The provided treatment volume is greater than
added impervious area required)
12. Generally, the State does not require quantity management for stormwater runoff. If Pond 2 is not
needed to meet the requirements of 15A NCAC 02B .0731, then it does not need to be included in the
submission. Since NSW calculations were not provided showing the need for Pond 2, it was not
reviewed for compliance with the MDC. If Pond 2 is needed to meet the NSW requirements, it will be
reviewed for compliance in the next review.
Sandfilter 2 is needed to meet the requirements of 15A NCAC 02B .0731, see SNAP output.
13. Please separate the provided stage -storage table for Pond 1 into sediment chamber and sand
chamber parts so that the storage volume information in the Supplement-EZ Form can be verified.
Stage -storage table for sandfilter 1 and 2 have been separated into sediment chamber and
sand chamber parts.
14. Please correct the following issues with the Supplement-EZ Form:
a. Cover Page:
i. Line 4 — This item should match Section IV, 6 of the Application. Revised
August 14, 2020
Mr. Jim Farkas
Page 4 of 5
Reference: Comment Response Letter
ii. Lines 7-10 — Vegetated setbacks are only required from surface waters. Since no
surface waters are located on or around the project site, these items are not
needed. Revised
iii. Line 22 — See earlier comment. Revised
Drainage Areas Page:
i. Click on the "Click to Load Forms" button to fully load this form.
ii. Line 4 — See earlier comment. Revised
iii. Entire Site Column:
1. There should not be any off -site components to the entire site column
since they are by definition not part of the site.
2. Lines 4 & 17 — 19 are not required. Revised
iv. Drainage Area 1 (Pond 1):
1. Lines 4 & 18 — See earlier comments. Revised
c. Sand Filter Page
i. Line 2 — See prior comment. Revised
ii. Line 3 — This is a general MDC and must be met. Revised
iii. Line 18 — See prior comment. No groundwater observed per Geotech report
iv. Line 31 — The bottom of the sand chamber is the lowest excavated part of the sand
chamber. Based on the provided detail, it appears that this value should be 439.5
ft. Revised
v. Line 33 — This value should be the distance between Line 31 & Line 35 (Temporary
pool elevation). Revised
vi. Lines 35 — 37 — These items are required. Added
vii. Line 38 — This value is the depth of the sand layer above the underdrain pipe.
Based on the provided detail, it appears that this value should be 18 in. Revised
d. General:
i. Make any other corrections to the Supplement-EZ Form as needed due to
addressing any of the earlier comments.
Revised
15. It is recommended to check with Franklin County to see if they should be reviewing this project since
projects in Nutrient Sensitive Watersheds tend to be reviewed by local jurisdictions. The stormwater
permitting interactive map on our website may not be 100% accurate and/or up to date.
Coordination has been made and verified that only NCDEQ review and approval are needed.
16. Provide pdfs of all revisions, 2 hardcopies of revised plan sheets, and 1 hardcopy of other documents.
Pdfs must be uploaded using the form at: htti)s:Hedocs.deg.nc.gov/Forms/SW Project Submittal
Provided.
August 14, 2020
Mr. Jim Farkas
Page 5 of 5
Reference: Comment Response Letter
Regards,
Stain ec SoutcLIlHJ11 g Servuces Ili c
-10 f e
4 00
Jleff II"'Cte Il1:3IIIIIIIIII
Senior Principal
Phone: 678 764 6624
Jeff. Rice@stantec.com
Attachment: Af`f'arhireigl'.
c. C:s C:s
fa document17