July , 2020
TOWN OF NORWOOD
WASTEWATER TREATMENT PLANT RENOVATIONS
EMC SOC WQ S18-011
QUARTERLY REPORT—JULY 2020
Mooresville Regional Supervisor
Division of Water Resources
Water Quality Operations Section
610 East Center Avenue, Suite 301
Mooresville, NC 28115
Water Quality Permitting Section/NPDES
1617 Mail Service Center
Raleigh, North Carolina 27699-1617
Gentlemen:
On August 12, 2019 the Town of Norwood was approved for a State Reserve Loan (SRP) from
the Water Infrastructure Fund in the amount of $4,271,000. The project includes new
headworks, aeration basin weirs, splitter box, clarifiers, sludge pump station, chlorine contact
chamber, and other site improvements. On October 30, 2019 Willis Engineers submitted the
construction drawings and contract documents to DWR for review, which met the November 1,
2019 deadline. Approval by the State was received on July 1, 2020. The project will be
advertised to potential bidders on July 6, 2020 with bids due on August 20, 2020. Construction
is anticipated to begin January 2021.